6.3 Building Information Modeling (BIM) in Design & Coordination

Key Takeaways

  • A Building Information Model can connect geometry, schedules, quantities, and attributes. Check which information is available and authorized for the proposed use.

  • AIA G203–2022 helps document the BIM Execution Plan, and a Model Element Table can specify Level of Development by element and milestone.

  • Level of Development 350 can support interface coordination. Level 500 describes existing or as-constructed conditions with accuracy stated.

  • AIA E201–2022 can allow specified model versions to be enumerated as contract documents. E202–2022 is for project sharing without such enumeration.

Last updated: November 2026

What a model can tell you

Building Information Modeling (BIM) uses digital information to describe and coordinate a facility. A door model element can carry size, location, and attributes such as a rating or a reference to another deliverable. A change to a parameter can update coordinated views and schedules generated from it. Review linked files, exports, schedules, and written requirements after revisions so that all issued information remains consistent.

Use the classification agreed for the task. UniFormat organizes functional elements, which can support comparison of building systems at an early stage. OmniClass offers separate classifications for information such as elements, products, and spaces. MasterFormat organizes work results and can provide a reference to written specifications. For exchanges between applications, Industry Foundation Classes (IFC) is an open data standard. Check whether the receiving application retains the properties, units, and geometry required for the exchange.

BIM Execution Plan and Model Element Table

The BIM Execution Plan (BEP) describes how the team will produce, share, and check model information. A project plan can establish:

  • Uses such as model authoring, coordination, time-linked sequencing (4D), model-based estimating, or data exchange for facility management.
  • Responsibility for producing elements, maintaining native models, reporting conflicts, and accepting updates.
  • Exchange rules such as a common origin and units, file formats, revision identification, dates, and checks after import.
  • Element requirements for the information and reliability needed at defined project milestones.

In AIA’s 2022 forms, G203 provides a BEP framework and G204 a Model Element Table. E201 permits eligible model versions to be identified as contract documents when the agreement follows the required procedure. E202 provides for model sharing among participants without enumeration as contract documents. E401 and E402 address sharing within the design and construction teams, respectively. AIA retired E203–2013 and G202–2013 in July 2024. For an existing agreement incorporating older forms, use the documents the parties actually adopted.

Level of Development depends on the element

A Level of Development (LOD) indicates what an element contains and what can be measured or relied upon. A visually detailed object may still have an approximate location. Assign the required level by element, exchange, and purpose. BIMForum’s 2025 specification leaves project teams to set the milestones and responsible authors.

LODWhat to expectExample for a building system
100Concept information. A symbol or related model data may indicate approximate requirementsApproximate plant capacity or reserved zone
200Recognizable generic geometry with approximate size and locationGeneric equipment volume for comparing room layouts
300Designed geometry sufficiently developed to measure the required element geometryDesigned chiller footprint and location
350Geometry also describes measurable interfaces with adjacent or dependent elementsEquipment connection interfaces and supporting geometry for coordination
400Information sufficient for fabrication, assembly, or installation as specified for the elementTrade fabrication model for a pipe spool
500Existing or as-constructed condition captured with stated accuracyObserved equipment location with the measurement basis and accuracy documented

LOD 500 answers a different question about observed conditions and accuracy. An owner can separately specify which asset identifiers, maintenance data, and warranty information are needed at turnover. The element’s number alone does not supply those records or authorize its use for construction.

Federated coordination and follow-up

A federated model brings discipline models into a common view while allowing each team to maintain its source files. A shared origin and current versions are prerequisites for meaningful automated checks. Confirm the modeled boundaries, tolerances, and exclusions before relying on the results.

  1. Physical clash. Two objects overlap in the model, for example a duct intersects a beam.
  2. Clearance clash. Objects do not touch, but one enters a service, access, or code clearance zone modeled for the other.
  3. Sequence clash. A time-linked review shows a conflict in when work can occur, for example a wall closes an access route before equipment is brought in.

An automated check flags an issue. The team reviews it, assigns the responsible author, updates the applicable source model and related documents, and verifies the resolution in the next exchange. If a pipe enters an electrical clearance envelope, confirm the required clearance and intended route before accepting the repair. A known clash belongs in the project’s coordination record until it is resolved or an authorized decision is made.

What bidders can rely on

Check the model exhibit, named version, any enumerated portion, and the permitted uses. A model issued only for reference helps a bidder visualize the work. The incorporated contract documents govern the scope. Where the agreement makes a particular model version a contract document, consult that version and the contract procedure for resolving discrepancies. Identify each requirement for submittals, tests, materials, and warranties in the applicable documents or authorized data. Maintain the connection between model references and written requirements through revisions.

References NIBS BIM Execution Planning, AIA 2022 BIM documents and retirement notice, AIA Digital Practice Documents Guide, BIMForum 2025 LOD Specification, and buildingSMART IFC.

Loading diagram...
BIM Coordination and Clash Resolution Workflow
Test Your Knowledge

The model element must show measurable designed geometry and measurable interfaces with adjacent elements for coordination. Which BIMForum level describes that requirement?

A

LOD 200 (Approximate Geometry)

B

LOD 350 (Interfaces and Coordination)

C

LOD 100 (Conceptual)

D

LOD 500 (Existing or As-Constructed with Stated Accuracy)

Test Your Knowledge

A pipe clears the solid geometry of a switchgear lineup but intrudes into its required, modeled working space. What kind of clash did the review find?

A

A workflow (4D) clash

B

A physical (hard) clash

C

A clearance (soft) clash

D

An LOD 500 as-built variance

Test Your Knowledge

A project uses AIA E202–2022 and shares a model solely for reference during bidding. What controls whether the bidder may rely on the model as a contract document?

A

The agreement and BIM exhibit control reliance. Under E202, model versions cannot be enumerated as contract documents.

B

Distributing any 3D BIM file to bidders automatically supersedes all written MasterFormat specifications in the Project Manual

C

Once a BIM model reaches LOD 300, contractors may omit shop drawings and submittals because the model replaces fabrication review

D

Models shared for coordination automatically shift statutory design-coordination liability from the Design Team to the Owner