9.2 Division 01: General Requirements

Key Takeaways

  • Division 01 is part of the Specifications Group and usually houses project-wide procedures.

  • Coordinated payment requirements explain how to submit values and evidence of work. The agreement establishes the payment basis and terms.

  • Submittals carry different purposes and require the routing and review defined by the project.

  • Check the extent to which technical sections add work-specific requirements to common procedures.

Last updated: November 2026

Read a requirement from the conditions through the work section

Division 01 General Requirements is the first division of the Specifications Group. It describes procedures that can apply across the construction work. A project may put electronic file format, delivery, and tracking for submittals in one section. The section specifying doors then identifies the actual door information to submit.

The conditions and agreement can establish authority, deadlines, contract price, and remedies, while general requirements give practical details for carrying them out. A document’s subject and contractual incorporation both matter. Division 01 can contain enforceable duties. Coordinate it with the conditions and ask for an approved clarification when the two appear to conflict.

Find the applicable Division 01 series

The following series illustrate common placements. Check the project’s index. Some projects choose more specific numbers and titles for the same type of requirement.

SeriesFunctionExamples
01 10 00 SummaryDefines overall work and relevant site constraintsSeparate contracts, owner-furnished equipment, occupied-area phasing, use of premises
01 20 00 Price and Payment ProceduresDescribes administrative requirements for price and changesAllowances, unit prices, alternates, substitutions, change documentation and applications for payment
01 30 00 Administrative RequirementsCoordinates communication, project schedules, and submittalsCoordination meetings, RFIs, progress schedules, submittal routing
01 40 00 Quality RequirementsEstablishes common quality proceduresReferences, qualifications, testing and inspection duties, reporting
01 50 00 Temporary Facilities and ControlsAddresses temporary site facilities and restrictionsAccess, temporary utilities, enclosures, erosion controls, security
01 60 00 Product RequirementsAddresses general product selections and handlingDelivery, storage, protection, and documentation
01 70 00 Execution and CloseoutDescribes common execution and handover requirementsWaste management, record documents, operation and maintenance data, warranty records, training
01 80 00 Performance RequirementsAddresses facility performance spanning systemsEnergy or sustainability requirements where included
01 90 00 Life Cycle ActivitiesAddresses life-cycle activities such as commissioningRoles, commissioning plan, testing coordination and closeout records

01 21 00 Allowances can state a dollar amount within the Contract Sum for a defined item whose actual cost is unresolved. Under AIA A201–2017 § 3.8, verify what the allowance covers and how scope or actual cost differences are handled. An owner should know whether the price carried is for the equipment only or also includes work to install it. 01 22 00 Unit Prices can establish a rate for measured work. Use the agreement to determine how measured quantities and any changes are paid. 01 23 00 Alternates forms a common description of an addition, deduction, or variation separately priced from base scope. Compare it with the bid form and accepted alternates in the agreement.

01 25 00 Substitution Procedures can state the evidence, route, and timing for requests. Procurement instructions control their own bidding provisions. 01 26 00 Contract Modification Procedures can outline the steps for notices, proposal support, draft change documents, and approved changes. The applicable contract establishes who can authorize a change. 01 29 00 Payment Procedures can address the format of supporting documents such as a schedule of values, application, or stored-material evidence. Use the actual contractual requirements for payment calculations, waivers, and review.

Give submittals a purpose and a route

01 33 00 Submittal Procedures can distinguish action submittals such as shop drawings requiring review from informational submittals such as reports supplied for defined project records. Check the actual classification and procedure. The U.S. Department of Defense’s UFGS 01 33 00 uses a publication-specific set of classifications, including government-approved and information-only submittals. A designer should coordinate review responsibility, required file identifiers, and the schedule before work is purchased or fabricated.

For an AIA A201–2017 project, the Contractor checks and coordinates its submittals under § 3.12. Under § 4.2.7 the architect’s review of shop drawings, product data, and samples is limited to conformance with information and the design concept expressed in the Contract Documents. The contractor remains responsible for its dimensions, quantities, and other contract obligations. The architect acts in accordance with the approved schedule or with reasonable promptness under the clause when no schedule is approved.

Apply the series to a handover

A control system may need a published submittal schedule and testing reports, a specific demonstration of its functions, and records for operations staff. Division 01 can establish common preparation, transmittal, and training procedures. The controls specification can identify the particular systems, manuals, test points, and demonstration tasks. VA Section 01 91 00 General Commissioning Requirements, for example, coordinates schedules, system identification, and commissioning documentation. Align the lists so the facility team can connect each item to the installed equipment and the applicable operating instructions.

References AIA A201–2017 §§ 3.8, 3.12, 4.2.7 and Articles 7 and 9, Fayetteville issued Project Manual index, City of Mobile allowance example, UFGS 01 33 00, and VA 01 91 00.

Loading diagram...
How conditions, procedures, and technical requirements work together
Test Your Knowledge

Which requirement is most directly suited to a project-wide Division 01 submittal procedure?

A

The contractor’s indemnification obligation

B

The required electronic submission format and naming convention for shop drawings

C

The owner’s right to terminate for convenience

D

The statutory period for filing a latent defect claim

Test Your Knowledge

Every bidder must include $40,000 for decorative light fixtures that the owner will select after bidding. Which commonly numbered Division 01 section describes that pricing device?

A

01 23 00 Alternates

B

01 22 00 Unit Prices

C

01 25 00 Substitution Procedures

D

01 21 00 Allowances

Test Your Knowledge

The owner requires a consistent index for all maintenance data and equipment-specific belt and filter schedules for the units installed. Where should the specifier place the requirements?

A

Put the common indexing and turnover procedure in Division 01 and coordinate the equipment-specific data with the applicable technical sections.

B

Put the common index in the contract’s insurance exhibit and the equipment schedules in the bid form.

C

Place the common index in the structural steel section and omit the product-specific requirements.

D

Place both requirements only in the invitation to bid.