3.2 Due Diligence Investigations & Site Selection

Key Takeaways

  • Compare the owner’s program with zoning, title, utility, access, and physical conditions before committing to a site.

  • Phase I ordinarily identifies potential releases using inquiry and observation; Phase II can use targeted sampling to answer a specific question.

  • Keep site feasibility, environmental release investigation, and surveys for hazardous building materials separate; they answer different questions.

  • A Division 00 reference report is not necessarily incorporated into the contract. Read the agreement and the applicable reliance provisions.

  • Under AIA A201–2017 § 3.7.4, give notice before disturbing a qualifying condition and within 14 days after first observance.

Last updated: November 2026

Due Diligence Investigations & Site Selection

Acquiring land or committing to a renovation without thorough physical, environmental, and regulatory verification exposes the Owner to redesigns, delays, and claims. During Project Conception (CSI Tasks 2.2 and 2.6), due diligence investigations verify whether a candidate site or existing building can legally, technically, and economically support the Owner's Project Requirements (OPR).

Site Selection & Regulatory Due Diligence

Before closing on real estate or starting design, the Owner evaluates four regulatory and infrastructure dimensions:

  1. Zoning Ordinances & Land-Use Controls: Local codes govern permitted uses, building setbacks, lot coverage, height limits, Floor Area Ratio (FAR), parking rules, and overlays. Use the local ordinance’s definitions of counted floor area and lot area. A variance or zoning change, if pursued, can affect the schedule and is not a substitute for checking the underlying restriction.
  2. Legal Surveys, Easements & Encumbrances: An ALTA/NSPS Land Title Survey (American Land Title Association / National Society of Professional Surveyors) documents surveyed conditions such as boundaries, access and encroachments against the title materials made available to the surveyor. An easement may grant use of part of a different owner’s property; read the instrument to see what it permits or restricts. Review title documents separately for restrictions not resolved by the survey. The joint 2026 survey standard took effect February 23, 2026.
  3. Utility Availability & Capacity: Verifying municipal potable water, fire-protection flow, sanitary and storm sewers, electrical power, natural gas, and telecommunications capacity—plus pricing main extensions or impact fees.
  4. Traffic, Access & Topography: Review access for users, services and emergency vehicles, grading, solar orientation, and affected structures. An impact study asks what the project would do to the surrounding area, such as adding trips to a congested intersection. A site study instead compares conditions and constraints of the candidate parcel.

Subsurface, Environmental & Hazardous Materials Investigations

Hidden ground conditions and legacy contaminants pose major financial risks:

  • Phase I environmental site assessment (ESA): A Phase I under ASTM E1527–21 uses records, interviews, and site reconnaissance to identify recognized environmental conditions or information gaps; it ordinarily does not sample soil or groundwater. EPA recognizes that practice for satisfying All Appropriate Inquiries (AAI), one element of certain federal landowner liability protections under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). It is not by itself a liability shield.
  • Phase II ESA: When an owner needs to test whether a suspected release is present, a Phase II under ASTM E1903–19 can use targeted sampling and laboratory analysis. The assessment objective determines which media and locations to sample. A Phase I finding does not create a universal legal duty to order Phase II; the transaction, governing rules and professional recommendations may call for it.
  • Water and flood constraints: Identify potential wetlands, check applicable permit requirements and confirm jurisdiction with the appropriate authority. Flood maps and local drainage rules can affect site layout and allowances for stormwater management.
  • Geotechnical investigation: Depending on scope, an investigation can characterize subsurface materials and groundwater and support recommendations for foundations, earthwork, and construction risks. Point observations do not establish uniform conditions throughout the site.
  • Existing hazardous materials: Renovation or demolition may require separate surveys for materials such as asbestos or lead-containing coatings. Identify the applicable regulations and distinguish this building-material survey from a Phase I ESA for real-property acquisition.

Feasibility Studies & Existing Facility Evaluations

When weighing whether to renovate, expand, adaptively reuse, or build new (Task 2.6), feasibility studies pair physical audits with life-cycle financial analysis:

  • Building Code & Life-Safety Audits: Assessing whether occupancy changes or major alterations trigger current code compliance—egress capacity, fire-resistance ratings, sprinklers, and seismic upgrades.
  • Americans with Disabilities Act (ADA) Accessibility Audits: Inspecting parking, paths of travel, door clearances, elevators/ramps, and restrooms, when the applicable accessibility requirements reach the proposed alterations. For example, the federal Title III rule addresses the accessible path serving an altered primary-function area, with specified feasibility and disproportionality provisions.
  • Structural and building systems capacity evaluations: Verifying whether existing framing supports added loads and whether existing heating, ventilation, and air conditioning (HVAC), electrical, and plumbing systems retain useful capacity.

Contractual Treatment of Owner-Furnished Site Reports

  • Available project information: A project manual may point to geotechnical or other site reports under Division 00. A reference copy is not automatically a contract document or a warranty of uniform conditions. Read the agreement and any specific reliance provisions before deciding which information the contractor may use for a claim.
  • AIA A201–2017 § 2.3.4: The owner provides surveys and a legal description. The contractor is entitled to rely on the furnished information’s accuracy while exercising proper precautions for safe performance.
  • AIA A201–2017 § 3.7.4: Give prompt notice to the owner and architect before disturbing a materially differing concealed condition indicated by comparison to the contract documents, or an unusual unknown physical condition that differs materially from what is ordinarily inherent in that work. Notice must be no later than 14 days after first observance. The architect investigates and recommends an adjustment if the clause’s conditions are satisfied; it is not an automatic change order.
  • EJCDC C-700–2018: The form distinguishes Technical Data the contractor may rely on from other report content. Check the supplementary conditions for express identification of Technical Data before using the form’s default treatment of objective factual data; reliance on a boring log is different from treating a report’s design recommendation as a guarantee.
Due Diligence InvestigationPrimary Standard / ScopeKey Project Risk Mitigated
Zoning & FAR AnalysisLocal zoning code, setbacks, height, parkingRedesign or rejection due to illegal building bulk or use
ALTA/NSPS Title SurveyBoundaries, easements, access and encroachmentsBuilding over utility easements or disputing lot lines
Phase I ESAASTM E1527–21 historical records, walkover, interviewsUnidentified potential releases or gaps in acquisition information
Phase II ESAASTM E1903–19 targeted sampling selected for the assessmentUnbudgeted environmental remediation and regulatory holds
Geotechnical InvestigationSubsurface exploration, bearing capacity, water tableFoundation settlement, dewatering surprises, and earthwork claims
Code, ADA & Hazmat AuditLife safety, accessibility, and suspected hazardous building materialsSurprise abatement orders, seismic triggers, and occupancy delays

References: 2026 ALTA/NSPS survey standards, EPA All Appropriate Inquiries, ASTM E1903–19, DOJ ADA Title III regulations, AIA A201–2017 §§ 2.3.4 and 3.7.4, and EJCDC’s C-700 site-condition guidance.

Test Your Knowledge

A Phase I ESA identified a potential solvent release from a former dry cleaner. The owner now wants an environmental professional to collect and analyze site samples to test the concern. Which investigation fits?

A

A second zoning review

B

An ALTA/NSPS title survey

C

A targeted Phase II ESA

D

A contractor’s building-permit application

Test Your Knowledge

The project manual provides a geotechnical report under Division 00 as available project information, and the agreement does not list the report as a contract document. What should the bidder conclude?

A

The report is not incorporated merely by being made available; check the contract for any reliance rights.

B

Every reference report in a project manual is a binding performance specification.

C

The report guarantees that conditions will be the same between borings.

D

A report listed in Division 00 is a record drawing issued after construction.

Test Your Knowledge

During site selection for a warehouse, title documents show an easement across the preferred loading area. Which action should the owner take before treating that layout as feasible?

A

Use the geotechnical report to determine the permitted use of the easement area.

B

Assume permitted loading access follows automatically from the zoning classification.

C

Rely on the proposed building outline to establish the limits of the easement.

D

Locate the easement using the title information and survey, and review the instrument for restrictions affecting loading.