15.2 Measurement, Schedule of Values, Progress Payments & Retainage

Key Takeaways

  • Track measured work, progress, stored goods, retainage and previous payments separately.

  • A201–2017 §§ 9.3–9.4 use different clocks for the contractor and architect.

  • Under C-700–2018 § 15.01, the engineer recommends payment and the owner has a distinct set-off role.

  • Review contractual conditions for stored materials, withholding, retainage, and any liquidated damages.

Last updated: November 2026

Match measurement to the price basis

For unit-price work, verify eligible quantities and apply the contractual rate and any required adjustment. Under EJCDC C-700–2018 § 13.03 the engineer determines actual quantities and classifications under its procedure. For stipulated sum or GMP work under AIA A201–2017 § 9.2, the contractor submits a schedule of values allocating the entire Contract Sum before the first application. The architect may require substantiating data and can object to the schedule or subsequent changes. The payment forms, such as AIA G702/G703, can use this schedule for itemized billing. Compare values against the defined scope and investigate unusually high early allocations.

Check each period’s completed work and eligible stored materials. Reconcile previous payments and authorized changes. For example, if work earned to date is 160,000 dollars, the contractually specified retainage is 5% on all that work, and prior payments were 90,000 dollars, retain 8,000 from earned value to date. The current balance is 62,000 dollars if there are no other amounts or adjustments. The contract and applicable law govern whether retainage applies, what is excluded and when it is released.

Apply the AIA workflow

  1. Application. Under § 9.3.1, the contractor submits an itemized application to the architect at least ten days before the scheduled progress payment date, with required support and notarization if required. Include applicable retainage. Use §§ 7.3.9 and 9.3.1.1 for qualifying amounts under a directive or interim determination.
  2. Stored materials. Under § 9.3.2, if agreed otherwise use the stated terms. The default addresses properly delivered and stored on-site materials. Off-site payment needs advance owner approval and a location agreed in writing. Meet owner requirements to establish its title or otherwise protect its interest. Include applicable insurance, storage and transportation costs for off-site storage as provided in the clause.
  3. Certification. Under § 9.4.1, the architect has seven days from receipt to certify all or part of the amount or withhold all, notifying the parties of reasons where required. Under § 9.4.2, the certificate represents the architect’s qualified judgment concerning indicated progress, quality and entitlement based on evaluation and the application. It is subject to later verification and expressed qualifications. It does not represent continuous inspection, review of methods, or an audit of expenditures.
  4. Payment. The owner pays as required by the documents. Under § 9.6.2 the contractor pays each subcontractor its entitlement no later than seven days after receiving payment, with retainage accounted for. Check applicable payment law and contract adjustments.

Compare the withholding and set-off roles

A201 § 9.5.1 permits withholding to the extent reasonably necessary if the architect cannot make the required representations or to protect the owner against specified losses attributable to the contractor. Examples include unremedied defective work, filed or probable third-party claims subject to acceptable security, nonpayment of subcontractors, inadequate remaining funds to complete, damage to the owner or a separate contractor, anticipated delay with inadequate remaining funds to cover damages, and repeated nonconforming performance. Once the reasons are removed, § 9.5.3 calls for certification. A liquidated-damages term, if applicable, follows the agreement, such as A101 § 4.5. A bonus or other incentive is a separate negotiated provision.

For unmodified C-700–2018 § 15.01, the contractor submits generally at least 20 days before the scheduled payment. The engineer has 10 days after receipt to recommend payment in writing to the owner or return the application with reasons. The engineer can recommend reductions, and the owner can impose specified set-offs, giving notice with reasons. The recommended amount subject to owner set-offs becomes due 10 days after presentation to the owner with the engineer’s recommendation. Read local amendments and the agreement. An AIA certificate and EJCDC recommendation have different procedures even though both support the owner’s payment decision.

Reconcile the application against the last certificate

On a stipulated-sum project, suppose a pump appears as stored material on the last certified application. When it is installed this period, transfer its eligible value to completed work and remove the same value from stored materials. Check the new totals against the schedule of values, the last certificate and the supporting delivery record. The same equipment value must appear only once in the running total. Track any additional earned installation value separately within the applicable schedule line.

References AIA A201–2017 Article 9, AIA payment forms, AIA A101–2017 Articles 4 and 5, and EJCDC C-700 base §§ 13.03 and 15.01.

Test Your Knowledge

Which review deadline applies to progress payment under the unmodified EJCDC C-700–2018 base provision?

A

Architect certificate within seven days as in AIA A201.

B

Engineer recommends payment or returns the application with reasons within 30 days of receipt.

C

Engineer recommends payment or returns the application with reasons within ten days of receipt.

D

Owner must make final payment on the day the application is received.

Test Your Knowledge

What does issuing a progress Certificate for Payment under A201–2017 § 9.4.2 represent?

A

The architect’s qualified judgment that progress and quality support the amount certified as due.

B

An exhaustive inspection of every component.

C

An audit of the contractor’s disbursement of earlier funds.

D

Final owner acceptance and waiver of claims.

Test Your Knowledge

A contractor requests A201–2017 progress payment for panels at a fabricator’s yard. What does § 9.3.2 require for the off-site location under its stated procedure?

A

Only a verbal promise of delivery.

B

An architect’s inspection that transfers title.

C

A cash bond equal to the full Contract Sum in every case.

D

Advance owner approval, a location agreed in writing, and the protections for the owner’s interest required by the clause.