4.2 Team Selection & Design/Construction Services

Key Takeaways

  • For federal architect-engineer services subject to the Brooks Act, rank qualifications first and negotiate fair and reasonable compensation with the most highly qualified firm.

  • Under federal sealed bidding, responsiveness concerns compliance of the bid and responsibility concerns the bidder’s ability to perform.

  • In AIA B101–2017, Basic Services include three design phases followed by procurement and construction-phase services.

  • The B101 Supplemental Services schedule identifies assigned scopes. Additional Services arise after execution and follow the notice and authorization provisions that apply.

  • In a construction-manager-as-constructor arrangement, early estimating and packaging advice informs design and the parties’ later construction commitment.

Last updated: November 2026

Once the Owner chooses a delivery method, assembling the project team requires selecting a procurement mechanism compatible with project complexity, public statutes, and desired service scope. Clear delineation of Basic Services, Supplemental Services, Additional Services, and preconstruction services prevents scope gaps and fee disputes.

Team Selection Processes

Qualifications-Based Selection (QBS)

Qualifications-Based Selection (QBS) evaluates and ranks design firms strictly on professional competence, relevant project experience, technical capacity, and key personnel. For federal architect-engineer services covered by the Brooks Act (40 U.S.C. §§ 1101–1104), select on qualifications and negotiate compensation after ranking. State and local procedures depend on the jurisdiction.

A federal selection under these provisions follows this sequence:

  1. Publish a public announcement or Request for Qualifications (RFQ) describing project scope.
  2. Evaluate Statements of Qualifications (SOQs) to develop a shortlist of top-qualified firms.
  3. Conduct interviews and rank the shortlisted firms strictly on qualifications.
  4. Negotiate a fair and reasonable fee and detailed scope solely with the top-ranked firm. If negotiations fail, the agency formally ends negotiations with that firm before negotiating with the next most qualified firm. Follow the agency procedure for documenting the decision.

RFQ, RFP, ITB, and Sole-Source Selection

Beyond QBS, Owners rely on four primary procurement tools depending on delivery method and statutory rules:

  • Request for Qualifications (RFQ): Used either as the opening step of QBS or as Phase 1 of a two-step Design-Build or CMAR procurement to prequalify firms based on financial strength, safety record, bonding capacity, and past performance. On construction contracts, Owners frequently collect standardized credentials using AIA A305 (Contractor's Qualification Statement) before issuing bidding or proposal documents to a vetted shortlist.
  • Request for Proposals (RFP): A solicitation for a proposal. Evaluation follows the stated factors, which can include technical approach, past performance, and price or fee. A best-value tradeoff is one possible award approach. In a two-step Design-Build selection, shortlisted teams from the RFQ receive Owner's Project Criteria and submit competitive technical and price proposals under the RFP.
  • Invitation to Bid (ITB): Competitive sealed bidding used predominantly for DBB construction once CDs are complete. Under federal sealed bidding, award is made to the responsible bidder whose responsive bid is most advantageous under price and price-related factors specified in the invitation. A responsive bid conforms in all material respects to the Bidding Requirements (no unauthorized qualifications, proper bid security, signed forms), whereas a responsible bidder demonstrates the financial resources, experience, integrity, and bonding capacity to perform the work.
  • Sole-Source Selection: Direct selection of a single firm without competition. For example, a private owner may negotiate with an incumbent firm. When federal competition rules apply, another-than-full-and-open procedure needs an applicable authority and supporting documentation, such as circumstances in FAR Subpart 6.3.
Selection MethodPrimary Selection BasisRole of Price at SelectionCommon Project Application
QBSCompetence, experience, and qualificationsNegotiated only after ranking top firmPublic and private A/E design contracts
RFQCredentials, capacity, and past performanceExcluded (screening step only)Phase 1 shortlisting for QBS, CMAR, or DB
RFPFactors published in the solicitationEvaluated as stated by the solicitation and governing rulesCMAR and Design-Build best-value award
ITBResponsive bid by a responsible bidderFederal comparison uses price and stated price-related factorsDBB construction with complete CDs
Sole-SourceExisting relationship or unique capabilityNegotiated directly with chosen firmPrivate work or public emergency/proprietary cases

Design and Construction Services

A/E Basic Services

Under standard agreements such as AIA B101–2017, Basic Services encompass five phases in the standard owner–architect agreement. Confirm the scope in the executed document:

  1. Schematic Design (SD): Establishes conceptual site layout, spatial relationships, massing, preliminary structural and Mechanical, Electrical, and Plumbing (MEP) systems, and an initial estimate of the Cost of the Work.
  2. Design Development (DD): Refines architectural plans, structural framing, MEP sizing, outline specifications, and an updated cost estimate to fix overall project character.
  3. Construction Documents (CD): Develops coordinated drawings and specifications. Confirm who prepares the procurement requirements and contracting forms for the project manual.
  4. Procurement (Bidding or Negotiation): Assists the Owner with distributing bid packages, preparing addenda, evaluating bids or proposals, and assisting with award. Substitution evaluation depends on the procurement scope and procedures.
  5. Construction Contract Administration (CCA): Includes periodic site observation visits (not continuous inspection), reviewing submittals and shop drawings, evaluating payment applications, issuing certificates for payment, preparing change instruments, responding to requests for information, and conducting Substantial Completion and Final Completion inspections.

A/E Supplemental and Additional Services

Services outside Basic Services fall into two distinct contractual categories:

  • Supplemental Services: Scopes identified and allocated in the agreement. Under B101–2017 Article 4, assign them to the architect or owner as applicable, with a scope description and agreed compensation for the architect’s work. Common examples include architectural programming, measured surveys of existing facilities, detailed Building Information Modeling (BIM) coordination for facility operations, Leadership in Energy and Environmental Design (LEED) certification administration, full-time on-site project representation, commissioning support, and post-occupancy evaluations.
  • Additional Services: Services arising after agreement execution. Some require prior written authorization, while the agreement can require prompt performance and notice in certain situations to avoid construction delay. Typical triggers include major Owner-directed redesigns after phase approval, evaluating an excessive number of contractor substitution requests, extending CCA due to prolonged contractor delays, or preparing documents to repair casualty damage.

CMAR and Contractor Preconstruction Services

In CMAR and negotiated engagements, the constructor provides formal preconstruction services during SD, DD, and CD as agreed, including before setting a GMP where one is used. Key deliverables include real-time market cost estimating grounded in current subcontractor pricing, constructability reviews assessing sequencing, site logistics, crane access, and detail buildability, Value Engineering (VE)—analyzing component function versus life-cycle cost to eliminate unnecessary expense without sacrificing performance—and developing early procurement packages for long-lead equipment such as switchgear or chillers.

Match the agreement to the requested service

A renovation may need a firm with comparable occupied-building work, staff who can manage phased approvals, and the financial and staffing capacity to handle concurrent packages. Check references for how the firm worked with design and construction partners. The price of the service matters at the stage permitted by the procurement process. Examples of documentation by delivery model include AIA B101 for owner–architect services, EJCDC E-500 for owner–engineer services, AIA C132 for owner–CM adviser services, and DBIA 544 for a progressive design–build team. In a project using EJCDC’s CMAR series, CMAR-500 governs the owner–engineer relationship and CMAR-525 governs the owner–constructor relationship. Compare the services and responsibilities allocated by each agreement before filling gaps with additional scopes.

References Brooks Act negotiation, 40 U.S.C. § 1104, FAR Part 14, FAR Part 36, AIA A305–2020, AIA B101–2017 instructions, and EJCDC document families.

Test Your Knowledge

During a federal A/E procurement governed by the Brooks Act, the Owner's selection committee cannot reach an acceptable fee agreement with the highest-ranked firm. What is the required next step?

A

Solicit sealed fee bids from all shortlisted firms and award to the lowest price

B

Reopen negotiations with the first firm while simultaneously negotiating with the second-ranked firm

C

Formally end negotiations with the highest-ranked firm, then negotiate with the next most qualified firm.

D

Cancel the QBS process and issue an Invitation to Bid (ITB) for design services

Test Your Knowledge

In a federal sealed bid governed by FAR Part 14, the solicitation requires liquidated damages. The low bidder attaches a letter disclaiming that provision. How should the contracting officer classify the bid?

A

Non-responsive, because the bidder altered a material term of the Bidding Requirements

B

Non-responsible, because the bidder lacks adequate bonding capacity

C

Responsive and responsible, because the bidder offered the lowest price

D

Eligible for sole-source negotiation to remove the exception

Test Your Knowledge

The parties assign measured drawings of existing conditions and AIA E204 sustainability services to the architect in the Article 4.1 schedule of AIA B101–2017. How are those services classified?

A

Basic Services included automatically in Schematic Design and Construction Documents

B

Additional Services triggered unexpectedly during Construction Contract Administration

C

Preconstruction Services assigned to the CMAR under a separate GMP

D

Supplemental Services assigned in the signed agreement outside Basic Services.