8.3 PageFormat: Text Hierarchy, Layout & Numbering
Key Takeaways
PageFormat guides margins, contents of the page, and identification of articles, paragraphs, and subparagraphs.
Section-relative page identifiers help isolate and detect changes to individual sections.
A closing marker identifies the intended end. Check the sequence and issue record to detect missing or stale pages.
Use the section and the full identifier, plus revision information where useful, to cite a requirement.
MasterFormat organizes the Project Manual by work results, and SectionFormat organizes each section into three parts. CSI PageFormat completes the trio by standardizing the physical and electronic layout of each page—margins, running headers and footers, typography, section-relative page numbering, and alphanumeric text hierarchy. Consistent page design helps readers locate requirements and compare revisions.
Page Geometry, Headers, Footers, and Margins
CSI’s recommended layout covers margins and page designations. Use the owner’s publishing requirements and check printed and electronic copies. Leave binding room where the project expects printed copies. Keep document identifiers distinct from requirements.
- Page identifiers can include the project, issue, and specification section. The location of those identifiers varies. A transit district’s published Terminal 2 project manual places the project identifier, section and page identifier, and project name in its footer.
- Section title identifies the number and subject at the beginning of a section. A consistent title helps readers match the table of contents, specification, and cross-references.
- Consistent typography and indents help a reviewer distinguish a heading from subordinate requirements. Use visible hierarchy and clear page breaks to keep lists together where feasible.
Section-Relative Pagination and End-of-Section Markers
In a Project Manual containing hundreds of pages, a single running page number can make revisions cumbersome. Specifications are routinely modified during bidding through Addenda and during construction through Modifications (such as Change Orders or Construction Change Directives). Under continuous numbering, expanding a single section by two pages forces renumbering—and potentially reissuing—every subsequent section in the manual.
Section-relative pagination solves this problem by starting every section at page 1 (03 30 00 - 1, 03 30 00 - 2, and so on). An addendum can replace the affected section without changing the local page numbers of unrelated sections. Verify which pages or full sections the issuer actually replaced.
A visible closing marker, such as END OF SECTION 01 23 00 in the Terminal 2 project manual, distinguishes the intended end of the section from a page break. An end marker cannot reveal every missing interior page or prove the entire issue is current. Compare page sequence, the index, and the issue or addendum record before using the set.
Alphanumeric Text Hierarchy and Citation Precision
To make every sentence uniquely addressable without relying on shifting page numbers, a project needs consistent article and paragraph designations. The example below uses an alphanumeric convention common in project specifications. Agency formats can use other consistent conventions, such as the numeric nesting used in UFGS.
| Hierarchy Level | Illustrative Identifier | Role in This Example | Example |
|---|---|---|---|
| Section Heading | SECTION XX YY ZZ - TITLE | Identifies the start of a section | SECTION 03 30 00 - CAST-IN-PLACE CONCRETE |
| Part | PART 1 -, PART 2 -, PART 3 - | Divides the section into parts | PART 1 - GENERAL |
| Article | 1.01 (or 1.1) | Names a requirement category within a part | 1.01 SUMMARY |
| Paragraph | A., B., C. | Uppercase letter, first indent level | A. Section Includes: |
| Subparagraph | 1., 2., 3. | Arabic numeral, second indent level | 1. Cast-in-place concrete footings. |
| Sub-subparagraph | a., b., c. | Lowercase letter, third indent level | a. Normalweight concrete, 4,000 psi. |
| Further Levels | 1), then a) | Numerals/letters with closing parenthesis (use sparingly) | 1) Maximum water-cementitious ratio 0.45. |
Long chains of nested clauses are hard to use. If a requirement needs several levels, consider a separate article where readers can find it. Cite the section and full identifier when asking for clarification or recording a response. A page number is useful for finding a location within one issue, but it may shift in a revision.
Track an addendum through the issue
If a new clause changes the vapor retarder scope, the issuer can direct replacement of the precise paragraph or release a revised section. In the example below, cite Section 03 30 00, 1.01.A.1.b.1) to identify that clause. Check the addendum date and item, confirm receipt where the solicitation requires acknowledgment, and verify that related details, bid forms, and section references reflect the same change. Keep superseded pages out of the pricing set.
PageFormat Worked Example
SECTION 03 30 00 - CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1. Cast-in-place concrete, including formwork, reinforcement, concrete
materials, mixture design, placement procedures, and finishes:
a. Footings and foundation walls.
b. Slabs-on-grade.
1) Vapor retarder beneath interior slabs-on-grade.
1.02 RELATED REQUIREMENTS
A. Section 03 10 00 - Concrete Forming and Accessories.
[... Parts 2 and 3 follow in identical hierarchy ...]
END OF SECTION
References CSI PageFormat scope, Santa Barbara MTD Terminal 2 project manual, Section 01 23 00, and UFGS tile example.
What does section-relative pagination such as 01 23 00 - 2 accomplish when the procurement team replaces one specification section by addendum?
To allow estimators to calculate total Project Manual page counts directly from the Table of Contents
It lets the issuer replace that section while preserving the section-relative page numbers of the other sections.
To satisfy building code requirements that mandate resetting page numbers at every division boundary
To replace alphanumeric article numbers when referencing specifications in Requests for Information
Using the alphanumeric hierarchy shown in the example, what is the descending sequence beneath Article 2.01?
1., A., a., 1)
a., A., 1., a)
A., 1., a., 1)
A., a., 1., 1)
Sections you finish are checked off in the contents.