9.3 Divisions 02–49: Technical Specifications & Work Results
Key Takeaways
The four technical subgroups are Facility Construction, Facility Services, Site and Infrastructure, and Process Equipment.
The section number classifies a work result. The contract and trade packages assign responsibility for performing it.
Identify the applicable specification for each requirement and cross-reference it from other affected sections as needed.
Check the locations, performance conditions, and scope interfaces. A section number alone cannot resolve a detail.
Use the index to locate work results
Drawings and Divisions 02–49 describe the technical work in a coordinated package. The specifications can set product, fabrication, acceptance, and installation requirements. MasterFormat groups the work by purpose and outcome. Some division positions are reserved. Use the governing edition and project index to locate a work result. The 2026 CSI release reorganized many entries, especially in Divisions 32 and 34.
| Subgroup | Division span | Work results to look for |
|---|---|---|
| Facility Construction | 02–19 | Existing conditions (02), concrete (03), masonry (04), metals (05), carpentry and composites (06), enclosure and firestopping (07), openings (08), finishes (09), specialties (10), equipment (11), furnishings (12), special construction (13), and conveying equipment (14) |
| Facility Services | 20–29 | Fire suppression (21), plumbing (22), heating, ventilating and air conditioning (23), integrated automation (25), electrical (26), communications (27), and electronic safety and security (28) |
| Site and Infrastructure | 30–39 | Earthwork (31), exterior improvements (32), utilities (33), transportation (34), and waterway and marine construction (35) |
| Process Equipment | 40–49 | Process piping and instrumentation (40), material processing (41), process heating or cooling (42), process gas or liquid systems (43), pollution control (44), industry-specific equipment (45), water and wastewater equipment (46), and electrical power generation (48) |
In a project using these arrangements, a building fire sprinkler system is in Division 21 and a fire alarm system is in Division 28. Both are in Facility Services. For a remote utility line, first check the site utilities or other applicable infrastructure section. For a processing facility, identify the equipment function in the process division. Building and process equipment can use similar materials or perform similar tasks, so confirm the actual classification and title.
A single work result can need several trades, and a trade scope can span several divisions. For example, a door opening can require mechanical hardware, power, access-control signaling, and connections to life-safety systems. Coordinate documents describing all of them. A prime contractor assigns responsibilities to subcontractors under its contracts and any restrictions of the owner agreement. Owner-held multiple-prime contracts or named procurement packages can allocate that responsibility differently. Check who owns each interface.
Coordinate interfaces by reference and by responsibility
Use a related-requirements reference or other project cross-reference to show readers where complementary requirements appear. The exact article number depends on the project’s organization. Each specification should describe its actual part of the work, including any acceptance criteria that differ by location.
| Interface | Possible document locations | Coordination decision |
|---|---|---|
| Concrete equipment pads | Concrete and HVAC equipment sections, structural and mechanical details | Identify pad size, loading, anchors, required isolation, and the party coordinating the template |
| Electrified door assembly | Door hardware, electrical, electronic access control, hardware and door schedules | Match openings to hardware sets and device schedules. Identify power supplies, door contacts, and release logic |
| Utility trench | Earthwork and utility piping requirements | Identify common compaction and testing, pipe-specific bedding, limits of work and details |
| Fire-rated wall and floor penetrations | Division 07 firestopping with affected services sections and rated assembly drawings | Identify the rated assemblies and penetration conditions so each opening can be matched to the specified system |
| Equipment roof curb | Equipment section, roof section, and curb details | Coordinate curb dimensions, supporting framing, slopes, membrane transitions and the terms of any required roofing warranty |
Suppose the issued basis is 07 84 00 Firestopping, as in the cited UFGS example. That section can identify the required evidence, installation, and assembly-specific acceptance criteria. The plumbing or mechanical section can locate its penetration and refer to the firestopping requirements. Reconcile penetrant type and size, opening dimensions, and the construction being penetrated before selecting a system. Different openings and ratings can call for different systems. Passing a component test by itself does not demonstrate the full assembly satisfies the project requirement.
Before issue, compare the specification index, drawings, scope narratives and bid schedule. For each ambiguity, assign a designer or coordinator to reconcile the interface and check every affected document. Decide whether text requires a cross-reference, a missing detail, or a change to the procurement package. This makes bids comparable and provides a usable record for construction.
References CSI MasterFormat 2026, UFGS master index, UFGS 07 84 00, and CSI SectionFormat/PageFormat.
A building project includes wet-pipe sprinklers, plumbing water heaters, integrated automation, and a building fire alarm. Which MasterFormat subgroup contains those work results?
Facility Construction
Facility Services
Site and Infrastructure
Process Equipment
A project’s firestopping requirements are in Section 07 84 00. Several service systems penetrate different rated walls. How should the specifier coordinate the applicable requirements?
Copy the same system and fire rating into every service section regardless of the wall or penetrant.
Choose an installer in the specification and leave the assembly performance undocumented.
Reference the firestopping section from affected service specifications, and coordinate the applicable wall and penetration conditions across the documents.
Remove firestopping from the contract and rely on discussions with the inspector.
Sections you finish are checked off in the contents.