6.2 Design QA/QC & Product Evaluation and Selection

Key Takeaways

  • Quality assurance establishes processes that give confidence in results. Quality control checks work or documents against requirements and follows up on deficiencies.

  • Effective QC checks cross-reference drawing tags against schedules, enforce consistent terminology between drawings and specifications, and verify code and accessibility clearances prior to bidding

  • Use the relevant test standard, listing or report, and verify that the evidence applies to the proposed assembly, not just a component.

  • Compare interfaces, lead time, maintenance, warranty, and any required disclosures. Follow the applicable procurement restrictions before naming a single source.

Last updated: November 2026

A quality plan makes document errors easier to find and correct before release. Design reviews catch issues such as conflicting door ratings across a plan, schedule, and specification. Product evaluation checks whether the assembly the documents call for can actually meet the project’s requirements.

Quality Assurance (QA) vs. Quality Control (QC) in Design

Although practitioners often use "QA/QC" as a single phrase, the functions place emphasis on different activities:

  • Quality Assurance (QA) is proactive and process-focused. It establishes the firm-wide and project-specific systems, standards, and workflows that give confidence the resulting documents will meet requirements.
  • Quality Control (QC) is verification- and deliverable-focused. It verifies work or actual deliverables against requirements and follows up on defects. Checks can occur during production as well as before issue.

Proactive Quality Assurance (QA) Mechanisms

Effective design QA embeds quality into daily production through repeatable infrastructure:

  • Office CAD and BIM Standards: Enforcing uniform layer naming, sheet numbering, symbol libraries, and drawing organization consistent with the United States National CAD Standard (NCS).
  • Master Guide Specifications: Maintaining vetted office master specifications structured under MasterFormat, SectionFormat, and PageFormat, updated regularly for current referenced standards and building codes.
  • Phase-Specific Design Checklists: Standardizing code-analysis templates, envelope-continuity checklists, and Division 01 coordination matrices tailored to the project delivery method.
  • Staffing and Peer-Review Gates: Assigning experienced technical leads and independent peer reviewers (practitioners not immersed in daily drafting) to review at the milestones in the project’s quality plan. An independent review can bring a fresh perspective to high-impact interfaces.

Deliverable-Focused Quality Control (QC) Checks

Tailor deliverable checks to the package and risk:

  • Discipline Red-Line Checks: Senior architects and engineers mark up plans, sections, details, and calculations—followed by documented back-checking to verify every mark was resolved.
  • Tag-to-Schedule Cross-Checking: Verifying that every door, window, louver, finish, plumbing fixture, and mechanical equipment tag shown on plans matches the exact designation, size, fire rating, and hardware group in the corresponding schedule.
  • Drawing-to-Specification Consistency: Confirming identical terminology across graphic and written documents (for instance, never calling an assembly "elastomeric roof coating" on details while specifying "fluid-applied membrane roofing" in Division 07), and ensuring drawings depict locations and quantities while specifications govern quality, materials, and workmanship.
  • Code, Accessibility, and Overlay Audits: Checking fire-barrier continuity, egress travel distances, Americans with Disabilities Act (ADA) Standards and ICC A117.1 door-maneuvering clearances, and multidisciplinary overlays (such as structural beam depths against ductwork soffits).

Comparing Design Quality Assurance (QA) and Quality Control (QC)

DimensionQuality Assurance (QA)Quality Control (QC)Primary Timing
Core OrientationProactive; prevents defects by governing how work is producedVerification-focused; detects and corrects defects in completed workQA: Continuous/upfront; QC: Pre-issue milestones
Primary TargetOffice standards, workflows, staffing, and review gatesActual drawings, schedules, BIM models, and Project Manual textQA: System-wide; QC: Deliverable-specific
Typical ToolsNCS CAD/BIM standards, master guide specs, phase checklistsRed-line markups, tag/schedule matrices, overlay checks, spec auditsUse the milestones set in the quality plan
Key PersonnelFirm QA director, discipline leads, independent peer reviewersSenior checkers, specifiers, and discipline coordinatorsAssign review responsibility based on risk and agreement

Evidence-Based Product Evaluation and Selection

A product comparison should use evidence relevant to required performance, compatibility, procurement, and operation. Review these criteria before selecting the assembly:

  1. Tests and listings. Identify the applicable test method and edition. Compare the test report, certification, or listing with the proposed assembly. For a fire-resistance-rated wall, review the complete listed design and any permitted variations in the documentation. A tested or listed component alone cannot establish the rating of every assembly that includes it.
  2. Interfaces and compatibility. At an opening, trace the air, water, and thermal control layers across the frame, flashing, and wall. Check applicable installation instructions, joint movement, and material compatibility.
  3. Durability and service. Compare expected service life, maintenance tasks, availability of replacement parts, and the facility staff’s ability to service the system.
  4. Timing and installers. Verify lead times, required qualifications, and whether the proposed system fits the work sequence. Give the estimator and scheduler a dated basis for their assumptions.
  5. Environmental and health evidence. An Environmental Product Declaration (EPD) discloses environmental impacts within a defined scope. A Health Product Declaration (HPD) reports ingredients and associated hazard information under its method. Check the project’s separate emissions or volatile organic compound (VOC) criteria. Documentation and formats such as GreenFormat help organize evidence for an evaluation.
  6. Warranty terms. Check what the warranty actually covers, including labor and materials, exclusions, prerequisites, and remedies.
  7. Competition. Evaluate available products and define measurable criteria. For an applicable federal procurement, FAR 11.104 requires salient characteristics for a brand-name-or-equal description, and FAR 11.105 governs requirements peculiar to one manufacturer. Confirm the rules that apply to the project and what justification or approval they require.

Structured Product-Evaluation Checklist

Evaluation CriterionRequired Verification EvidenceCommon Pitfall to Avoid
Code & PerformanceRelevant test standard and reports or listings that match the proposed useRelying on unverified sales brochures or non-comparable test assemblies
Substrate InterfacesManufacturer-tested transition details, flashing compatibility, and movement jointsSelecting isolated components without detailing air, water, and thermal continuity
Lifecycle & SupportExpected service life, maintenance manuals, spare-part availability, and sample warrantyChoosing low first-cost products with prorated warranties or orphaned parts
Market & SustainabilityAvailable suppliers, lead times, required installer qualifications, and applicable disclosuresCreating single-source traps or specifying long-lead items invisible to the schedule

References ASQ quality assurance and control, UL rated assemblies, EPA environmental declarations, Health Product Declaration Collaborative, FAR 11.104, and FAR 11.105.

Test Your Knowledge

Before issuing 90 percent Construction Documents for final Owner review, a senior architect compares every door tag on the floor plans against the Door Schedule and checks that terminology in the wall sections matches Division 09 specifications. Which quality function does this activity represent?

A

Proactive Quality Assurance (QA), because it establishes firm-wide CAD layering standards

B

Deliverable-focused Quality Control (QC), because it verifies and corrects completed project documents before issue

C

Value analysis, because it reduces the total number of doors to lower capital cost

D

Post-occupancy commissioning, because it tests hardware operation after substantial completion

Test Your Knowledge

A sales representative recommends a newly introduced exterior wall panel based on sleek project renderings and a quote 18 percent lower than established systems. Which evaluation step is most critical before including the product in Construction Documents?

A

Accepting the verbal quote as a binding lump-sum subcontract price for bidding

B

Specifying the product by brand name alone so bidders cannot propose alternatives

C

Replacing all flashing details on the architectural drawings with a note deferring interface design to the installer

D

Verify the applicable tests and assembly listings, review interfaces, check availability and warranty terms, and identify feasible sources.

Test Your Knowledge

A federal procurement subject to FAR 11.105 proposes to specify a feature available from only one manufacturer. What must the agency establish before excluding other sources?

A

The feature is essential, market research supports the restriction, and the applicable justification or approval requirements are met.

B

The architect names the product, which automatically authorizes a federal competition exception.

C

The owner has obtained three unrelated quotes, which removes the need to justify the named product.

D

The named feature appears in a MasterFormat section, which makes it a federal specification exception.