11.1 Competitive Bidding Process & Document Availability
Key Takeaways
Use the issued solicitation to identify bid availability, delivery, and evaluation rules.
Distribute amendments through the authorized channel and price the current bid set.
Responsiveness concerns material terms in the offer. Responsibility concerns the bidder’s ability and eligibility to perform.
AIA A701–2018 and federal sealed bidding use different procedures for correcting or withdrawing bids.
Identify the rules before pricing
The procurement package includes the solicitation, bidding instructions and forms, proposed agreement and conditions, drawings, specifications, and relevant project information. Check who can bid and what the solicitation asks the bidder to submit. Follow every current revision through estimating, signing, and delivery.
Public entities use procurement rules that depend on the jurisdiction, funding, and authorized award method. For example, FAR Part 14 federal sealed bidding uses publicized invitations, sealed bids, public opening, evaluation without discussions, and award to a responsible bidder with a responsive bid most advantageous to the government considering only price and stated price-related factors. A private owner may invite prequalified firms and set different rules for receiving and evaluating offers. Where a private solicitation incorporates AIA A701–2018, read Article 5 and project-specific instructions. The A701 default states an intent to award to the lowest responsive and responsible bidder, subject to the applicable terms and law.
Keep a complete bidding set available
State where bidders obtain documents, whether they can download or inspect them, what fees or deposits apply, and where official notices appear. A digital plan room can publish a common issue and maintain a list of recipients. Printed sets can also be used. A701 § 3.1 requires use of the complete set. An A701 project can provide documents directly to sub-bidders if the solicitation or supplementary instructions offers that option. Otherwise, prime bidders should convey applicable requirements and addenda when requesting trade prices.
At a pre-bid meeting or site walk, bidders can identify access constraints, utility shutdowns, work hours, and conditions that affect pricing. The solicitation defines attendance rules. For A701 § 3.2, submit written inquiries through the required channel. Under that form, an official change or interpretation is made by addendum. Under FAR 14.208, the contracting officer must amend the invitation where warranted even if a change was discussed at a pre-bid conference. Check the current set after the meeting.
Complete and compare the bids
A common bid form can require base price, unit prices, separately stated alternates, the bidder’s signature, bid security, and acknowledgments. Under A701 § 4.1.3, words control discrepancies between words and figures when the form uses both under the default rule. Check the actual form before using that rule. Calculate and submit the bid security in the form and amount required. If a solicitation requires 5% on an illustrative $2,000,000 base bid, the security is $100,000. Check whether the effective base includes alternates and how long the offer must remain open.
Bid security supports obligations such as entering the agreement and supplying required bonds after selection. The solicitation and bond terms specify the conditions and limit. AIA A310–2010 is a bid bond form. Performance and payment bonds serve different functions after selection and their required amounts come from the governing terms. Use the stated submission deadline, platform or address. Federal late-bid treatment has limited exceptions under FAR 14.304. An A701 bid received after the date and time or at an incorrect place is not accepted under § 4.3.3.
| Evaluation question | Evidence to examine |
|---|---|
| Is the bid responsive? | Material requirements, required signatures and security, acknowledgment of material addenda, exceptions and qualifications |
| Is the bidder responsible? | Applicable financial capacity, resources, ability to meet schedule, integrity, work history and eligibility |
| Can an irregularity be cured? | Authorized procedure and effect on price, quantity, quality, delivery and bidder equality |
For example, an unacknowledged federal amendment adding material scope generally makes the bid nonresponsive. A small defect can be a minor informality under FAR 14.405, with limited exceptions for amendment acknowledgment as stated in that provision. In federal bidding, the requirement to reject for an inadequate bid guarantee is subject to the exceptions in FAR 28.101-4. Being capable of doing the work does not cure a material qualification in the offer.
Handle an alleged mistake under the actual rule
Under AIA A701–2018 § 4.4, bidders can replace or withdraw bids using the specified notice before the deadline. After the deadline, § 4.4.3 allows a bidder with a clerical error to request withdrawal within two days, or within the period specified by applicable law. When the bidder provides evidence reasonably satisfactory to the architect, the bid is withdrawn without resubmission. The form leaves the treatment of bid security to terms filled in for the project.
Under FAR 14.407-2 and 14.407-3, there are distinct procedures for apparent clerical mistakes and other mistakes raised before award. The contracting officer can verify an apparent error on the face of the bid. Correcting other mistakes requires the prescribed determination and evidence of the mistake and actual intended bid, with added constraints when correction would displace lower bids. Withdrawal can be available when the rule’s evidence requirements are satisfied. Neither a correction request nor a withdrawal request is an opportunity to bargain about a bid.
References AIA A701–2018 Articles 3–5, AIA A310–2010, FAR Part 14, FAR 9.104-1, and FAR 28.101-4.
A project uses unmodified AIA A701–2018. At a site walk, the architect says an existing chiller can remain, though the bidding documents require replacement. There is no addendum changing the requirement. How should bidders prepare the bid?
Exclude replacement based on the site discussion.
Qualify the bid to exclude the chiller.
Price replacement as required by the issued documents and use the written inquiry procedure for clarification.
Modify the bid bond instead of addressing the scope.
In federal sealed bidding, a capable firm submits the lowest price but does not acknowledge an amendment adding substantial structural steel. The bid contains no other evidence it received that amendment. How should the omission be classified?
A material responsiveness defect in the bid.
A reservation bearing only on the firm’s responsibility.
A minor informality because the bidder is otherwise qualified.
An opening for price negotiations with only that bidder.
On a project using unmodified AIA A701–2018, the bidder submits a timely request after opening and proves a clerical totaling error to the architect’s reasonable satisfaction. The bid security fill-point has project-specific terms. What does § 4.4.3 provide?
Automatic correction to whatever new price the bidder proposes.
No relief once the bids are opened.
Acceptance at the original price with reimbursement from the owner’s contingency.
Withdrawal without resubmission, with bid security handled under the filled-in terms.