9.1 Division 00: Procurement & Contracting Requirements

Key Takeaways

  • Division 00 is the Procurement and Contracting Requirements Group. A project manual can contain Division 00, written specifications, and other project information.

  • Procurement requirements govern the solicitation and selection process. The agreement identifies which parts of the procurement package carry into the contract.

  • Use the project-specific agreement and exhibits for terms such as liquidated damages and insurance. Use supplementary conditions to amend identified general conditions.

  • Addenda revise the bidding package before execution. After execution, use the form and authority specified for the action.

Last updated: November 2026

Read the procurement package and the contract

A project manual is a compilation of written documents. It can include procurement requirements, agreements and conditions, technical specifications, and other project information. The drawings are a coordinated part of the construction document set and may be issued separately. The format of delivery, including a file’s placement in a single electronic package, does not determine contract status.

CSI MasterFormat places Division 00 (Procurement and Contracting Requirements) before the Specifications Group of Divisions 01–49. Its index helps you find documents by purpose. Start with the issued project manual and drawing index because section numbers and titles can vary with the project and edition.

Procurement requirements

Typical seriesPurposeWhat to check
00 01 00, introductory informationIndex, title page, seals, and list of drawings where usedVerify issue date, included sections, and drawing revisions
00 10 00, solicitationAdvertisement, invitation, or request announcing the procurementCheck eligibility, delivery method, and submission date
00 20 00, instructionsBid security, questions, submissions, award criteria, and acknowledgment of addendaIdentify the governing solicitation and amendments
00 30 00, available informationRecords such as utility information, surveys, or geotechnical dataCheck incorporation, permissible reliance, and Contractor site-review duties
00 40 00, procurement forms and supplementsBid form, proposal attachments, bid security, and alternate or unit price entriesComplete the required forms and distinguish these from the eventual agreement

For example, AIA A701–2018 provides bidding instructions. If a surety bond is the required bid security, § 4.2.3 calls for AIA A310 unless the bidding documents provide otherwise. EJCDC C-200 is an instructions-to-bidders form in the Construction Series. Use the instructions actually issued for the project.

Available Project Information, often 00 31 00, may identify documents made available to bidders. Under AIA A201–2017 § 1.1.1, other information furnished by the owner in anticipation of bids is excluded unless specifically enumerated in the agreement. Under EJCDC C-700–2018 § 5.03, the contract can distinguish a listed report from Technical Data within it on which the Contractor may rely for stated purposes. Follow the version and supplementary conditions. If the parties intend to incorporate a Geotechnical Baseline Report, identify it in the executed agreement. Do not infer incorporation or eliminate reliance solely from the filing location.

Contracting requirements and project forms

  • 00 50 00, contracting forms and supplements, is where an index may list the notice of award, agreement, and notice to proceed. The owner–contractor agreement identifies price and time, terms, and other contract documents. AIA A101–2017 is for stipulated sum, A102–2017 for cost of work plus a fee with a guaranteed maximum price, A133–2019 for the construction manager as constructor with a guaranteed maximum price, and EJCDC C-520–2018 for stipulated price. A101 § 3.1 offers commencement by agreement date, notice to proceed, or another stated date.
  • 00 60 00, project forms, can include performance and payment bond forms such as AIA A312–2010 or EJCDC C-610 and C-615, and other forms for administering work. Examples include AIA G702/G703 for payment application and continuation sheet, and G704 to document substantial completion. A blank reference form has a different function from a signed bond, certificate, or contract modification.
  • 00 70 00, conditions of the contract, can include 00 72 00 General Conditions and 00 73 00 Supplementary Conditions. Standard conditions such as AIA A201–2017 and EJCDC C-700–2018 allocate authority and duties. Supplementary conditions identify how particular clauses change for a project. Some project-specific legal terms belong in the agreement or its exhibits. AIA A101–2017 § 4.5 supplies a place for liquidated damages, and its Exhibit A addresses insurance and bonds.
  • 00 90 00, revisions, clarifications, and modifications, can identify addenda and modifications. An addendum may revise bid instructions or technical requirements before execution. Under A201 § 1.1.1, the four modification forms are a written amendment signed by both parties, a Change Order, a Construction Change Directive, and a written architect’s order for a minor change. For example, an order implementing an A201 minor change must preserve price and time. EJCDC uses its own Change Order, Work Change Directive, and Field Order terminology and authority.

Reconcile the issued set at execution

Under A201 § 1.1.1, use the agreement and its enumeration to identify the conditions, drawings, specifications, incorporated addenda and other documents. An owner-supplied sample, the bidder’s bid, or a provision extending the bid deadline ordinarily remains outside the contract unless specifically enumerated. Consider an addendum that moves the due date and changes a door detail. Track the door revision into the final drawings and contractual text. Check how the agreement identifies the addendum, including any portions it excludes.

The agreement can incorporate a different set. In Panama City’s Millville generator replacement agreement, a 2018 EJCDC C-520 form, Article 7 expressly lists the contractor’s bid submittal, drawings, addenda 1 through 7, bonds, and later instruments. That result follows the language in the project agreement. Compare the list with the issued contract files before directing the team to build from any item.

References AIA A201–2017 § 1.1.1 and Article 7, AIA A701–2018, AIA A101–2017, AIA form catalog, EJCDC Construction Series, EJCDC C-800 and identification of Technical Data, Fayetteville C-520 and Geotechnical Baseline Report instructions, and Panama City C-520 Article 7.

Test Your Knowledge

An AIA A201–2017 agreement enumerates a set of Supplementary Conditions and the technical portions of an addendum. The agreement does not specifically incorporate bid paperwork. Which items are Contract Documents?

A

Instructions to Bidders

B

The contractor’s submitted bid and subcontractor listing

C

The enumerated Supplementary Conditions and the technical revisions in the addendum

D

The addendum’s provision changing only the bid opening date

Test Your Knowledge

A construction agreement using AIA A201–2017 does not enumerate a geotechnical report furnished in anticipation of bids. Where can the project manual reference it and what is its status under § 1.1.1?

A

00 31 00 Available Project Information. It is outside the Contract Documents in this agreement.

B

00 73 00 Supplementary Conditions. The report is incorporated automatically.

C

00 41 00 Bid Form. Its recommendations apply as unit-price terms.

D

00 91 13 Addenda. It supersedes conflicting foundation drawings.

Test Your Knowledge

A team using AIA A101–2017 needs to enter a project-specific liquidated damages term and specify required liability insurance limits. Where should it start?

A

Division 01 Summary and an application for payment

B

Supplementary Instructions to Bidders and a blank bid bond

C

The project title page and a certificate of insurance

D

A101 § 4.5 for liquidated damages and the contract insurance exhibit for coverage limits