15.3 Project Closeout, Commissioning & Facility Manager Handoff

Key Takeaways

  • Substantial completion is a contractual milestone. Verify applicable regulatory occupancy approvals separately.

  • A201 and C-700 use distinct certificate and final payment procedures and different waiver terms.

  • Plan seasonal tests, warranty dates, and unresolved corrective work during handoff.

  • The facility team verifies usable records, training and asset information before taking over operations.

Last updated: November 2026

Establish which milestone has been reached

Under AIA A201–2017 § 9.8.1, work is substantially complete when the work or designated portion is sufficiently complete under the contract for the owner to occupy or use it for its intended purpose. When the contractor considers it ready, it submits a list of items to complete or correct. The architect inspects, identifies items that must be addressed before the milestone, and prepares the Certificate of Substantial Completion when the work reaches the milestone. An item omitted from the list can still be required by the contract.

AIA G704 documents the date, responsibilities for matters such as security, maintenance, heat, utilities, damage and insurance, and the time for completing the attached items. Under § 9.8, obtain the required written acceptance of assigned responsibilities and follow the payment and surety provisions. Check the certificate for the start of required warranties under § 9.8.4. Track the contractual correction period separately under § 12.2.2. The applicable terms determine triggers and exceptions.

For EJCDC C-700–2018 § 15.03, the contractor gives written notice and a draft list to the owner and engineer. The owner, contractor and engineer inspect. The engineer issues a preliminary certificate if the work meets the standard, and the owner has seven days after receipt to object in writing. Within 14 days after submitting the preliminary certificate to the owner, the engineer issues the final certificate or notifies the contractor in writing that the work is not substantially complete, with reasons. Use the project’s adopted version and check the insurance transition.

A certificate of occupancy or other applicable authorization comes from the jurisdiction. Contractual substantial completion and code authorization address separate requirements. Under A201 § 9.9, partial occupancy has its own steps, including insurer consent, authority approval and written responsibilities. Confirm controlled access and responsibilities before use.

Verify systems, training, and handover

Commissioning checks that systems meet the documented owner requirements and design intent under the commissioning plan. At the end of construction, use completed installation checklists and startup records to establish readiness for applicable functional performance testing. Test the specified operating modes and sequences, record results, and track unresolved issues through correction and retesting. If conditions prevent a required seasonal test, agree on a deferred test plan and record who provides access, conducts the test, documents resolution and owns any outstanding work.

The facility manager can participate in walkthroughs and training, inspect access for servicing, and reconcile equipment labels with drawings and asset information. Deliver the contractually required manuals, operating sequences, testing results, warranties, record documents, training records, keys and spares. For example, link an air-handling unit’s tag to its location, approved operating instructions and maintenance tasks. Document warranty triggers, deferred tests and parties to contact. Set up the maintenance system before handover if it is required to support operation. The applicable commissioning plan and agreement assign who compiles the final report and Systems Manual.

Complete final payment and preserve legitimate claims

Under A201 § 9.10.1, after notice of readiness and a final application, the architect inspects and issues a final certificate when the work is acceptable and the contract is fully performed. Under § 9.10.2, prerequisites for final payment and remaining retainage include the specified affidavit, insurance evidence and renewal statement, consent of surety if any, special warranty documentation, and other evidence if required. AIA G707 is a consent form for final payment. Sections 9.10.4–9.10.5 describe what final payment waives. The owner retains the enumerated exceptions, including failure to comply with the requirements and special warranties. The payee preserves claims previously made in writing and identified as unsettled at the final application.

Under base C-700 §§ 15.05–15.06, the engineer inspects and, if satisfied with completion and documentation, recommends final payment in writing within ten days of receiving the application and issues a separate notice of acceptability. The owner pays the balance after applicable set-offs within 30 days of receiving the final application from the engineer. The contractor’s final application includes the required releases or approved alternatives, title evidence, surety consent if any, and a list of duly pending Change Proposals and Claims. Under § 15.07, owner final payment waives late-completion damages except for an outstanding Claim, appeal, set-off, or express owner reservation. The owner reserves its other claims and rights. Contractor acceptance preserves duly submitted pending Claims or appealed matters under the applicable provisions. Confirm the exact waiver and jurisdiction before treating any informal reservation as effective.

MilestoneContract exampleEvidence to retain
Substantial completionA201 § 9.8Certificate, assigned responsibilities and work remaining
Outstanding seasonal testApplicable commissioning planDeferred test, timing and responsible parties
Final closeoutC-700 § 15.06Final recommendation, notice of acceptability and required submissions

References AIA A201–2017 §§ 9.8–9.10 and 12.2, AIA G704 and G707 catalog, EJCDC C-700 base §§ 15.03–15.08, GSA Commissioning Guide, and VA commissioning specifications.

Test Your Knowledge

Under base EJCDC C-700–2018 § 15.06, what does the engineer issue when satisfied at final closeout?

A

A municipal certificate of occupancy.

B

A written recommendation of final payment and a notice of acceptability subject to its stated limitations.

C

Final payment from the engineer’s account.

D

An unconditional release of all contractor obligations.

Test Your Knowledge

Conditions at handover prevent a required winter operating sequence from being tested. What should the commissioning team do?

A

Assume the sequence works once the facility is substantially complete.

B

Replace the test permanently with a product data sheet.

C

Track the open item and coordinate a deferred functional test under the plan when suitable conditions are available.

D

Treat regulatory occupancy approval as proof of equipment performance.

Test Your Knowledge

A bonded project uses unmodified A201–2017 and omits consent of surety from the final package. What does § 9.10.2 provide?

A

Final payment and remaining retainage do not become due until required surety consent and the other listed items are submitted.

B

Consent is due only after final payment has been made.

C

The architect may replace the surety’s consent with an RFI.

D

The omission automatically voids all equipment warranties.