14.2 Submittals: Shop Drawings, Product Data, Samples & Review

Key Takeaways

  • For required reviewed submittals, the contractor checks and approves before sending them to the architect.

  • Under A201–2017, shop drawings, product data, and samples are not Contract Documents by reason of being submitted or approved.

  • A contractor must identify a deviation at submission and obtain the applicable specific authorization.

  • Delegated design and substitution involve additional requirements under the actual contract.

Last updated: November 2026

Identify what is being submitted

Under AIA A201–2017 §§ 3.12.1–3.12.4, shop drawings are prepared for the particular work, such as project-specific steel fabrication details. Product data can include standard illustrations, performance charts, or instructions showing the materials or equipment. Identify the model and configuration. Samples are physical examples that can establish criteria for materials and workmanship. These documents describe how the contractor proposes to conform to incorporated requirements. Their submission or approval does not make them Contract Documents.

Read the project’s submittal schedule and procedures. They can distinguish shop drawings needing review and action, reports submitted for information, and closeout records. Required warranty documents and maintenance information can be due at specified handover milestones. UFGS 01 33 00 provides an example of government, design-builder and information-only classifications. A label and the required action vary by contract.

Check, submit and review

  1. Contractor review. Under §§ 3.12.5–3.12.6 the contractor reviews for compliance, approves and submits required items. The contractor represents it has checked and coordinated the information and has determined and verified, or will determine and verify, related materials, field measurements and field criteria. Apply the project’s review markings when required.
  2. Architect’s action. Under § 4.2.7, review of contractor shop drawings, product data or samples checks conformance with information and design concept in the Contract Documents. Schedule the review according to the clause. The architect’s review does not transfer responsibility for field quantities, dimensions or safety. Approval of a component does not indicate approval of the assembly that contains it.
  3. Release affected work. Under § 3.12.7, work that requires these submittals and review cannot proceed until the applicable architect approval. Interpret action labels using the actual project definitions. If the result requires resubmission, correct the listed issues and identify other revisions at resubmission under § 3.12.9. Distribute current returned submittals to the affected parties.
  4. Track exceptions. Keep each decision linked to the correct version, and check any additional authorizations before ordering, fabricating or installing work with a changed requirement.

For a door assembly, the contractor can verify the opening, identify the frame anchors and glazing and coordinate hardware before submitting. If the architect marks a sample acceptable, the contractor still must provide the assembly required by the contract. If the proposed unit will not fit the opening, route the discrepancy as early as possible.

Identify deviations and delegated design

Under A201 § 3.12.8, the contractor remains responsible for deviations unless two conditions are met. First, it specifically notifies the architect at the time of submittal. Second, it obtains the architect’s written approval of the specific deviation as a minor change or authorization in an issued Change Order or Construction Change Directive. Keep the notice and decision in the project record. A general review stamp does not authorize an undisclosed difference, nor does approval remove responsibility for errors or omissions in the submittal. EJCDC C-700–2018 § 7.16 uses its own procedures for shop drawings and samples, including separate written notice of variations. Follow the adopted version and project requirements.

Where professional design is specifically delegated under A201 § 3.12.10.1, the owner and architect establish design and performance criteria. The contractor obtains services from an appropriately licensed professional. That professional signs and seals the design documents and related submittals it prepares and provides written approval when others prepare related shop drawings or submittals covered by the clause. Architect review remains limited to the contractually specified information and design concept.

Route substitution requests separately

Under A201 § 3.4.2, a substitution ordinarily needs owner consent, architect evaluation, and a Change Order or Construction Change Directive. Check the minor-change exceptions in §§ 3.12.8 and 7.4. Follow the project procedures for evaluating equivalent performance, interfaces, cost and schedule. Identify all affected scope before authorizing fabrication. A request sent only as routine product data can leave a change and its impact undisclosed.

Plan for a returned submittal

If a steel submittal returns with a request for revision, identify exactly which connection the review addressed. Update the shop drawing and coordinate related sheets, then re-submit in time for the applicable review period. If the fabricator also changes a connection the architect did not ask it to revise, call attention to that change under § 3.12.9. Track which issue is approved so the shop does not fabricate from an obsolete file.

References AIA A201–2017 §§ 3.4.2, 3.12 and 4.2.7, EJCDC C-700 § 7.16 comparison, and UFGS 01 33 00.

Loading diagram...
Review and release required submittals
Test Your Knowledge

A contractor submits steel shop drawings showing a different connection but does not identify the deviation. The architect issues routine approval. What is the result under unmodified AIA A201–2017 § 3.12.8?

A

Approval transfers responsibility for the deviation to the architect.

B

The contractor remains responsible because the deviation was not specifically disclosed and authorized under the clause.

C

The owner automatically accepts the different connection.

D

The shop drawings supersede the applicable contract documents.

Test Your Knowledge

Which is within the architect’s ordinary A201–2017 § 4.2.7 shop drawing review?

A

Check conformance with information and design concept expressed in the Contract Documents.

B

Assume the contractor’s responsibility for verifying every fabrication dimension.

C

Select field safety precautions for the installer.

D

Approve each assembly solely because one component was approved.

Test Your Knowledge

An A201–2017 project proposes a different air-handling unit that changes the specified work and requires a price adjustment. The change does not qualify as minor. How should the contractor proceed?

A

Hide the unit change in routine product data.

B

Obtain a verbal instruction and treat it as owner approval.

C

Submit the request under the contract procedure and obtain architect evaluation, owner consent and the applicable Change Order or Construction Change Directive.

D

Identify it for the first time in the closeout manual.