13.3 Preconstruction Meetings & Communication Protocols

Key Takeaways

  • Confirm roles, notices, schedule, reviews, payment and site logistics before the first affected work.

  • EJCDC C-700–2018 § 2.04 requires written designation of authorized owner and contractor representatives at the conference.

  • AIA A201–2017 § 4.2.4 routes communications with subcontractors through the contractor unless another protocol is specified.

  • Meeting records document discussions and actions. Use the applicable contractual authority for changes.

Last updated: November 2026

Prepare before the first site work

A preconstruction conference establishes how the parties will carry out the project’s required administrative procedures. Read the contract before assigning attendees, dates or authority. EJCDC C-700–2018 § 2.04 calls for a conference with the owner, contractor, engineer and others as appropriate before work at the site starts. The owner and contractor designate an authorized representative in writing at the meeting. It also addresses schedules, submittals, pay applications, digital transmittals and records. The cited UFGS 01 30 00 § 1.8 is a federal example of a differently organized preconstruction meeting requirement.

Invite people who can settle the procedures or identify unresolved decisions. The owner can confirm access and occupancy restrictions. The contractor’s project manager and superintendent can explain workflow and schedule needs. The designer can identify review responsibilities. Invite testing or commissioning representatives where their early coordination matters.

Confirm routes, deadlines, and authority

Agenda itemQuestions to settle against the contract
Authority and communicationsWho may act, who receives formal notices, how routine requests are transmitted, and what proof of delivery is required
Progress and accessWhich date starts the work, what milestones apply, where site access is available, and what occupied-area constraints apply
Submittals and RFIsWho checks and routes them, the agreed or contractual time for review, document identifiers and where responses are stored
PaymentSchedule of values, billing cutoffs, supporting documents, stored-material procedures, and any stipulated retainage
ChangesRequest for pricing versus authorization, applicable change instruments, and assignment of decisions
Site logistics and testingWork limits, shutdown requests, emergency contacts, required test notification, and protection of occupants

Under AIA A201–2017 § 4.2.4, communications with subcontractors and suppliers go through the contractor unless other protocols are specified. Communications between owner and contractor that affect the architect’s services include the architect. The clause addresses owner notice to the architect about other direct project communications. For claim notices, § 1.6.2 specifies written delivery by certified or registered mail or courier with proof of delivery. Check agreed electronic methods for ordinary notices under § 1.6.1. A portal message used for a routine RFI does not automatically serve as a claim notice.

Under A201 § 3.12.6, contractor submission represents that it reviewed and approved the submittal, verified or will verify applicable materials and field information, and coordinated it with requirements. The project’s procedure can require evidence of that review, such as a stamp. Check the approved submittal schedule and the architect’s RFI response rules under § 4.2.14. Record the actual deadlines for the project.

Record the actions and follow through

Meeting minutes can state what was checked, who follows up, and what is still pending. Record a request to price a change as a request. Route any binding change through the contract procedures. If the project chooses an informal draft payment review, sometimes called a pencil-copy review, use it to identify disputed progress, missing evidence for stored materials, or inconsistencies with the schedule of values. Submit the formal payment application separately and follow the contract for the architect’s or engineer’s action and the owner’s payment.

For example, record a proposed Saturday utility shutoff as pending until the representative authorized to approve it confirms the time and affected users. Assign the contractor to identify the impacted systems and update the schedule. Route any resulting change in price or time under the contract. Treat issues that could affect the first work as separate action items. For an occupied building, confirm isolation boundaries, access for emergency response, shutdown authorizations and the required inspection or test holds. The contractor’s duties for site operations and safety follow the contract and law even when others participate in planning the site.

Assembly-specific preinstallation conferences

A preinstallation conference deals with a particular system before the work it covers. For a roof, check the contract for attendees, allowable weather and substrate conditions, details, products, testing and warranty inspections. Resolve the interface between the roofer and adjacent work before starting. Use the meeting record to track outstanding checks. The project-wide conference establishes coordination procedures, and the assembly-specific meeting applies them to a narrower installation.

References EJCDC C-700 base § 2.04, AIA A201–2017 §§ 1.6, 3.12, 4.2 and Articles 7 and 9, UFGS 01 30 00 § 1.8, and UFGS 07 55 00 § 2.1.2 pre-roofing conference.

Loading diagram...
Use the communication route required by the contract
Test Your Knowledge

On an unmodified AIA A201–2017 project, an architect finds a conduit location that needs clarification. What communication route does § 4.2.4 specify for conveying it to the subcontractor?

A

The architect directly instructs the trade foreman.

B

Route communications with the subcontractor through the prime contractor.

C

Wait until substantial completion to report the issue.

D

Have the commissioning provider issue the instruction.

Test Your Knowledge

The team has agreed to a draft payment walkthrough before formal submission. What is its purpose?

A

Revise line-item totals unilaterally.

B

Replace the required formal payment application.

C

Compare claimed progress and supporting documentation before the formal application.

D

Authorize extra work verbally.

Test Your Knowledge

What is the purpose of a specified preinstallation conference for a roof system?

A

Coordinate the particular assembly, substrates, approved products and installation conditions before the roofing work.

B

Open and evaluate bids.

C

Replace the construction and submittal schedules.

D

Decide whether the prime contractor’s bonds remain valid.