10.1 Hierarchy of Requirements & Construction Warranties

Key Takeaways

  • Classify requirements by their function and check the executed agreement, modifications, and applicable conflict provisions.

  • AIA A201–2017 makes Contract Documents complementary. FAR 52.236-21 gives specifications priority over drawings when the contract includes that clause and still requires submission of discrepancies.

  • AIA A201 separates the obligation to provide conforming work from the one-year correction obligation. Notice and opportunity to correct matter.

  • EJCDC C-700–2018 contains different correction and warranty notice terms. Check the specific contract for repair extensions and claim timing.

  • Track each special warranty using the contract’s start trigger, written warranty terms, and notice requirements.

Last updated: November 2026

Follow the purpose of a requirement

Start with the executed agreement and its list of incorporated documents. It establishes terms such as the parties, price, time, and documents used for performance. General conditions allocate rights and duties, and supplementary conditions revise or supplement their clauses. An incorporated addendum can affect the requirements in place at execution. A valid modification can change those requirements afterward. Review the effective documents and dates before deciding what governs.

Division 01 commonly states procedures and controls shared across work results. Technical sections and drawings give work-specific criteria and geometry. For example, the general conditions can establish how the architect reviews submittals. Division 01 can set a submission and tracking procedure, and a door section can specify which samples and product data the contractor submits. These three levels serve different functions. Their order in the manual does not create a contractual tie-breaker.

Complementary requirements and actual conflict clauses

AIA A201–2017 § 1.2.1 treats the Contract Documents as complementary. A requirement can apply even if only one incorporated document states it. If a door schedule identifies the location of a rating and the specification sets the submittal evidence, bidders read both requirements. If the requirements conflict, apply the contract’s reporting and interpretation procedure. A201 § 3.2.2 requires the contractor to report discovered errors, inconsistencies, or omissions to the architect. A conflict that changes the work can require an authorized modification.

Some contracts contain an express precedence rule for a specific conflict. A federal contract containing FAR 52.236-21 gives specifications priority over drawings and requires discrepancies to be promptly submitted to the contracting officer for a written determination. The rule does not remove the reporting duty. EJCDC C-700–2018 § 3.03 includes discrepancy notices to the engineer and addresses conflicts with reference standards, supplier instructions, and laws and regulations with stated limitations. Check supplementary conditions for amendments before applying its rules.

Construction warranties and correction

General warranty

Under AIA A201–2017 § 3.5.1, the contractor warrants to the owner and architect that materials and equipment are new and of good quality unless the documents require or permit otherwise. The work must conform to the documents and be free of defects except those inherent in the specified quality. The clause excludes remedies for specified causes, including abuse, improper maintenance or operation, alterations the contractor did not perform, and normal wear under normal usage. Review the actual warranty and cause of failure before deciding whether a claim applies.

Correction of identified nonconforming work

Under A201 § 12.2.2.1, the contractor generally must promptly correct work found nonconforming within one year after substantial completion of the work or designated portion, subject to other commencement triggers, applicable special warranty terms, and prior written acceptance. The owner must notify the contractor promptly and give it an opportunity to correct. During the one-year period, a failure to provide notice and opportunity can waive correction and warranty-claim rights under the clause.

A201 § 12.2.2.2 extends the period for work first performed after substantial completion by the elapsed time until that portion is actually completed. Under § 12.2.2.3 a repair performed under § 12.2 does not itself extend the correction period. Under § 12.2.5, the correction period sets no general time limit for enforcing the contractor’s other obligations. A defect discovered later can still implicate the general warranty, subject to the contract, applicable law, and the facts of the claim.

EJCDC C-700–2018 §§ 7.17 and 15.08 distinguish warranty and correction rights using different notice and extension rules. For an example using unmodified base terms, the owner gives written defect notice within 60 days of discovery. During the correction period, a qualifying notice triggers the contractor’s obligations under § 15.08. After the correction period, § 7.17.B treats the notice as the start of the event for a related claim and requires the related claim within 30 days of that notice. Section 15.08.E adds a year for affected work after satisfactory completion of correction or removal and replacement under that paragraph. Read the executed supplementary conditions before relying on these time limits.

Manufacturer, equipment, and other special warranties

The technical section and warranty documents should identify coverage, term, issuer, maintenance conditions, and how to submit a claim. Under A201 §§ 3.5.2 and 9.8.4, required material, equipment, and other special warranties are issued to or transferable to the owner and normally start on the date of substantial completion of the work or designated portion. The Certificate of Substantial Completion can provide a different start. Record the date in the certificate, compare the warranty actually delivered with what was specified, and resolve conflicting triggers before accepting the closeout package.

ObligationHow to identify itWhat to track
General warrantyConformity and defects under the general conditionsResponsible party, defect and discovery, notice and claim terms
Correction periodContract duty to correct when specified conditions are metApplicable start, duration, notices, response and any extension under the adopted form
Special warrantyCoverage for the relevant product, assembly, or serviceIssuer, beneficiary, effective date, term, actions needed to maintain coverage

References AIA A201–2017 §§ 1.2, 3.2, 3.5, 9.8 and 12.2, EJCDC C-700–2018 base clauses reproduced in the Muskegon packet, followed by project amendments, and FAR 52.236-21.

Loading diagram...
From general terms to project and work-specific requirements
Test Your Knowledge

The unmodified AIA A201–2017 documents contain a door rating in the schedule and a submittal requirement for rated door assemblies in the specification. How should the contractor treat those provisions?

A

Follow the schedule only because drawing data always take priority.

B

Apply both requirements as complementary and report any actual inconsistency through the contractual procedure.

C

Use the requirements only if both are repeated in Division 01.

D

Apply the specification only because all standard contracts give it priority.

Test Your Knowledge

Under unmodified AIA A201–2017, a defect is first discovered two years after Substantial Completion. Assume the work was first performed before Substantial Completion, with no special correction term, later start date, or prior written acceptance. What does § 12.2.5 establish?

A

Expiration of the correction period extinguishes every warranty remedy.

B

Only the material supplier can be responsible.

C

A concealed defect automatically restarts the one-year correction period.

D

The one-year correction period sets no time limit on enforcement of the contractor’s other obligations.

Test Your Knowledge

The contract requires a 20-year roof warranty and incorporates unmodified AIA A201–2017. When does § 9.8.4 start the required warranty unless the Certificate of Substantial Completion provides otherwise?

A

On the date of substantial completion of the work or designated portion.

B

When materials arrive at the job site.

C

One year after substantial completion.

D

When the architect reviews the roof product data.