13.1 Executed Agreement, Notice to Proceed & Contract Documents
Key Takeaways
The governing documents determine what the award notice authorizes and what the selected bidder must deliver.
AIA A101–2017 § 3.1 and EJCDC C-700–2018 § 4.01 use different commencement rules.
Confirm scope, authority, cost limits, bonds and insurance before releasing early work.
Compare a conformed working set with the enumerated documents and authorized modifications.
Trace the authority to proceed
After selection, the owner and contractor complete required documents, check that the appropriate financial and regulatory protections are in place, and identify when Contract Time begins. Record each step against the applicable form. The selection date, signature date, effective date, start date, and site possession date can serve different purposes.
| Document or event | What it does | What to verify |
|---|---|---|
| Notice of Award | Notifies the selected bidder and can set next steps for signing and delivering required post-bid documents | Issuer authority, deadlines, and effect under the solicitation |
| Letter of Intent or early release authorization | Can document an intention to proceed or authorize a specifically defined package if the parties have the authority and terms to do so | Whether the document is binding, scope, maximum expenditure where used, insurance, cancellation, delivery and payment terms |
| Executed agreement | Sets the price basis, time and applicable Contract Documents | Authorized signatures, effective and commencement dates, accepted alternates, exhibits, and contractual conditions |
| Notice to Proceed | Establishes or communicates the start under the contract when the applicable form uses it | Person authorized to issue it, the effective date stated in it, and the prerequisites for the affected scope |
The EJCDC Construction Series includes C-510 Notice of Award and C-550 Notice to Proceed. For example, USDA’s Rural Utilities Service lists the two as distinct instruments in its preapproved construction series. The terms of the actual notice and procurement govern. Do not infer unrestricted mobilization from wording that only notifies a bidder of selection.
Early release of a limited package
If an owner needs to reserve fabrication capacity, identify who is authorized to spend money, which equipment or services are covered, what is payable if work is canceled, and when the release ends. Verify equipment criteria, technical approval, insurance, and any required bonds for the authorized package. Document interfaces and whether the purchase would later be assigned. A letter titled “Letter of Intent” can have different effects depending on its terms and applicable law.
In an AIA A133–2019 or A134–2019 CM-as-constructor arrangement, AIA G735–2021 is an example of a separate early release authorization under the owner–CM agreement. It allows specified work before agreement on the project-wide GMP or control estimate. Define scope, time, compensation, and insurance and bond terms for that work. If the parties have not agreed on the terms for release, a procurement lead time alone does not supply authority.
Start date and prerequisites
AIA A201–2017 § 8.1.2 points to the agreement for the date of commencement. A101–2017 § 3.1 allows the date of the agreement, a date in the owner’s notice to proceed, or another stated method. If the form has no selection, it defaults to the agreement date. Section 3.2 measures Contract Time from the commencement date.
Under EJCDC C-700–2018 §§ 4.01 and 4.02, the indicated day in the NTP applies when one is given. The base clause otherwise uses the 30th day after the effective date, subject to the outside limit in § 4.01. That limit is the earlier of the 60th day after bid opening and the 30th day after the effective date. Check supplementary conditions and any negotiated version. The base form prohibits work at the site before Contract Times begin. When planning release, verify the agreement and bond and insurance terms, access, and the permits or approvals applicable to the first work. Record which prerequisites are still open and who clears them.
Hand the team the correct documents
Start with the signed agreement and its enumeration. Under A201 § 1.1.1, some bidding material is excluded unless specifically enumerated. Reconcile addenda, accepted scope and drawing revisions, and distinguish later authorized modifications. Preserve the issue record so the project team can trace each change.
A conformed set can combine accepted revisions into a convenient working copy. Verify that each change is included and label the issue and its contractual status. If the conformed copy is for convenience and conflicts with the applicable documents, notify the architect or engineer under the contract. Correct the working copy and obtain an authorized change if needed. A new date on an administrative copy does not by itself change the contract.
References AIA A101–2017 § 3.1, AIA A201–2017 §§ 1.1.1 and 8.1.2, AIA G735–2021, USDA RUS C-series document sequence, and EJCDC C-700 base §§ 4.01–4.02, Muskegon packet.
An owner and its construction manager have an A133–2019 agreement. They want to release equipment procurement before agreeing on the full GMP. Which approach addresses that need?
Issue an unrestricted start instruction for all work.
Agree on a limited written early release such as G735–2021, defining scope, time, compensation, bonds and insurance.
Ask the supplier to bill future changes orally.
Treat the conformed drawings as permission to place the order.
A conformed copy issued for convenience omits the incorporated addendum requiring heavier studs. What should the contractor do?
Treat the latest dated working copy as an automatic amendment.
Build using the bid worksheets.
Assume the drawing and specification conflict is resolved by their locations.
Use the incorporated set as the contract basis and report the omission so the working copy can be corrected.
An unmodified AIA A101–2017 agreement leaves all three § 3.1 commencement selections blank. What date applies under the form?
The date of the agreement.
The date of the pre-bid meeting.
Thirty days after the effective date under EJCDC C-700.
The date of first payment.