1.2 Stages of the Facility Life Cycle
Key Takeaways
CSI uses six facility life-cycle stages: project conception, design, construction documents, procurement, construction, and facility management.
Predesign produces the owner program and can establish the Owner’s Project Requirements for commissioning. A Preliminary Project Description records emerging design intent in schematic design.
Pricing and award precede field work in traditional design–bid–build. The executed agreement determines how the start and contract time are established.
Record drawings, operation and maintenance manuals, and commissioning records connect construction closeout to facility management.
Fast-tracking overlaps design, procurement, and construction for different packages; it does not eliminate approvals or package coordination.
Stages of the Facility Life Cycle
A facility begins with a business or public-service need and can remain in use long after the construction agreement ends. CSI organizes the life cycle into six stages. At each stage, ask what decision the team needs to make, who makes it, and what record the next team uses. A health clinic, for example, starts as a capacity goal, becomes a design with measurable requirements, and eventually has a maintenance history that supports decisions about reuse or replacement.
1. Project Conception
Project conception includes programming, planning, and predesign. The owner identifies the purpose, evaluates feasibility, examines sites or existing facilities, and establishes an initial budget and schedule. A program identifies needed spaces, relationships, and use constraints. For a commissioned project, the Owner’s Project Requirements (OPR) also capture expectations for performance, training and operation. These records support the decision to fund design; they are not a bidder’s scope of work.
For the clinic, the owner might require a separate after-hours entrance and reliable operation of a particular exam suite. The program states the needs. It does not yet specify door hardware, equipment models, or wiring.
2. Design
Schematic design (SD) establishes the organization of the building and major system concepts. A Preliminary Project Description (PPD) can describe anticipated assemblies by function, often in a UniFormat structure, while technical solutions are still being compared. In design development (DD), the design team develops layouts, materials, systems, and interfaces enough to make decisions that will carry into the construction documents. A Basis of Design (BoD) records how the design responds to the owner’s requirements on a commissioned project. The team can ask the owner to confirm scope and reconcile the estimate before issuing documents for pricing.
3. Construction Documents
The construction documents stage develops the coordinated drawings and specifications used to describe the work. A project manual assembles written project requirements, commonly including procurement and contracting material as well as specifications. The manual is not itself a ruling that every page is part of the contract. For example, bid instructions govern the procurement process, while an incorporated technical section governs the installed work.
A door on the clinic plan needs a matching mark in the schedule, a hardware set, and coordinated electrical and security requirements. Before documents are issued, check whether those records identify the same opening and operating sequence. Schematic design approval alone does not make the opening ready for contractor pricing.
4. Procurement
During procurement, prospective contractors price the work through bidding or negotiation as applicable. Written addenda can revise or clarify procurement documents before bids or proposals are due. The owner evaluates offers under the stated criteria and selects a contractor. After award, project participants prepare for field work: confirm the agreement and incorporated documents, collect required bonds and insurance evidence, plan permitting, and coordinate mobilization. The start date is set as the agreement provides; an award announcement is not automatically permission to start site work.
5. Construction
The contractor executes the work, coordinates trades, and controls its site operations. The architect in a traditional AIA arrangement performs the administration assigned under the agreements. Typical records include submittals, responses to Requests for Information (RFIs), test reports, contract modifications, and applications and certificates for payment. Closeout then turns installation records into information the owner can use, including record drawings, warranties, and operation and maintenance (O&M) data. Substantial completion, final completion, and readiness for occupancy serve different purposes; read the contract and applicable approvals rather than equating them.
6. Facility Management
Occupancy begins the operating portion of facility management. Facility staff use the systems manual and O&M materials to operate and maintain equipment and update their maintenance records. They may commission evaluations when user needs change, system performance declines, or asset renewal is due. The resulting evidence supports decisions to repair, renovate, adapt, or decommission. End-of-use decisions are part of the life-cycle story, not a seventh stage in this CSI study model.
| Decision at issue | Best starting record |
|---|---|
| Can this project serve the owner’s intended users and budget? | Program, feasibility study, and initial budget |
| How will the clinic design meet its program and performance goals? | SD and DD drawings, PPD, BoD where applicable |
| What must the prime contractor price and deliver? | Current drawings, specifications, and applicable procurement and contracting documents |
| Which changes were actually authorized? | Applicable signed change instruments and contract change record |
| Which unit was installed and how is it maintained? | Turnover records, equipment information, and the maintenance history |
Where stage overlap changes the handoff
In traditional design–bid–build (DBB), the owner typically procures construction after the drawing and specification package is developed for bidding. Fast-track delivery can instead release a completed foundation package while the interior package is still in design. The foundation package still needs authorized release, applicable approvals and enough information to price and build. For example, if the equipment selection in a later package changes foundation loading, the team must reconcile that interface instead of treating an early release as proof that all later design decisions are settled.
References: CSI CDT domains, CSI project delivery education program, AIA B101–2017 design and construction services, and WBDG commissioning.
Which deliverable distinguishes CSI’s construction documents stage from the preceding design stage?
An owner program identifying user needs
Coordinated drawings and specifications prepared to describe the work
The contractor’s construction progress payment application
An operating log of equipment problems after occupancy
The signed agreement states that contract time starts on the date established in a formal notice from the owner. Which record supplies that date?
Certificate of Substantial Completion
Facility Condition Assessment (FCA)
Basis of Design (BoD)
Notice to Proceed (NTP)
A design–build team chooses to fast-track a project. What change to its stage sequence should the owner expect?
Early work packages enter Procurement and Construction while later design packages are still being completed
Project Conception and Facility Management are omitted to compress the project schedule
Procurement is completed before Schematic Design defines the building layout
Substantial Completion is issued before building permits are obtained from the AHJ