10.2 Document Coordination, Discrepancies & Pre-Issue QA

Key Takeaways

  • Trace interfaces with consistent identifiers and verify connected requirements before issue.

  • Overlay and review current drawings and models and confirm results in the issued set.

  • Send pre-bid inquiries under the solicitation. For AIA A201–2017 construction, send an RFI in the required format and get the architect’s written response.

  • Identify whether site documents are incorporated and the extent to which the contract permits reliance on the data.

Last updated: November 2026

Coordinate the interfaces before issue

Read the set as a builder who must price and install it. Check which discipline locates each item, which sets its acceptance criteria, and which coordinates the connection to other work. Review the current issue and keep the resulting decisions in the project’s coordination record.

InterfaceCompareVerify before issue
Ceiling and structureReflected ceiling plan, sections, framing and duct layoutsBeam and duct geometry, routing and maintenance clearances, and access at transitions
Penetrations and supportsStructural plans, service routes and equipment detailsSize and location of sleeves, support and reinforcement requirements, and authorization to alter a structural member
Power and controlsEquipment schedule, specifications, single-line diagram and circuit scheduleCompatible voltage and phase, disconnects or starters where needed, controls interfaces, and division of connection work
Electrified openingDoor and hardware schedules, access control details and electrical drawingsHardware set, device tags, power and control assignments, rated opening and required egress operation
Rated or acoustic assemblyWall sections, door and partition schedules, service detailsActual tested or approved assembly criteria, top and edge conditions, dampers where required, and permitted penetrations

For door S-102, use the same opening identifier in the plan and door schedule. Link the door to the hardware set and use it or a clear cross-reference in the relevant security details. Check lock functions and project-specific release requirements before issuing the set. Keep consistent data where the project needs the same information in more than one view. The objective is to give each reader a traceable requirement and avoid out-of-sync versions.

Review the coordinated package

A quality assurance plan identifies reviewers, disciplines, required checks, and issue milestones. Quality control checks the actual drawings and written documents. Overlay current backgrounds or review current models for conflicts. Check the drawings against schedules, detail callouts, and the specification index. Inspect the affected text after revisions to make sure the correct section is still linked. A valid reference can still identify the wrong assembly, so resolve scope before relying on a matching number.

Review Division 00 and Division 01 together with the bidding package. For example, a separately priced alternate may add a controls connection. Verify that the bid form identifies it, that Division 01 describes the changed scope, and that the equipment specification and drawings show the associated installation. Track each check to a responsible reviewer and confirm closure on the issue intended for procurement or construction.

Distinguish bidding inquiries and construction RFIs

Follow the issued procurement instructions during bidding. Under AIA A701–2018 § 3.2, bidders request clarification or interpretation by the stated procedure, and official interpretations or revisions are issued by addendum. After execution on an AIA A201–2017 project, § 3.2.2 requires the contractor to check the documents for the portion of work, compare applicable site information and conditions, take relevant field measurements, and promptly report discovered discrepancies to the architect in the required request for information (RFI) format. Under § 4.2.14 the architect responds in writing. If a response changes scope, time, or price, check the changes and claims provisions for authority and notice before relying on it.

For example, a schedule specifies a 480-volt rooftop unit but the scheduled circuit supplies 208 volts. Document both sources and ask for clarification. Coordinate the affected procurement or work while seeking a written resolution. Under A201 § 3.2.4, failure to perform the reporting and related duties can make the contractor responsible for avoidable costs and damages, subject to the applicable contract provisions. EJCDC C-700–2018 § 3.03.A.2 expressly requires written notice to the engineer when a conflict is discovered during performance and withholding affected work pending resolution, with an emergency exception. Do not import that precise wording into an AIA clause.

Label and handle project reference information

An issued project manual can identify reference material under 00 31 00 Available Project Information. The City of Sycamore well project, for example, points readers from that section to its geotechnical data. Use the bid instructions and executed contract to distinguish the report’s location, incorporated materials, data to which the contractor may look, and any duty to investigate or give notice. An available report can include data with limited contractual reliance under the applicable conditions. The filing label does not make the entire report binding or determine reliance on its own.

References AIA A701–2018 § 3.2, AIA A201–2017 §§ 3.2 and 4.2.14, EJCDC C-700 base §§ 3.03 and 5.03 reproduced by Muskegon, and Sycamore Well 7 Project Manual.

Loading diagram...
Resolve a discrepancy under the procedure that applies
Test Your Knowledge

A specifier is coordinating a lock, reader, and power supply for Stairwell Door S-102. Which approach makes the requirements traceable?

A

Repeat every manufacturer and electrical attribute in every drawing and schedule.

B

Put the security wiring diagrams in Supplementary Conditions so they supersede the schedules.

C

Use the same opening identifier and coordinating cross-references in the plans, door and hardware schedules, and affected security and electrical documents.

D

Leave the opening without a hardware set and ask a subcontractor to select a lock in the field.

Test Your Knowledge

On an AIA A201–2017 project, the contractor discovers a 480-volt requirement in the mechanical schedule and a 208-volt circuit in the electrical schedule. What action does § 3.2.2 require?

A

Promptly report the discrepancy to the architect as an RFI in the required form.

B

Select the voltage from the electrical schedule under an automatic precedence rule.

C

Order the mechanical unit and charge the owner for the circuit upgrade without authorization.

D

Use whichever voltage is cheaper and record that choice at closeout.

Test Your Knowledge

During pre-issue review, the team finds a mismatch between a priced controls alternate in Division 01 and the bid form. What should the team do?

A

Leave the bid form as issued and have bidders choose which scope to carry.

B

Delete the drawings that show the connection and maintain the inconsistent scope text.

C

Carry both alternatives in the base bid without modifying the solicitation.

D

Reconcile the alternate, bid form, and related drawings and specifications before release, then verify the coordinated issue.