13.4 Verification of Site Conditions & Mobilization

Key Takeaways

  • Before each affected portion, compare documents, relevant field dimensions and site information under A201 § 3.2.2.

  • A201 § 3.7.4 requires prompt notice to owner and architect before disturbance and within 14 days of first observation.

  • EJCDC C-700–2018 § 5.04 requires prompt written notice to owner and engineer before further disturbance, subject to its emergency rule.

  • Plan temporary facilities, access, utility protection and applicable environmental controls before mobilizing affected operations.

Last updated: November 2026

Confirm existing conditions before committing to work

Under AIA A201–2017 § 3.2.2, before starting a portion of the work, the contractor studies the applicable documents and owner-furnished information, takes relevant measurements of existing conditions, and observes site conditions that affect that portion. Promptly report discovered errors, omissions or inconsistencies as an RFI to the architect in the required form. This review facilitates coordination and construction. It does not assign a design audit to the contractor.

Measure irregular openings before releasing custom replacement frames. Compare the measurements to the layouts and details and record differences. If an opening is narrower than indicated, verify the datum, location and known finish thickness, then send the relevant discrepancy through the project’s procedure. Confirm the resolution before relying on it for the affected fabrication.

Where required, make dated photographs or surveys of structures, pavement and adjacent features before disturbance. Tie observations to locations and record who gathered the evidence. Under EJCDC C-700–2018 § 4.03, the owner supplies the engineering surveys the engineer judges necessary to establish reference points. The contractor lays out the work and protects established reference points and property monuments. Check any additional survey and inspection requirements before setting out.

Respond to a qualifying differing condition

AIA A201–2017 § 3.7.4 covers material differences from indicated subsurface or otherwise concealed physical conditions and unknown physical conditions of an unusual nature that materially differ from those ordinarily inherent in the type of work. Promptly notify both owner and architect before disturbance, and no later than 14 days after first observation. The architect investigates and recommends an equitable adjustment if the stated conditions for it are met. Use the contract notice procedure. An RFI about a drawing mismatch does not by itself serve every notice function.

EJCDC C-700–2018 § 5.04.A also addresses materially inaccurate Technical Data on which the contractor is entitled to rely and conditions requiring a design change. The base clause requires prompt written notice to owner and engineer before further disturbance or related work, subject to the emergency provision. Wait for the written permission addressed by the clause, including the engineer’s early-resumption authority when its conditions are met. A later Change Proposal has its own timing. Check the supplementary conditions and never assume the initial notice uses a 30-day deadline.

If the contractor discovers an unaddressed hazardous material and reasonable precautions are inadequate to prevent foreseeable bodily injury or death, A201 § 10.3.1 requires immediate stoppage in the affected area and notice to owner and architect. Do not treat an apparent spill or suspected hazardous exposure only as a quantity or pricing issue. Follow the applicable safety and regulatory procedures and coordinate any separate differing-condition notice when warranted.

Prepare temporary facilities and the logistics plan

Review the work limits, emergency access, pedestrian protection and deliveries with the parties who control the affected locations. A project can place its temporary facility and construction site plan requirements in Division 01, such as UFGS 01 50 00. Confirm the approval route in the specification and permits.

Mobilization issuePreparation and verification
Site access and securityConfirm access dates, haul routes, fencing, emergency lanes and delivery restrictions
Utilities and excavationsCheck records and contact utility owners, verify locations using the applicable procedures, and protect exposed installations
Field offices and welfareSet up the required offices, temporary connections and sanitary facilities where they can operate safely
Material storage and equipmentDefine protected laydown areas, loading and delivery routes, temporary power and weather protection
Construction stormwaterDetermine permit coverage, assigned operator duties, required plan and controls, and inspection and maintenance records

OSHA 29 CFR 1926.651(b) requires identifying the estimated locations of reasonably expected underground installations before opening an excavation and determining exact locations by safe and acceptable means when operations approach. Follow applicable utility notification laws and site procedures. Discharging construction stormwater can require NPDES coverage when disturbance is at least one acre, or when a smaller site belongs to a common plan that will disturb at least one acre. Confirm the permitting authority, operator status, exceptions and site-specific requirements before land disturbance. For a permitted site, implement the required controls and documentation under the permit and project plan.

References AIA A201–2017 §§ 3.2.2, 3.7.4 and 10.3.1, EJCDC C-700 base §§ 4.03 and 5.04, UFGS 01 50 00, OSHA excavation requirements, and EPA construction stormwater coverage.

Test Your Knowledge

On an unmodified AIA A201–2017 project, excavation reveals a dry concealed concrete obstruction materially different from the conditions indicated. No hazardous material or emergency is suspected. What does § 3.7.4 require?

A

Remove it and notify the owner on the next invoice.

B

Wait 30 days after first observing it.

C

Notify only the excavation subcontractor.

D

Give prompt notice to owner and architect before disturbance and no later than 14 days after first observation.

Test Your Knowledge

Before releasing custom replacement frames, a contractor on an A201–2017 project finds that existing masonry openings differ from the drawings. What does § 3.2.2 require?

A

Assume record drawing dimensions are guaranteed.

B

Take applicable field measurements and promptly report the discovered discrepancy to the architect as an RFI.

C

Order the frames and request an automatic time extension later.

D

Use the submittal schedule as a substitute for measuring.

Test Your Knowledge

The project uses UFGS 01 50 00. Which division topic is the best starting point for the temporary site layout, traffic controls and field facilities?

A

Summary of Work.

B

Submittal Procedures only.

C

Temporary Construction Facilities and Controls.

D

Closeout Procedures.