11.2 Addenda & Pre-Bid Substitutions
Key Takeaways
AIA A701–2018 requires official revisions and interpretations by addendum.
The A701 default distinguishes written inquiry and substitution deadlines from the deadline to issue an addendum.
Recipients must check and acknowledge addenda under A701. The agreement determines the incorporated provisions.
An approved pre-bid substitution must be published to bidders by addendum under A701.
Issue a revision to the current bidding set
An addendum is a formal instrument that changes or interprets the solicitation documents. It may extend the due date, supply missing design information, publish approved equivalents, or change a bid form. Follow the solicitation’s rules for who issues and distributes it. AIA A701–2018 § 3.2 uses addenda for official modifications and interpretations. An AIA Change Order, Construction Change Directive, or written minor change has a separate function under the executed contract.
A usable addendum identifies the project, issue date, and revision number. Cite the affected section or drawing, and say what is inserted, deleted, or replaced. If a scope revision changes an alternate or unit-price entry, reconcile the bid form and technical documents together. Mark the superseded material. Follow the approved distribution channel. Under A701 §§ 3.4.1–3.4.2, the issuing office transmits the addenda to bidders known to have received complete bidding documents and makes them available where the set is on file.
Keep the A701 deadlines distinct
| Action | Unmodified A701–2018 default |
|---|---|
| Bidder’s written substitution request is received by the architect | At least 10 days before the date for receipt of bids, § 3.3.2.1 |
| Bidder’s written request for clarification or interpretation is received by the architect | At least 7 days before the date for receipt of bids, § 3.2.2 |
| Addenda are issued | No later than 4 days before the date for receipt, except an addendum withdrawing the request for bids or including a postponement, § 3.4.3 |
| Bidder checks and acknowledges all issued addenda | Before submission and in the bid, § 3.4.4 |
Read any amendments or governing procurement rules before applying these numbers. For a federal sealed bid under FAR 14.208, the contracting officer considers the time remaining and need for an extension and must allow sufficient time for bidders to consider the amendment. The FAR clause is a separate requirement from the AIA form’s intervals.
For example, an omitted structural detail is discovered three days before receipt of bids on an unmodified A701 project. If the project can proceed with a corrected solicitation, issue an authorized addendum that includes a postponement. Supply the detail with the addendum or make it part of a properly timed later addendum. Give bidders time after receiving the actual detail to obtain subcontractor pricing and update the prime bid. A revised bid deadline alone does not supply the missing geometry.
For a calendar-day example, assume receipt of bids is June 26 and the solicitation has no deadline adjustments. Count back 10 days to June 16 for substitution requests, seven days to June 19 for clarification requests, and four days to June 22 for ordinary issuance of addenda. If an addendum postpones bid receipt to June 30, use the new issuance deadline of June 26 for an ordinary technical addendum, subject to any express deadlines in the amended solicitation. Ensure the amended instructions clearly tell bidders which request deadlines govern.
Incorporate the applicable revision at contract execution
Under AIA A201–2017 § 1.1.1, a technical provision in a pre-execution addendum can carry into the executed contract. Bidding-only provisions are excluded unless specifically enumerated. If an addendum moves the submission date and changes the glazing requirement, note the deadline for bidding and coordinate the revised glazing in the documents used to build. Check the enumerated documents rather than relying on the file location.
Evaluate a proposed pre-bid substitution
A substitution request can allow bidders to compare another product when the governing procurement process permits it. Under A701 § 3.3, the proposer bears the burden of demonstrating merit. Identify the specified and proposed products, the reason for the request, supporting performance evidence, and changes to related work. If the solicitation provides a request form, use it. For equipment, check capacity, utility demands, footprint, support loads, maintenance and required clearance, and warranty or certification consequences. A less expensive unit can require electrical or structural changes that affect the total bid.
Under A701, the architect’s decision on the proposed substitution is final for that procedure. Publish an approval in an addendum so bidders can rely on the same requirements. The A701 form permits post-award consideration only as specifically provided in the Contract Documents. Under A201 § 3.4.2, owner consent, architect evaluation, and an appropriate change instrument normally govern construction-phase substitutions, with specified exceptions for minor changes.
References AIA A701–2018 §§ 3.2–3.4, AIA A201–2017 §§ 1.1.1 and 3.4.2, and FAR 14.208.
On an AIA A201–2017 project, an enumerated addendum changes the bid deadline and revises the exterior glazing requirement. The agreement does not specifically incorporate bidding-only requirements. Which item carries into the contract?
Both items.
The revised glazing requirement.
Neither item unless reissued as a Change Order.
The bid deadline only.
A project uses unmodified AIA A701–2018. A subcontractor emails an unapproved air-handling unit five days before bids are due and receives an informal affirmative response. No addendum approves it. How may the prime bidder treat the unit?
Use it if the email is attached to the bid.
Use it as a voluntary deductive alternate even if none is requested.
Use it because any written response is an approval under the form.
Price the issued unit or another permitted product. The request was late and only an addendum can announce approval under the form.
Three days before bids are due under unmodified AIA A701–2018, a major connection detail is found missing. Which step permits an authorized correction before bidding closes?
Issue an addendum including a postponement, and document the detail with adequate pricing time.
Direct the change using a Construction Change Directive before bids are received.
Call a few bidders with information and keep the same date.
Issue an architect’s minor change order to the bidders.