4.1 Project Delivery Methods Compared

Key Takeaways

  • Traditional design–bid–build uses separate owner agreements for design and construction. A negotiated award can also use separate agreements.

  • A construction manager at risk provides early advice and then contracts to build. A construction manager as adviser provides services while the owner holds the construction contracts.

  • In design–build, one entity contracts with the owner for both design and construction. The owner’s criteria and the agreement define scope and responsibilities.

  • An owner–builder performs the general contractor role. In a multiparty integrated model, core parties can agree on joint governance and incentives.

  • Fast-tracking overlaps work packages to shorten the schedule. Track authorizations, package interfaces, and unresolved scope before releasing early work.

Last updated: November 2026

Choose a delivery structure before choosing an award process

A project delivery method allocates design, construction, and coordination responsibilities. Start by drawing the contracts. Then identify how the team is selected, how the work is priced, and when each package can be released. A guaranteed maximum price (GMP) addresses payment for a defined scope under the agreement. Fast-tracking addresses schedule. Either can appear under more than one contract structure.

CSI’s Project Delivery Education Program distinguishes five main methods: design–bid–build, construction management at risk, design–build, owner–build, and integrated project delivery. It is also useful to distinguish a negotiated award, a construction manager hired as an adviser, and multiple-prime contracting.

Design–bid–build and negotiated construction

In design–bid–build (DBB), the owner usually retains an architect or engineer (A/E) to design and document the project and later contracts with a prime contractor to build it. The two prime agreements create separate contractual relationships with the owner. The architect’s construction administration authority comes from the applicable agreements and general conditions. Under unmodified American Institute of Architects (AIA) A201–2017 § 4.2.4, the owner and contractor include the architect in communications affecting the architect’s services. The clause also addresses direct owner–contractor communications and recognizes other protocols in the contract documents.

Competitive bidding gives bidders a common documented basis for comparison. It can produce a construction price after design, but the owner must account for time to complete documents and conduct procurement. Examples are AIA B101 for design and A101 with A201 for construction, or Engineers Joint Contract Documents Committee (EJCDC) E-500 for engineering and C-520 with C-700 for construction. Design–negotiate–build can retain the same two agreements while the owner negotiates scope and price with the selected contractor. Check the applicable procurement rules before assuming negotiation is available.

Construction management at risk and advisory services

A construction manager at risk (CMAR) can advise the owner during design on cost, procurement, constructability, and phasing. In the construction phase it is the constructor, usually contracting with trade subcontractors for the construction scope it accepts. AIA A133–2019 pairs preconstruction services with cost of the work plus a fee and a GMP. The cap applies to the scope and assumptions in the agreement and can change under contract procedures. In the related AIA A134–2019 form, the construction manager is also the constructor, with a cost-plus arrangement without a GMP.

A construction manager as adviser (CMa) provides services such as estimating, scheduling, and coordination. The owner contracts with the builders. AIA C132 and A232–2019 address an advisory arrangement commonly used with multiple prime construction contractors. An adviser remains accountable for its own contracted services. Look for the construction obligation and the party that holds the trade contracts before deciding whether a question describes a CMa or a CMAR.

Design–build

In design–build (DB), the owner contracts with one design-builder for design and construction. The design-builder organizes its design and trade teams. Clear owner criteria are essential because they describe the performance, constraints, or program the team must meet. AIA A141–2024 uses Owner’s Criteria and a design-build amendment to establish the contract sum. The Design-Build Institute of America (DBIA) uses Owner’s Project Criteria in its progressive design-build agreement. The criteria may include preliminary or bridging design information if the owner chooses that approach. An owner can also retain an independent adviser. A single point of responsibility simplifies routing issues to the builder, while scope and risk allocation still depend on the contract.

Owner–build and multiple prime contracts

In owner–build, the owner performs the general contractor role, coordinating work performed by its own forces, separately hired contractors, or both. The owner can control when packages are released and how interfaces are managed, but must provide or procure those management capabilities. Multiple-prime contracting describes the owner holding several direct construction contracts. An owner may retain a CMa to coordinate a multiple-prime project. In either case, identify who schedules shared resources and resolves conflicts between trades before concluding that removing a prime contractor reduces total cost or risk.

Integrated project delivery

Integrated project delivery (IPD) brings core parties into early collaboration and can tie compensation to common goals. For example, AIA C191–2009 is a multiparty form in which the owner, architect, contractor, and any other named participants execute one agreement and establish common performance and cost targets. Other AIA integrated forms use separately executed agreements or a single-purpose entity. Read the selected form for governance, incentives, and any liability provisions.

Delivery methodFollow the contractsTrade-off to evaluate
Design–bid–buildOwner retains designer and construction prime separatelyCommon documents for bidding, with construction procurement generally following design
Construction management at riskOwner retains designer and CMAR. CMAR provides preconstruction input and contracts to buildEarly pricing and phasing input. Define assumptions and exclusions before agreeing to a GMP
Design–buildOwner contracts with design-builder for both servicesSingle point of responsibility. Define and verify owner criteria
Owner–buildOwner acts as general contractor, possibly with direct trade contractsMore control over packages. Owner must manage their interfaces
Integrated project deliveryIn a multiparty form, core parties sign one agreement with joint goalsAlign incentives and establish governance. Check applicable public procurement constraints

A hospital owner with an immovable opening date may release a completed foundation package before interior design finishes. This fast-track approach can shorten elapsed time. Set a clear release boundary and confirm loads, access, and connection details. A late equipment change can affect a foundation already under construction, regardless of who holds the prime contract.

References CSI Project Delivery Education Program, EJCDC E-500, AIA C132–2019, AIA A141–2024, DBIA 544, and AIA integrated project delivery forms.

Loading diagram...
Typical contract relationships for five delivery methods
Test Your Knowledge

An owner wants to keep a separate architect and hire a manager who will advise on cost and phasing during design, then contract to build and hold trade subcontracts under a guaranteed maximum price. Which arrangement best fits?

A

Construction management as adviser

B

Construction management at risk using a cost-plus GMP form

C

Traditional design–bid–build

D

Owner–build with direct trade contracts

Test Your Knowledge

Which feature distinguishes design–build from traditional design–bid–build with one construction prime?

A

The owner signs separate prime design and construction agreements.

B

The construction prime is selected after the owner’s separate architect completes bidding documents.

C

The owner serves as general contractor for the trades.

D

The owner contracts with one entity for both design and construction.

Test Your Knowledge

What feature is characteristic of the multiparty integrated project delivery model in AIA C191–2009?

A

Core parties sign one agreement and use jointly established cost and performance goals.

B

The owner awards a construction-only contract after opening sealed low bids.

C

A construction adviser holds the prime trade contracts.

D

The owner acts as general contractor and pays each trade under a separate contract.