2.2 Written Formats: SectionFormat, PageFormat & Preliminary Project Descriptions

Key Takeaways

  • SectionFormat organizes each technical specification section into three standardized parts: Part 1 – General, Part 2 – Products, and Part 3 – Execution

  • Division 01 sets common procedures; Part 1 of a technical section spells out requirements for that scope without duplicating common procedures.

  • PageFormat standardizes specification page layout—including headers, footers, section-based page numbering (such as 03 30 00 - 1), and the alphanumeric hierarchy (Part, Article, Paragraph, Subparagraph)

  • A PPD can use UniFormat to describe system intent. An outline specification can summarize emerging work-result selections; a full specification gives enforceable requirements when incorporated.

Last updated: November 2026

While MasterFormat establishes where a specification section sits inside a Project Manual, it does not dictate how text is organized within an individual section. To give specifiers, estimators, and field superintendents a predictable roadmap inside every section, CSI and Construction Specifications Canada (CSC) co-published SectionFormat and PageFormat. Together with phased narrative deliverables, these standards ensure written requirements remain clear, concise, and legally consistent from early concept design through construction.

SectionFormat: The Three-Part Specification Structure

SectionFormat standardizes the internal organization of technical specification sections into three distinct parts:

Part 1 – General

Part 1 – General establishes administrative, procedural, and quality requirements associated with the individual section. Use applicable articles; a section need not contain every example below.

  • Summary: Scope included in the section and cross-references to related sections.
  • References: Industry standards (such as ASTM or ANSI) cited within the section.
  • Administrative Requirements: Section-specific coordination and preinstallation meetings.
  • Submittals: Action submittals (shop drawings, product data, samples), informational submittals (certificates, test reports), and closeout submittals (operation and maintenance data).
  • Quality Assurance: Installer qualifications, mockups, and regulatory criteria.
  • Delivery, Storage, and Handling: Packaging, protection during transit, and site storage conditions.
  • Field Conditions and Warranty: Environmental limits during installation and special or extended warranties.

Part 2 – Products

Part 2 – Products defines the materials, equipment, and manufactured assemblies incorporated into the work. Typical articles cover Manufacturers, Performance/Design Criteria, Materials, Equipment, Fabrication, Mixes, Finishes, and Source Quality Control (factory testing and shop inspections conducted before shipment).

Part 3 – Execution

Part 3 – Execution specifies how products are installed, applied, tested, and protected at the project site. Typical articles include Examination (verifying substrate readiness), Preparation, Installation/Erection/Application, Field Quality Control (site testing and special inspections), Repair/Restoration, Adjusting, Cleaning, Closeout Activities (owner training and demonstration), and Protection of completed work.

SectionFormat Part 1 vs. Division 01 (General Requirements)

A frequent exam distinction involves Division 01 (General Requirements) versus SectionFormat Part 1. Division 01 establishes project-wide administrative and procedural rules—such as overall submittal transmission workflows (for example, Section 01 33 00 Submittal Procedures), general temporary utilities, project-wide quality management, and closeout procedures—that apply across the work as provided in the contract. Rather than copying those procedures into each trade section, use Part 1 to set section-specific scope, qualifications, submittals, storage, or warranty requirements. For example, Division 01 can say how and when to submit a record, while the steel section tells the contractor which mill certifications to submit. Check any intended exception against the governing contract.

PageFormat: Visual Layout and Alphanumeric Hierarchy

PageFormat (also co-published by CSI and CSC) standardizes the graphic appearance, margins, pagination, and text-numbering hierarchy of specification pages so readers can cite and locate requirements unambiguously.

Key PageFormat conventions include:

  • Headers and Footers: Identify the project, MasterFormat section number and title, and any issue or revision identifier the project requires.
  • Section-Based Page Numbering: Pages are numbered sequentially within each section rather than across the entire Project Manual (for example, 03 30 00 - 1, 03 30 00 - 2), allowing individual sections to be revised or issued via addendum without renumbering the entire manual. A closing marker such as END OF SECTION helps identify the section boundary. Verify completeness by checking the page and revision sequence, not by relying on the closing marker alone.
  • Alphanumeric Text Hierarchy: One common hierarchy for labeled requirements is:
    1. Part: All uppercase (PART 1 - GENERAL).
    2. Article: Part number plus sequential number (1.01 SUMMARY or 1.1 SUMMARY).
    3. Paragraph: Capital letters (A., B., C.).
    4. Subparagraph: Arabic numerals (1., 2., 3.), followed if necessary by lowercase letters (a., b., c.) and parenthetical numerals or letters.

Keeping outline indentation shallow helps prevent buried requirements and simplifies contract administration when referencing specific clauses.

From Preliminary Project Descriptions to Full Specifications

Written technical documentation matures alongside design decisions across the Schematic Design (SD), Design Development (DD), and Construction Documents (CD) phases:

Preliminary Project Descriptions (PPDs)

Prepared during Schematic Design, Preliminary Project Descriptions (PPDs) use UniFormat to describe building systems, functional performance, and major assemblies conceptually. Because specific products are not yet finalized, a PPD enables cost estimators to build reliable elemental budgets and helps owners confirm project scope early.

Outline Specifications

An outline specification summarizes emerging technical selections under a work-result structure such as MasterFormat. It can be used during Design Development or earlier when the scope calls for it. They capture selected materials, finishes, structural systems, and major mechanical or electrical equipment in abbreviated narrative or bulleted form—bridging conceptual intent, validating cost estimates against owner budgets, and guiding full specification writing.

Full Construction Specifications

Prepared during Construction Documents, Full Construction Specifications combine MasterFormat (section numbering), SectionFormat (three-part internal structure), and PageFormat (standardized layout and alphanumeric hierarchy) inside the Project Manual. Together with the Drawings and Conditions of the Contract (such as AIA A201-2017 or EJCDC C-700), they govern the work to the extent incorporated into the agreement.

Document TypeDesign PhaseClassification FormatLevel of DetailPrimary Purpose
Preliminary Project Description (PPD)Schematic DesignUniFormatConceptual assemblies and functional performanceDefine system scope and support elemental cost estimating
Outline SpecificationAs design selections developTypically MasterFormat work resultsAbbreviated material, finish, and equipment selectionsEstablish material decisions and guide engineering coordination
Full Construction SpecificationConstruction DocumentsMasterFormat + SectionFormat + PageFormatComplete three-part enforceable requirementsGovern bidding, procurement, fabrication, and field execution

References: CSI SectionFormat/PageFormat, CSI PPDFormat, and UFGS examples.

Test Your Knowledge

A section already lists the waterproofing materials in Part 2. Where should the specifier give the instructions for applying the system at laps and terminations in the field?

A

Part 1 under Warranty.

B

Part 2 under Source Quality Control.

C

Part 3 under Installation.

D

Division 00 under Bid Form.

Test Your Knowledge

Which statement correctly explains the relationship between Division 01 (General Requirements) and Part 1 – General of a technical specification section?

A

Division 01 sets common administrative procedures; Part 1 addresses requirements specific to the section.

B

Part 1 must copy all Division 01 submittal and closeout procedures verbatim so each trade subcontractor has a complete standalone document

C

Division 01 applies only during bidding, whereas Part 1 governs all administrative rules during construction

D

Part 1 establishes general conditions of the contract such as indemnification and dispute resolution