5.1 Schematic Design & Design Development Documentation
Key Takeaways
Schematic design explores spatial relationships, initial systems, and site arrangement. A preliminary project description can record early decisions by functional element.
Design development describes the size and character of the selected design through developed drawings, system layouts, outline specifications, and an updated estimate.
Under AIA B101–2017 Article 3, owner approval supports the transition from schematic design to design development and from design development to construction documents.
The design team’s Basis of Design explains how design assumptions and system selections address the Owner’s Project Requirements. It can develop across design submissions.
After the program defines the owner’s needs, the design team develops and tests a physical response. A building project under American Institute of Architects (AIA) B101–2017 Article 3 progresses through schematic design (SD), design development (DD), and construction documents (CD). Engineering services under Engineers Joint Contract Documents Committee (EJCDC) E-500–2020 may use a preliminary and final design sequence instead. Match the deliverable and approval process to the governing agreement.
On a project with commissioning, distinguish the Owner’s Project Requirements (OPR), which provide the owner’s expectations, from the design team’s Basis of Design (BoD), which records the technical response. Update these records as decisions develop and trace the effects through the relevant deliverables.
Schematic Design (SD): Exploring and Confirming the Concept
The primary objective of Schematic Design (SD) is to translate the approved architectural program and OPR into clear visual and written concepts. Rather than rushing into granular construction details, the Design Team (the architect and consulting engineers) tests massing, site orientation, and functional relationships so the Owner can compare viable schemes and confirm overall project direction.
Key Schematic Design Deliverables
- Conceptual Drawings: Include a conceptual site plan (showing building placement, parking, access drives, and major utility entry points), conceptual floor plans, departmental adjacency diagrams, pedestrian and service circulation studies, exterior massing studies, and preliminary elevations or building sections.
- Preliminary Structural and MEP Concepts: Narrative descriptions or single-line diagrams identifying candidate framing systems (such as structural steel, cast-in-place concrete, or mass timber) and mechanical, electrical, and plumbing (MEP) system approaches without finalizing individual equipment schedules.
- Preliminary Project Description (PPD): A concise written narrative often organized by UniFormat functional elements such as the shell, interiors, or building services. Using UniFormat allows the team to describe qualitative building systems—such as curtain wall versus punched openings—before individual products or MasterFormat specification sections are selected.
- SD Cost Estimate: An estimate may use elemental or assemblies-level quantities linked to the PPD. It tests the proposed scope against the construction budget and exposes assumptions that require more definition.
- Alternative Scheme Comparisons: Where multiple site layouts or building configurations satisfy the program, the Design Team presents side-by-side evaluations of spatial efficiency, constructability, schedule impact, and relative cost.
At the close of SD, the design team submits the schematic package and estimate as required by the agreement. Record the owner’s approval and the conditions attached to it. Approval identifies the concept to develop and the outstanding decisions to carry into the next phase.
Design Development (DD): Locking In Systems and Character
Design Development (DD) takes the approved schematic concept and defines the size, character, and technical integration of the entire facility. The Design Development Documents show the major spatial dimensions, planned structural and enclosure systems, and building services arrangements at sufficient detail for the owner to make informed decisions and for the team to coordinate subsequent detailing.
Key Design Development Deliverables
- Dimensioned Drawings: Dimensioned floor plans, building sections, and exterior elevations; enlarged layouts for complex spaces such as restrooms, kitchens, or laboratories; reflected ceiling concepts; and coordinated structural and MEP plans.
- System Sizing and Routing: Structural framing sizes (column grids, beam depths, slab thicknesses, and lateral-force resisting systems) and MEP equipment sizing and routing (chiller and air-handler footprints, mechanical shaft sizes, plenum depth clearances, main ductwork and piping runs, and electrical room dimensions).
- Basis of Design (BoD): On a commissioned project the design professionals develop this record of the design response to the OPR. It describes relevant code and design assumptions, system selections, controls, and integration. Update it with design submissions so reviews and testing can trace the requirements.
- Outline Specifications: Written descriptions of major materials, systems, and general quality levels. A work-result outline can use MasterFormat numbering and titles. Outline Specifications identify major materials, performance benchmarks, and preferred equipment types without yet expanding into full three-part SectionFormat specification text.
- Preliminary Schedules: Early door, finish, hardware, plumbing fixture, lighting, and specialized equipment schedules establishing unit counts and performance classes.
- Updated DD Cost Estimate: A semi-detailed systems estimate incorporating measured quantities from dimensioned drawings and vendor budget quotes, to check the developing scope against the owner’s construction budget.
Transitioning to Construction Documents (CD)
During construction documents (CD), the team details the approved design and coordinates the drawings and specifications for the planned release. The project manual can organize specifications using MasterFormat, SectionFormat, and PageFormat. Check which documents are incorporated into the construction agreement when determining the enforceable scope.
Use DD approval as a baseline. For example, a change in floor-to-floor height after approval can affect stairs, shaft coordination, façade details, and structure. Document the owner’s decision and update the affected drawings, specifications, estimate, and schedule. Leave a clear record of unresolved interfaces and when they must be settled.
Comparison of Design Phase Deliverables and Sign-Off Gates
| Phase | Primary Purpose | Core Drawings | Written Technical Documents | Cost Estimate Basis | Owner Sign-Off Gate |
|---|---|---|---|---|---|
| Schematic Design (SD) | Confirm spatial concept, scale, and general systems | Conceptual site plan, floor plans, adjacencies, massing, preliminary elevations | Preliminary Project Description (PPD) organized by UniFormat; system narratives | Elemental / assemblies estimate keyed to UniFormat elements | Owner approval of schematic package and direction |
| Design Development (DD) | Fix size, character, structural/MEP integration, and materials | Dimensioned plans, sections, elevations, enlarged rooms, coordinated framing and MEP routing | Updated BoD where applicable, outline specifications, preliminary schedules | Semi-detailed systems estimate with measured quantities and vendor quotes | Owner approval of developed design and baseline decisions |
| Construction Documents (CD) | Detail, coordinate, and specify work for permitting and construction | Final dimensioned working drawings, construction details, schedules, and code diagrams | Full Project Manual (procurement, contracting requirements, three-part MasterFormat specs) | Detailed unit-by-unit quantity takeoff estimate by MasterFormat | Approval and release process set by the project agreement |
References AIA B101–2017 Article 3, EJCDC E-500–2020 Exhibit A changes, CSI PPDFormat, and WBDG commissioning documents.
Which early written deliverable describes proposed system functions and assemblies and can be organized by UniFormat?
Project Manual
Preliminary Project Description (PPD)
Outline Specifications
Record Drawings
What is the purpose of a Basis of Design on a commissioned project?
To replace the Owner-Contractor Agreement for fast-track delivery
To establish final unit-price quantities for competitive bidding
To serve as the contractor's binding shop drawing submittal schedule
To document the technical assumptions, codes, and system selections satisfying the Owner's Project Requirements
Why seek owner approval of Design Development Documents before advancing the construction documents under AIA B101–2017?
Establish an approved baseline for developing and coordinating detailed requirements.
To transfer statutory building-code compliance liability from the architect to the Owner
To eliminate the need for contractor submittals and shop drawings during construction
To waive the contractor's right to issue Requests for Information during bidding