14.4 QA/QC Implementation, Testing & Uncovering Work

Key Takeaways

  • Quality assurance establishes confidence in the process. Quality control checks particular work against requirements.

  • A201 § 13.4 distinguishes routine testing, legally owner-arranged testing, additional testing and costs caused by failure.

  • A201 §§ 12.1.1 and 12.1.2 use different rules for uncovering depending on whether covering violated a requirement or request.

  • The owner can elect to accept nonconforming work under applicable conditions and with the price consequences specified.

Last updated: November 2026

Plan quality and check the work

Quality assurance (QA) establishes processes intended to give confidence that requirements will be met. Quality control (QC) includes checks on specific work, recording deficiencies and verifying corrections. Contractor QC can operate alongside owner or government QA and independently performed tests. Check the actual contract and code to identify who arranges and pays for each test. The name of a program does not determine the cost allocation.

UFGS 01 45 00 illustrates three phases of contractor control for a defined feature of work:

  1. Preparatory. Review requirements, materials, approved submittals, readiness of preceding work and planned tests before beginning the feature.
  2. Initial. Check the first representative work, compare workmanship to the standard and correct problems before extending the installation.
  3. Follow-up. Check ongoing work and maintain the required records. Track deficiencies through correction and verification.

For a wall enclosure, QC might check substrate and approved product at the preparatory stage, review the first installation for fastening and sealing, and inspect recurring work and changes in crews or conditions. Keep test reports traceable to the item, location, requirement, date and disposition.

Allocate testing under A201–2017

Under § 13.4.1, unless otherwise provided, the contractor arranges required testing and inspections through an acceptable independent entity or public authority and bears related costs. The contractor gives timely notice to the architect. The owner bears costs of requirements that arise after bids are received or negotiations conclude and directly arranges and pays for testing or inspections where code or applicable law requires it. Identify project-specific allocations.

If additional testing outside § 13.4.1 is necessary, under § 13.4.2 the architect instructs the contractor to arrange it on written owner authorization. The default cost is the owner’s, subject to § 13.4.3. If a covered test, inspection, or approval procedure reveals nonconformance, § 13.4.3 assigns costs made necessary by failure, including repeated procedures and required additional architect services and expenses, to the contractor. The duty to correct rejected or nonconforming work discovered before substantial completion is also addressed by § 12.2.1.

Determine the rule for covering work

ConditionA201–2017 result
Contractor covers work contrary to the architect’s request or an express contract requirement, and the architect then requests uncovering in writingUnder § 12.1.1, uncover and replace at contractor expense without change in Contract Time
Covered work uses the applicable § 12.1.2 procedure and proves conformingContractor is entitled to an equitable adjustment to Contract Sum and Contract Time as appropriate
Work uncovered under § 12.1.2 proves nonconformingContractor pays uncovering and correction costs under that clause

Read the applicable version. EJCDC C-700–2018 § 14.05 separately addresses uncovering, including work covered contrary to the engineer’s written request. Use its cost and adjustment provisions for that contract. Document which requirement was violated, what was exposed, and the result of the inspection or test. Article 12 in A201 also contains separate correction provisions after substantial completion.

Decide whether to correct or accept

Under AIA A201–2017 § 12.3, the owner may accept nonconforming work instead of requiring removal and correction. The Contract Sum is reduced as appropriate and equitable, even if final payment has been made. Record the accepted condition, dollar adjustment and authority under the contract. Check whether the condition complies with applicable law and whether it affects the expected performance or warranties. The owner’s contractual election cannot authorize a code violation.

EJCDC C-700–2018 § 14.04 has distinct procedures. Before final payment, owner acceptance is subject to the engineer’s confirmation concerning general design intent, applicable engineering principles and public safety. Document required revisions by Change Order before final payment under that clause. For acceptance after final payment the contractor pays the appropriate amount to the owner under the clause. Determine diminished value and review costs using the actual terms.

Connect the result to the next operation

For an example with a specified pre-cover test, record the date of the test, the result, and the area still on hold. If the test fails, keep the result in the project record, document the correction and retest, and record who verifies disposition before covering. If exposing already covered work becomes necessary, identify whether the original covering violated a requirement and apply the matching cost rule before recording any price or time adjustment.

References ASQ quality assurance and quality control, UFGS 01 45 00, AIA A201–2017 Articles 12 and 13, and EJCDC C-700 base §§ 14.04–14.05.

Test Your Knowledge

A contractor covers an assembly contrary to an express observation requirement. The architect requests uncovering in writing. The exposed assembly conforms. Who pays under AIA A201–2017 § 12.1.1?

A

The owner because the assembly conforms.

B

The architect because continuous site inspection was required.

C

The contractor, without change in Contract Time.

D

Both parties equally.

Test Your Knowledge

A required test subject to A201–2017 § 13.4.1 reveals defective welds. Which cost result follows under § 13.4.3?

A

The owner always pays any retest because it received the reports.

B

The lab pays all correction and review costs.

C

The contractor pays for repair alone and the owner is responsible for all further test and architect costs.

D

The contractor bears costs made necessary by failure, including repeated tests and resulting architect services and expenses.

Test Your Knowledge

The owner wishes to retain a color variation formally identified as nonconforming, with no code violation. What does AIA A201–2017 § 12.3 permit?

A

The architect alone can accept the work at the original price.

B

The owner may accept the work with an appropriate equitable reduction in the Contract Sum.

C

The contractor can elect acceptance and keep the full price.

D

The owner is always required to remove the work.