15.1 RFIs, Contract Modifications, Claims & Disputes
Key Takeaways
An RFI seeks clarification. If performing the answer would change the contract, verify the authority and notice required.
A201 recognizes a written amendment, Change Order, Construction Change Directive and architect’s written minor-change order.
A201 § 7.4 requires notice and holding the proposed minor change if the contractor believes it affects sum or time.
AIA and EJCDC use different notice recipients, deadlines and dispute paths.
Distinguish clarification, pricing, and authorization
An RFI asks for information needed to perform the specified work. Under AIA A201–2017 §§ 4.2.11–4.2.14, the architect responds in writing to requests concerning the Contract Documents. The architect interprets requirements consistently with the intended work and can issue supplemental drawings or specifications. If the resolution changes the contractual scope, sum or time, check the requirement for an authorized change and any applicable claim notice. Keep the query, response, and resulting action linked in the issue record.
An AIA G709–2018 Proposal Request solicits pricing information. A contractor’s price proposal can identify changed quantities, costs, and schedule impact. Both help the parties evaluate a change before authorizing it. Under EJCDC C-700–2018 § 11.09, a capitalized Change Proposal is a particular contractual vehicle submitted to the engineer to seek relief or contest certain decisions. Read its requirements before equating it with an ordinary price quote.
Match the instrument to the circumstance
| AIA A201–2017 instrument | Authority and effect | EJCDC comparison |
|---|---|---|
| Written amendment, § 1.1.1 | Written amendment signed by the owner and contractor | Use the amendment procedure and forms in the applicable C-700 contract |
| Change Order, § 7.2 | Architect prepares and owner, contractor and architect sign to record agreement on work, sum and time | C-700 §§ 11.01–11.02 assign execution to owner and contractor and require the engineer’s recommendation for changes involving design, acceptability or other technical matters |
| Construction Change Directive, § 7.3 | Architect prepares and owner and architect sign to direct a change within general scope before agreement on price or time | Under C-700 § 11.03, an owner-issued Work Change Directive orders or documents changed work pending later price or time resolution |
| Architect’s written minor change order, § 7.4 | Architect issues for a change consistent with intent and without adjustment of contract sum or extension of time | Under C-700 § 11.04, the engineer issues a Field Order for a qualifying minor change |
Under A201 §§ 7.3.3–7.3.4, check the agreed basis for evaluating a directive. Where no applicable method is agreed or the contractor disagrees, the architect determines the adjustment using reasonable expenditures and savings with the contractual allowance for overhead and profit, and the contractor supplies itemized supporting data. A contractor-signed directive indicating agreement is recorded as a Change Order under § 7.3.7. Interim payment and later agreement have separate provisions in §§ 7.3.9–7.3.10.
If an A201 contractor believes a minor change affects sum or time, § 7.4 requires notice to the architect and withholding implementation of that change. Performing the change without prior notice waives an adjustment under the clause. Under the C-700 Field Order procedure, a contractor seeking an adjustment submits a Change Proposal before proceeding with the affected work.
Route and substantiate claims
For an A201 § 15.1.3.1 claim first discovered before expiration of the correction period, initiate notice within 21 days after the event or after first recognizing the condition, whichever is later. Notify the other party and the Initial Decision Maker (IDM), and copy the architect if it is not the IDM. Use § 1.6.2 delivery and follow any separate earlier notice, including prior notice for additional-cost work under § 15.1.5 subject to its emergency exception. For example, a qualifying concealed condition also triggers the separate § 3.7.4 notice before disturbance and within 14 days of first observation. For a condition first discovered after the correction period expires, § 15.1.3.2 requires notice to the other party without an IDM decision.
Under § 15.2.1, the architect serves as IDM unless the agreement provides otherwise. The clause lists claims outside the IDM path. On its ordinary path, an initial decision precedes mediation, unless the IDM has issued no decision within 30 days after referral. § 15.3 generally requires mediation before binding resolution. The agreement selects arbitration, litigation or another stated method. Read the separate demand and waiver deadlines. Continue performance and payment as required by § 15.1.4.1, with its stated exceptions. The consequential-damages waiver in § 15.1.7 preserves applicable contractual liquidated damages.
Under base C-700–2018 § 11.09, the contractor generally submits a Change Proposal to the engineer within 30 days after the start of the event or the initial decision being contested, and submits supporting data within 15 days thereafter. Check special triggers. For example, under § 11.03.B a contractor’s proposal about a Work Change Directive is due within 30 days after the work in the directive is complete. An owner’s Claim for an adjustment under the directive is due within 60 days after issuance. Under § 12.01, a Claim or appeal is delivered directly to the other party with a copy to the engineer for information, generally within 30 days of the applicable trigger. The parties can agree to mediate. Article 17 and the supplementary conditions determine the final resolution procedure.
References AIA A201–2017 §§ 1.1.1, 1.6, 4.2, and Articles 7 and 15, AIA G709–2018, AIA A101–2017 Article 6, and EJCDC C-700 base Articles 11, 12 and 17, Muskegon packet.
The architect issues a written minor change under unmodified AIA A201–2017. The contractor believes it will add time and labor costs. What should it do under § 7.4?
Implement the change and first raise costs after completing it.
Notify the architect and refrain from implementing the proposed change.
Treat an owner countersignature to the minor change as automatic authority to increase price.
Ignore the change without notifying anyone.
The owner needs an authorized within-scope change promptly on an A201–2017 project, before the parties agree on its price and time effect. Which instrument fits?
Proposal Request.
Contractor’s price proposal.
Architect’s minor change order for a priced change.
Construction Change Directive signed by owner and architect.
On an unmodified A201–2017 project, recognition of a claim condition occurs after the triggering event but before the correction period expires. The claim is subject to ordinary IDM review and no earlier specific notice is at issue. What is the proper first step?
Initiate notice to the other party and IDM within 21 days after recognition and copy the architect if it is not the IDM.
File for arbitration immediately without giving notice.
Request a price from the architect within 14 days and treat it as a claim.
Wait until substantial completion to raise the issue.