8.2 SectionFormat: Organizing Part 1, Part 2 & Part 3
Key Takeaways
SectionFormat organizes a specification into Part 1 General, Part 2 Products, and Part 3 Execution.
Division 01 can use the same structure. Follow the project’s convention for unused parts.
Distinguish the purpose of a mockup, source testing, field testing, and submittal evidence when placing requirements.
Examination verifies that conditions are suitable. Preparation makes them suitable for installation.
While MasterFormat determines where each section sits inside the Project Manual, CSI SectionFormat provides a consistent way to organize requirements within a specification section. By assigning each topic to one canonical home across three standardized parts—Part 1 – General, Part 2 – Products, and Part 3 – Execution—SectionFormat reduces the risk of omissions and duplicate requirements and lets estimators, superintendents, and inspectors locate requirements predictably.
Use the three-part framework for technical specifications and adapt the content to the work. In Division 01 (General Requirements), a procedural section may use one part for most requirements. Sections covering physical or site work, such as temporary facilities or final cleaning, may need product or execution requirements. For example, the UFGS Format Standard § 2-1.1 directs authors to retain a part and mark it “Not used” if empty.
Part 1 – General: Administrative and Procedural Scope
Part 1 defines the administrative, procedural, and quality framework specific to the section without duplicating broad rules already stated in Division 01:
- Summary: Identifies work included in the section, products furnished but not installed (or vice versa), and Related Requirements (cross-referencing related sections by number and title rather than repeating their provisions).
- Price and Payment Procedures: Specifies unit prices, allowances (for example, a $25,000 hardware allowance), or measurement/payment rules only when unique to that section.
- Administrative Requirements: Covers trade coordination, preinstallation meetings, and mandatory sequencing.
- Submittals: Organizes required submissions into standard categories: action submittals (product data, shop drawings, samples requiring A/E review), informational submittals (certificates, test reports, installer qualifications), closeout submittals (operation and maintenance manuals, executed warranties), and maintenance material submittals (extra stock or attic stock).
- Quality Assurance: Establishes manufacturer, fabricator, and installer qualifications, regulatory certifications, and mockups. A mockup that establishes a benchmark can be specified under Part 1 Quality Assurance. UFGS 04 20 00 § 1.3.1 provides an example with mockup location, composition and acceptance purpose. A related installation or test provision can cross-reference the benchmark.
- Delivery, Storage, and Handling: Governs packaging, receiving inspections, environmental protection during storage, and rigging precautions.
- Field Conditions: States ambient temperature, relative humidity, and substrate moisture limits required during installation.
- Warranty: Specifies special or extended warranties (such as a 20-year roofing membrane warranty) with the required term, scope and documents. Coordinate any special warranty with the general warranty and correction provisions of the applicable contract. A written special warranty and a general correction period serve distinct purposes.
Part 2 – Products: Materials, Fabrication, and Source Quality Control
Part 2 specifies materials, equipment, fabrication, and related tests. Product criteria can apply to things mixed or assembled on site as well as factory products:
- Manufacturers / Named Products: Lists acceptable manufacturers, basis-of-design products, and section-specific substitution references (deferring substitution procedures to Division 01).
- Performance / Design Criteria: Defines structural loads, thermal values, acoustic ratings, or operational metrics, particularly for delegated design systems.
- Materials, Equipment, Components, and Accessories: Details base materials (often citing ASTM or ANSI standards), major equipment, fasteners, anchors, adhesives, sealants, and trim.
- Mixes: Specifies proportions and mix-design criteria for site- or plant-batched materials such as concrete, mortar, grout, or plaster.
- Fabrication and Finishes: Controls shop assembly tolerances, shop welding, shop-applied primers, and factory finishes or color selections.
- Source Quality Control: Covers factory, mill, or fabrication-plant testing and inspection performed at the source—such as witness testing of electrical switchgear at the factory or ultrasonic weld testing in a steel fabrication shop.
Part 3 – Execution: Site Preparation, Installation, and Closeout
Part 3 defines site work for the section, from examination through protection:
- Examination: Requires the installer to inspect substrates, dimensions, and field conditions before starting work and report unsuitable conditions as the contract and specification require. Follow the stated notice and correction procedure before proceeding.
- Preparation: Covers cleaning, scarifying, priming, layout, and protecting adjacent existing or completed work prior to application.
- Installation / Erection / Application: SectionFormat tailors the primary work article verb to the trade—Installation for equipment and assemblies, Erection for structural steel or precast framing, and Application for coatings, roofing, and finishes—referencing manufacturer instructions and acceptable tolerances.
- Field Quality Control: Specifies on-site testing, inspections, special inspections, and correction of nonconforming work—such as field concrete slump and cylinder testing or curtain-wall field water-penetration testing.
- Repair / Restoration, Reinstallation, Adjusting, and Cleaning: Addresses remediation of damaged surfaces, reinstallation of salvaged items, operational calibration or HVAC balancing, and post-installation cleanup.
- Closeout Activities and Protection: Covers owner demonstration and staff training, followed by Protection of completed work against damage for the period defined by the specification and contract.
Practical Placement Rules for Specifiers
Place a mockup benchmark with the section’s quality assurance requirements. Put test conditions with the work or stage they verify. For a curtain wall, distinguish factory product testing, field testing after installation, and the submittal of reports for both. For site work, describe the protection of adjacent finishes during preparation and protection of the newly installed surface after installation. The article depends on what the instruction is meant to accomplish.
| SectionFormat Part | Core Focus | Representative Standard Articles |
|---|---|---|
| Part 1 – General | Administrative, procedural, quality benchmarks, and special warranties | Summary, Price and Payment Procedures, Administrative Requirements, Submittals, Quality Assurance (including Mockups), Delivery/Storage/Handling, Field Conditions, Warranty |
| Part 2 – Products | Materials, equipment, shop fabrication, and off-site testing | Manufacturers, Performance/Design Criteria, Materials, Equipment, Components, Accessories, Mixes, Fabrication, Finishes, Source Quality Control |
| Part 3 – Execution | On-site verification, installation, field testing, closeout, and protection | Examination, Preparation, Installation/Erection/Application, Field Quality Control, Repair/Restoration, Adjusting, Cleaning, Closeout Activities, Protection |
References CSI SectionFormat/PageFormat, UFS 1-300-02 §§ 2-1.1 and Appendix A, and UFGS 04 20 00 masonry mockup.
A masonry specification uses a mockup panel to establish the benchmark workmanship before production. In the section layout illustrated by UFGS 04 20 00, where is that requirement placed?
Part 2 - Products, under Fabrication
Part 3 - Execution, under Installation
Part 1 - General, under Quality Assurance
Part 3 - Execution, under Field Quality Control
A specification uses separate Part 2 Source Quality Control and Part 3 Field Quality Control articles. Which article defines a factory witness test of custom switchgear before shipment?
Part 2 - Products, under Source Quality Control
Part 3 - Execution, under Field Quality Control
Part 1 - General, under Submittals
Part 3 - Execution, under Closeout Activities
A tile installer must check the existing slab against the specified flatness, cleanliness, and moisture criteria before installation and report deficiencies. Which article should describe this verification step?
Part 1 - General, under Field Conditions
Part 2 - Products, under Performance Criteria
Part 3 - Execution, under Preparation
Part 3 - Execution, under Examination