4.3 Insurance & Risk Allocation at Conception
Key Takeaways
Commercial general liability addresses covered third-party claims. Professional liability addresses covered errors or omissions in professional services and is often claims-made.
AIA A101–2017 Exhibit A generally assigns builder’s risk to the owner unless the contractor is designated under the exhibit.
AIA A201–2017 § 11.3.1 establishes a waiver for specified parties and property losses to the extent covered by applicable property insurance.
An owner- or contractor-controlled insurance program covers enrolled parties and listed risks. Confirm the treatment of excluded participants, off-site work, and completed operations.
Under a surety bond the principal owes a performance or payment obligation, the obligee requires the bond, and the surety undertakes obligations defined by the form.
Allocate the risk and identify the policyholder
Contracts can allocate duties to prevent losses, purchase insurance, supply bonds, and indemnify other parties. These obligations serve different purposes. On an AIA A201–2017 project, Article 11 addresses insurance and bonds, but limits and coverage selections are stated in the agreement or other contract documents. Exhibit A to AIA A101–2017 is one agreement exhibit that specifies them. Confirm the signed exhibit before assuming who pays for a policy.
Insurance by exposure
| Exposure | Coverage to check | Who commonly arranges it |
|---|---|---|
| Covered claims for bodily injury or property damage arising from contracting operations | Commercial general liability (CGL), including completed operations where specified | Contractor, with additional insureds and terms as required by the agreement |
| Injury or illness related to work | Workers’ compensation, plus employers liability for covered employer exposures | Employer under governing law and contract requirements |
| Third-party injury or damage involving project vehicles | Automobile liability, with covered owned, hired, and nonowned vehicles as the agreement and policy require | Contractor or other employer operating vehicles |
| Fire or other covered physical damage to the work during construction | Builder’s risk, a property policy | Owner or contractor as designated |
| Claim alleging negligent professional services | Professional liability, also called errors and omissions (E&O) | Architect or engineer, or another entity bearing professional design responsibility |
| Covered pollution loss or limits above primary liability policies | Contractor’s pollution liability, excess, or umbrella coverage as applicable | Participant assigned the relevant requirement |
State workers’ compensation obligations differ. Even where the law gives some private employers a choice, a construction contract or public project rule can require coverage. Employment-related benefits and employer liability have distinct policy terms. For CGL on an A201–2017 project, § 11.1.1 specifies additional-insured treatment for the owner, architect, and architect’s consultants, subject to the contract documents. A certificate is evidence of insurance. Additional-insured status and rights depend on the policy and endorsements.
Compare policy triggers
For an occurrence form, the timing of the covered event or injury relative to the policy period is central. A claims-made form looks to the date the claim is first made and the applicable reporting rule. Some policies also require that it be reported within a stated period. Check the retroactive date, which limits qualifying prior acts, and any extended reporting period, often called tail coverage. For example, assume a claims-made-and-reported design policy ended in June and its reporting extension has expired. A claim first made in October falls outside the stated timing condition even when the design occurred while the policy was active.
Builder’s risk and project property
A101–2017 Exhibit A § A.2.3.1 generally assigns the owner a builder’s-risk completed-value or equivalent policy sufficient for the project’s replacement value. The exhibit can instead assign this obligation to the contractor under § A.3.3.2.1. A broad causes-of-loss form still has exclusions, deductibles, and limits. Verify the applicable property, coverage dates, and treatment of materials at the site, stored elsewhere, or in transit. If the owner is renovating an occupied building, check coverage for the existing structure separately from coverage for the new work.
Wrap-up coverage
An owner-controlled insurance program (OCIP) is sponsored by the owner. A contractor-controlled insurance program (CCIP) is sponsored by the contractor. A wrap-up can centralize selected policies, safety coordination, and claims handling for enrolled project participants. Review the enrollment terms, policy periods, locations, and retained coverage. For example, a fabricator working off-site may need its own policy for work outside the wrap-up. The contract should identify how pricing and certificates account for the coverages that each firm retains.
Recovery after a covered property loss
Subrogation generally allows an insurer that pays a claim to assert recovery rights that its insured held against another party. Under A201–2017 § 11.3.1, the owner and contractor waive their rights against specified parties for fire and other property losses to the extent covered by required project property insurance or other applicable project property coverage. Rights to the proceeds are preserved. The clause calls for similar written waivers from relevant participants and policies that permit the waiver. This is why a quiz about the full amount of a covered project fire can have a different answer from a question about an uninsured loss.
Indemnification is a separate contractual promise. A201–2017 § 3.18.1 covers specified work-related claims and losses, to the extent caused by contractor-side negligence and permitted by law. Do not infer a separate duty to defend from this clause. Check the controlling contract language and applicable restrictions.
Insurance and surety
A performance bond addresses the contractor’s performance obligations, and a payment bond protects eligible claimants furnishing labor or materials. A bid bond addresses obligations linked to the bid and award. A surety’s response follows the particular bond, including any notice and default provisions. The surety may have reimbursement rights under a separate indemnity agreement. An insurance policy instead covers defined losses or liabilities subject to its own terms. Federal public construction requirements are addressed by the Miller Act and Federal Acquisition Regulation Part 28. Bond requirements, amounts, and alternative protections depend on the applicable procurement and its rules.
References AIA A101–2017 insurance exhibit, AIA A201–2017 Articles 3 and 11, AIA professional liability coverage examples, FHWA wrap-up guidance, and FAR Part 28.
A design firm’s claims-made-and-reported policy expired last June. It had no replacement insurance, all extended reporting periods ended before October, and the claim was first made and reported in October. Which policy timing conclusion follows for the expired policy?
It responds automatically because the design was performed during the original policy period.
The claim falls outside the policy’s stated timing condition.
The contractor’s automobile coverage supplies the missing reporting period.
The builder’s risk policy extends the architect’s former liability policy.
Under unmodified AIA A201–2017 with a property policy permitting the waiver, a subcontractor accidentally causes a fire. The owner’s builder’s risk insurer pays the full covered loss to the work. What does § 11.3.1 do to the owner’s recovery rights against that subcontractor for the covered damage?
It preserves the rights because the subcontractor did not sign the prime agreement.
It gives the insurer the same recovery rights as a performance-bond obligee.
It waives those recovery rights to the extent the loss is covered by applicable property insurance.
It transfers those recovery rights to the architect.