14.3 Site Visits, Observations, Inspections & Stopping the Work
Key Takeaways
Under A201 § 4.2.2 the architect visits periodically to evaluate general progress, quality and conformance.
Code inspections and special inspections follow adopted requirements and the authority having jurisdiction.
AIA A201 § 4.2.6 and EJCDC C-700 §§ 10.04 and 14.03 address rejection of nonconforming or defective work.
Owner stop-work authority follows AIA A201 § 2.4 or EJCDC C-700 § 14.06 and is distinct from enforcement or safety action.
Observe performance under the contract
AIA A201–2017 § 4.2.2 calls for site visits appropriate to the stage of construction or as otherwise agreed with the owner. The architect becomes generally familiar with progress and quality and determines in general whether observed work indicates that the completed work will comply. The clause does not require exhaustive or continuous inspections. Under § 4.2.3, report known deviations from the contract and the last submitted schedule, and observed defects and deficiencies to the owner. A field report can record the location, observation, condition to verify and follow-up.
A separate service such as AIA B207–2017 can provide on-site project representation. The architect can also conduct the completion inspections assigned by A201 § 4.2.9. These activities have different stated purposes. Check the agreements and required frequency before treating any visit as comprehensive verification or transferring the contractor’s supervision and safety duties.
Follow adopted inspection requirements
A building official or another authority having jurisdiction administers regulatory inspections and permits. The applicable code and local amendments set which work must be inspected before concealment and what approval is needed for occupancy. Check who requests inspection, which work is ready and accessible, and whether work can proceed after findings.
In jurisdictions using 2024 IBC Chapter 17 without a different local rule, for work requiring special inspections under § 1704.2, the owner or authorized agent other than the contractor generally employs approved agencies, subject to the code’s exceptions. The statement of special inspections and § 1705 identify applicable items and whether checks are periodic or continuous. Examples can include structural steel, concrete or designated fire-resistive work under their respective provisions. The agency keeps records and submits reports as required by § 1704.2.4. A scheduled special inspection and a routine building inspection can both be required.
Identify the authority for the action
| Function | Source and responsible party | Action |
|---|---|---|
| Periodic visit under A201 § 4.2.2 | Architect | Observe progress and general quality, follow up and report |
| Regulatory inspection | Authority having jurisdiction or its authorized personnel | Apply adopted code and required approvals |
| Special inspection under 2024 IBC Chapter 17, where adopted | Approved agency | Inspect or test listed work and report the results |
| Reject nonconforming or defective work | A201 architect or C-700 engineer, under the specific clauses | Identify affected work and apply correction, testing or evaluation procedures |
| Contractual stop-work remedy | Owner under the applicable general conditions | Issue the order within the authority and grounds specified |
Under A201 § 4.2.6, the architect can reject nonconforming work and require testing or inspection in accord with §§ 13.4.2–13.4.3. Under § 2.4, the owner can issue a written order stopping the work or part of it if the contractor fails to correct nonconforming work as required by § 12.2 or repeatedly fails to carry out the work according to the documents. The remedy is separate from suspension for convenience and from safety actions by the contractor or statutory authority.
Under EJCDC C-700–2018 §§ 10.04 and 14.03, the engineer’s rejection authority is distinct from the owner’s stop-work authority under § 14.06. The latter also addresses insufficient skilled workers, unsuitable materials or equipment, and performance that will not yield conforming work. Section 14.05 addresses uncovering and additional inspection or testing. Read the project’s applicable amendments before choosing the instruction.
For a suspected reinforcement discrepancy, identify the actual location and governing detail, route the finding through the contract, and verify any inspection requirement before concealment. If the issue calls for a stop order, identify the issuer and basis. A stop order and correction of the affected work can have different scopes and conditions for resumption.
Check the evidence behind a finding
During a site visit, the architect sees a portion of a weld obscured by another element. The observation identifies what is visible and flags the area to follow up. Check the inspection statement and contract to determine whether an approved agency must examine the weld and who gives readiness notice. Keep the architect’s report and the agency’s findings distinguishable and use the applicable rejection or corrective procedure if the findings show nonconformance.
References AIA A201–2017 §§ 2.4, 4.2.2–4.2.3, 4.2.6, and 4.2.9, AIA B207–2017, 2024 IBC Chapter 17, and EJCDC C-700 base §§ 10.04 and 14.03–14.06.
An architect finds that installed masonry reinforcement fails to meet the A201–2017 Contract Documents. What does § 4.2.6 authorize?
Take over field supervision.
Cancel all subcontract agreements.
Unilaterally accept the work and negotiate a deduction for the owner.
Reject the nonconforming work and require inspection or testing under the applicable provisions.
Under unmodified AIA A201–2017 § 2.4, who can issue a written stop-work order when the contractor has failed to correct nonconforming work as required?
Architect acting independently under § 4.2.6.
Owner, for the work or portion covered by the order.
Special inspector acting solely under the contract.
Surety on receipt of a field report.
A contract uses A201–2017, and the jurisdiction adopts 2024 IBC Chapter 17 for designated portions. What is the difference between the architect’s ordinary site visits and required special inspections?
Periodic architect visits assess progress and general quality. An approved agency separately performs the special inspections required for designated work.
Every architect visit is continuous inspection of all work.
Special inspections replace building official inspections and the contractor’s quality control.
Both automatically transfer contractor safety duties to the observers.
Sections you finish are checked off in the contents.