16.1 Facilities Operation & Maintenance Strategies
Key Takeaways
Compare operating costs by scope, assumptions and study period.
Run-to-failure, scheduled service and monitoring address different failure patterns. Reliability-centered maintenance selects a mix.
Record the project’s actual correction and special warranty dates, notice instructions and required maintenance.
Use existing-building commissioning to investigate and verify system performance.
Compare the costs of owning and maintaining a facility
Owners consider first cost together with energy, water, operation, maintenance, replacement and residual value over a defined study period. Use the same service requirements and period when comparing options. Life-cycle cost analysis accounts for the timing of costs by bringing future amounts to a common value. Assumptions about use, service life, discount rate and utility prices can change the comparison. The NIST/FEMP method provides a framework for making these assumptions visible.
Suppose the present value of all relevant future costs, net of residual value, is 270,000 dollars for equipment with a 180,000-dollar purchase and installation cost. The total is 450,000 dollars. For comparable equipment with a first cost of 210,000 dollars and present-value future costs of 210,000 dollars, the total is 420,000 dollars. The second choice costs 30,000 dollars less on the stated assumptions. During design, verify whether the projections include maintenance access, downtime or equipment replacements relevant to this owner.
Choose maintenance by failure consequence
| Approach | Trigger or decision basis | Example |
|---|---|---|
| Reactive or run-to-failure | Repair or replace at failure where its consequences are acceptable | Replace a single failed lamp where remaining lighting provides safe service |
| Time-based preventive | Calendar or runtime interval set by equipment instructions, the maintenance program or applicable requirements | Inspect a wear component at its specified service interval |
| Condition-based | Measured degradation or a validated threshold | Change a filter when differential pressure reaches the specified limit |
| Predictive | Trends and diagnostics identify a developing failure and help schedule intervention | Use increasing bearing vibration under comparable loads to plan a repair |
| Reliability-centered maintenance | Select a combination of maintenance tasks based on system function, failure modes and consequences | Combine required standby equipment tests, critical bearing monitoring and reactive replacement of low-impact components |
The best maintenance mix depends on failure consequences, monitoring cost, redundancy and available staff. Condition monitoring supplies evidence for action, and predictive analysis can use trends to anticipate when service is needed. Check the applicable operating or inspection requirements before deferring any scheduled task. An operator can document a baseline reading and check the alarm setpoint against the equipment data instead of treating every alarm as a proven fault.
Maintain the asset and its contractual records
A computerized maintenance management system (CMMS) can link asset tags, locations, service histories, spares and work orders. Link each special warranty to its coverage, start trigger, notice contact and required service. Schedule inspections so there is time to give effective notices and document work. Store reports and receipts where the operator can retrieve them when a defect appears.
Under AIA A201–2017 §§ 3.5, 9.8.4, 9.9.1 and 12.2.2, distinguish general and special warranties from the post-completion correction procedure. Substantial completion normally supplies the date, but applicable certificate terms, partial occupancy, work first performed later and special warranty terms must be checked. Under § 12.2.2.1 give prompt notice and an opportunity to correct qualifying work, subject to the clause. Under base EJCDC C-700–2018 § 15.08, give written notice within 60 days of discovering a defect and within the correction period to invoke that section’s remedy. The clause addresses earlier service for specified equipment and separate extensions for corrected work. Track the governing form and each equipment warranty individually.
Use commissioning to sustain performance
DOE’s Federal Energy Management Program distinguishes retro-commissioning for a building that was never commissioned, recommissioning to restore or adjust performance in a previously commissioned facility, and ongoing commissioning that integrates monitoring and correction into operations. Investigate documented operating problems, agree on changes, and verify the results. For example, a trend showing ventilation equipment running well after occupancy may warrant checking the operating schedule and override history. Record the correction and confirm that the new schedule still satisfies occupant and system requirements. Document who will monitor for recurrence and who can authorize future overrides. Record the initial and adjusted settings, relevant load and weather conditions, and the dates used for comparison. If results differ, revisit the original diagnosis and preserve the evidence alongside the work order.
References DOE building life-cycle costing program and NIST Handbook 135, DOE maintenance approaches, DOE condition monitoring and diagnostics, DOE commissioning in federal buildings, AIA A201–2017, and EJCDC C-700–2018 § 15.08, base clauses.
A facility engineer replaces an air-handling unit filter when measured differential pressure reaches the specified limit. Which approach most directly describes the decision?
Time-based preventive maintenance.
Condition-based maintenance.
Reactive run-to-failure maintenance.
Retro-commissioning.
Under unmodified AIA A201–2017, the certificate establishes substantial completion and the roofing manufacturer gives a separate 20-year special warranty. How should the facility manager set up the records?
Use one one-year expiration for all roofing obligations.
Keep only the special warranty because it replaces the correction procedure.
Start all periods at final payment.
Track the applicable correction deadline separately from the warranty’s own start, duration and required upkeep.
Two equipment packages provide the same required service over the same study period. One has a higher purchase cost but lower operating costs. What comparison supports the selection?
Compare life-cycle costs on a common present-value basis, including planned service and replacement.
Compare initial costs only until the purchase order has been issued.
Compare manufacturers’ warranty durations as a proxy for all ownership costs.
Compare one undiscounted utility bill from each option and choose the lower one.