12.2 Basis of Payment, Pricing & Purchasing
Key Takeaways
Price certainty depends on the defined scope and adjustment terms. A GMP caps covered costs and can change under its contract.
Pay unit-price work according to eligible actual quantities and the applicable rate or adjustment rule.
Review line items as well as the total when checking for unbalanced pricing.
Freight cost, risk of loss, and title are separate issues. Confirm the governing law, delivery terms, and risk provisions.
Match the payment basis to the pricing risk
| Basis | How payment is determined | What to verify |
|---|---|---|
| Stipulated sum | Agreed price for defined work, subject to authorized adjustments | Scope limits and agreed exclusions. AIA A101–2017 is an example |
| Cost of the work plus fee without GMP | Allowable cost plus fee defined in the agreement | Cost exclusions, documentation and fee calculation. AIA A103–2017 is an example |
| Cost of the work plus fee with GMP | Allowable cost and fee subject to the cap for agreed scope | GMP basis, allowances, contingencies, cost records, and permitted adjustments. AIA A102–2017 and A133–2019 are examples |
| Unit price | Actual eligible quantities times the contractual rates, subject to adjustments | Unit definitions, estimated versus measured quantities, and rate adjustment rules such as C-700 § 13.03 |
| Time and materials (T&M) | Specified labor rates times eligible hours plus material costs as defined | Time records, materials, required approvals and any ceiling. Federal T&M contracts under FAR 16.601 require a ceiling |
A lump sum can fix a released scope without covering future packages. A GMP similarly depends on the agreed drawings, assumptions and limits. Review the actual terms for allowable costs, audits, and any shared savings. For a cost-reimbursement basis, neither a fixed fee nor a percentage fee by itself creates a maximum. For retainage, consult the agreement and governing law. Under AIA A101–2017 § 5.1.7, the parties fill in retainage terms. Under a federal contract with FAR 52.232-5(e), satisfactory progress calls for full progress payment and unsatisfactory progress can justify withholding up to 10% of the payment. Check the separate substantial completion and release provisions. Retainage is one payment term rather than a payment basis.
Test bid pricing before award
A bid tabulation can compare base price, alternates, unit prices, extended amounts, contract time and evidence required by the solicitation. Compare against independent estimates and review unusual entries. Apply the actual arithmetic or precedence rules. For instance, AIA A701–2018 § 4.1.3 gives precedence to words when words and numbers differ under its bid-form rule. A rule about unit rates and extensions must come from the applicable bid documents.
Unbalanced pricing can exist when an acceptable total conceals significantly high or low line prices. A high early payment such as mobilization can be front-loading. A high rate on an item likely to exceed the estimate can change the total cost at actual quantities. Under FAR 14.404-2(g), materially unbalanced line items can justify rejection. Analyze the evidence and risk under the applicable rule.
Consider two hypothetical bids. Other items cost $80,000 for A and $95,000 for B. Rock excavation rates are $180 and $100 per cubic yard. At 100 cubic yards the evaluated totals are $98,000 and $105,000. At 200 cubic yards, assuming no change in rates, they become $116,000 and $115,000. A’s evaluated lead of $7,000 becomes a $1,000 higher total if the quantities double. This sensitivity flags a risk to investigate. It does not establish the bidder’s intent or an automatic right to reject.
Buy, expedite, and verify materials
A purchase order can form part of the purchase contract. Identify scope and approved product requirements, permitted substitutions, delivery, acceptance, payment, warranty, and changes. Before releasing fabrication, confirm the approved information, lead-time commitments, and schedule dependencies. Track fabrication and any specified tests and shipment or receiving inspections. For direct purchasing by a tax-exempt owner, confirm applicable law and who will order, pay for, insure, receive and take responsibility for the goods before pricing any savings or contract credits.
For a domestic sale of goods governed by New York’s UCC, §§ 2-319 and 2-509 distinguish shipment and destination obligations. If a conforming shipment is duly delivered to the carrier under a FOB shipping point contract with no contrary terms, transit risk generally passes to the buyer there. Under FOB destination, the seller bears the risk until due tender at the specified destination. A prepaid freight arrangement by itself need not alter the risk allocation. Title is analyzed separately under § 2-401 and any explicit agreement. Check applicable provisions if there is a breach.
An owner can pay for stored equipment before installation if the contract allows. AIA A201–2017 § 9.3.2 addresses suitably stored materials and equipment. Off-site payment requires the owner’s advance approval and a location agreed in writing. Protect the owner’s title or interest as required and address applicable insurance, storage, and transportation. Confirm the purchased equipment and storage evidence before relying on it in an application for payment.
References AIA owner–contractor agreements, AIA A101–2017 instructions, AIA A201–2017 § 9.3.2, AIA A701–2018 § 4.1.3, FAR 16.601, FAR 14.404-2, FAR 52.232-5, New York UCC § 2-319, § 2-509, and § 2-401.
The owner wants reimbursement of allowable construction costs and fee, documented buyout, and a ceiling for an agreed scope. Which basis fits?
Stipulated sum without allowances.
Cost plus fee without a GMP.
Cost plus fee with a GMP.
Unit pricing for estimated rock quantities.
A federal bid tabulation shows an acceptable overall amount, substantially above-market mobilization and rock excavation, and below-market backfill. What should the contracting officer examine?
Potential unbalanced pricing and the effect of payment timing and changed quantities on total risk.
Whether these prices were an accepted deductive alternate.
Whether this is a tax-exempt direct purchase.
Whether AIA’s material allowance automatically adjusts all unit rates.
A domestic goods contract governed by New York’s UCC uses FOB shipping point. The seller prepays freight and duly delivers conforming units to the carrier. There is no contrary risk term or breach. Who bears the contract risk of loss in transit?
Architect, because the units were specified in Division 23.
Seller, because it prepaid freight.
Building official, because acceptance inspection is pending.
Buyer, because the units were duly delivered to the carrier under the shipment contract.