13.2 Preconstruction Submittals, Bonds, Insurance & Permits
Key Takeaways
Check bond forms, penal sums and insurance requirements against the selected agreement and exhibits.
Under A201 § 3.10, the construction schedule is for information and the submittal schedule is for approval.
The schedule of values allocates the contract sum for progress payment under the applicable payment basis.
Use the adopted contract and the authority having jurisdiction to determine permit responsibilities.
Establish which submissions are due when
The preconstruction package can support several decisions. Some items are due before work starts. Others follow award, are needed before a particular activity, or are due before the first payment application. Check the agreement, conditions and Division 01 for the action, recipient and due date for each item.
| Submission | What it supports | What to verify |
|---|---|---|
| Performance and payment bonds | Performance remedies and protection for eligible unpaid claimants | Parties, penal sums, signatures, effective date and required form |
| Insurance evidence | Contract compliance before the insured operations begin | Applicable policy, dates, limits, endorsements, and party assigned property insurance |
| Construction and submittal schedules | Work sequence, release and review timing | Milestones, procurement lead time, review intervals and updates |
| Schedule of values | Progress payment for the work | Complete allocation, support for values, and actual contract adjustments |
| Proposed trades and suppliers | Timely review for objections where applicable | Names, qualifications, allocation of principal work, and contract deadlines |
AIA A312–2010 contains two separate bonds. The performance bond sets out surety obligations and options after the required conditions are met. The payment bond protects eligible parties supplying labor or material under its terms. Verify the amounts required by the contract and applicable law. A bond is distinct from an insurance policy and does not automatically eliminate all liens.
For a project using AIA A101–2017 Exhibit A, § A.3.1.1 calls for the contractor’s certificates before commencement and at other stated times. Confirm that the specified endorsements and coverage are present. A certificate is evidence, while the policy and endorsements establish coverage. Under §§ A.2.1 and A.2.3.1 the exhibit assigns the owner’s insurance and evidence duties, and it can shift builder’s risk to the contractor under § A.3.3.2.1. Check this assignment before release.
Coordinate the schedules and payment basis
Under A201 § 3.10.1, submit the contractor’s construction schedule promptly after award for the owner’s and architect’s information. Include commencement, interim milestones, substantial completion and the timing of activities appropriate for the project. Under § 3.10.2, submit a current submittal schedule for the architect’s approval. Coordinate it with the construction schedule and allow reasonable review time. Failure to submit one or to supply submittals in accordance with the approved schedule bars increases in Contract Sum or extensions of Contract Time based on review time under that clause.
For a stipulated sum or GMP project using A201 § 9.2, the contractor submits a schedule of values allocating the entire Contract Sum before the first application. Supply substantiation as required. Compare early and late line values to the work to find possible front-loading. Request supporting information for a questionable allocation before relying on the schedule. A large mobilization line by itself does not prove an imbalance.
Under A201 § 5.2.1, unless otherwise stated, the contractor notifies the owner and architect of proposed persons or entities for principal portions as soon as practicable after award. The architect has 14 days from receipt to give notice of a reasonable objection or request additional review time. Read the rest of § 5.2 for replacement and adjustment terms. This is separate from post-selection bidder submittals under A701.
Determine who obtains each approval
Under A201 § 3.7.1, the contractor generally secures and pays for building permits and other permits, fees, licenses and governmental inspections relating to proper execution and completion that are customarily secured after execution and legally required when bids are received or negotiations conclude, subject to the Contract Documents. Under § 2.3.1, the owner secures and pays for necessary approvals, easements, assessments and charges for permanent structures or changes, except those assigned to the contractor. Check the actual approvals and local procedure rather than assuming a utility or plan-review fee has the same assignment on every project.
EJCDC C-700–2018 § 7.09 specifies a different default. It assigns construction permits, licenses and certificates of occupancy to the contractor unless otherwise provided, calls for owner assistance as needed, and assigns permanent utility connection charges to the owner. The authority having jurisdiction determines the regulatory process for permits, notices, inspections and occupancy. Before each affected operation verify the approval, conditions, and required inspection hold points.
References AIA A201–2017 §§ 2.3.1, 3.7.1, 3.10, 5.2, 9.2 and 11.1, A101–2017 insurance exhibit, A312–2010 instructions, and EJCDC C-700 base § 7.09.
The initial schedule of values materially overstates early mobilization and understates later finishes. Why request substantiation and a corrected allocation before using it?
Mobilization is never an allowed line.
The contractor submits the schedule only after substantial completion.
Overstated early values can produce payments ahead of actual progress and leave too little balance for later work.
Only the surety can allocate line values.
Under unmodified AIA A201–2017, which item is generally assigned to the owner when the documents make no other assignment?
An easement needed to use the permanent facility.
The general building permit secured after execution.
Governmental inspections customarily secured by the contractor during construction.
Construction trade permits customarily secured after execution.
A contractor on an unmodified AIA A201–2017 project submits no submittal schedule. It then requests a time extension solely because of the time the architect spent reviewing the submittals. What does § 3.10.2 provide?
Automatic extension if review exceeded five days.
Automatic reimbursement if review exceeded seven days.
Submission is optional if the work has started.
No extension or increase in sum based on review time when the contractor fails to submit the required schedule.