14.1 Executing the Work & Progress Meetings

Key Takeaways

  • The contractor supervises work, coordinates operations, and evaluates the safety of any procedures the documents prescribe.

  • A201–2017 § 3.3.1 calls for timely notice and a proposed alternative when prescribed procedures may be unsafe.

  • Current marked contract documents and approved submittals must be available at the site under A201 § 3.11.

  • Use progress meetings, trade coordination and field records to track different decisions and follow-up actions.

Last updated: November 2026

Supervise and coordinate execution

Under AIA A201–2017 § 3.3.1, the contractor supervises and directs the work, controls construction means, methods, techniques, sequences and procedures, and coordinates portions of its work. Under §§ 10.1 and 10.2 the contractor administers the safety precautions and program connected with performance of the contract. The contractor designates a responsible member of its organization for accident prevention as required by the clause, ordinarily the superintendent unless another member of its organization is designated in writing. Other parties retain duties under their own agreements and applicable law.

EJCDC C-700–2018 §§ 7.01 and 7.13 also assign execution and protection duties to the contractor. The contract governs coordination with the owner’s other contractors and utilities. In an A201 project, Article 6 provides for the owner’s separate construction and requires reasonable opportunities for storage and execution and proper connection and coordination with related work. Before integrating two packages, confirm points of connection, shared access, work dates, and who resolves discrepancies. Route contractual notices accordingly.

When the documents prescribe a potentially unsafe method

An A201–2017 project may specify a sequence or method. Under § 3.3.1, the contractor evaluates its jobsite safety and remains responsible for that safety. If the prescribed method may be unsafe, the contractor gives timely notice to the owner and architect and proposes an alternative. The architect evaluates that proposal solely for design intent of the completed construction. Unless the architect objects, the contractor performs the work using its proposed alternative. Document the notice and proposal under the applicable notice requirements. The architect’s evaluation does not transfer jobsite safety responsibility.

For example, if a contractor questions a specified excavation sequence, it should describe the concern and submit an alternative that addresses the design requirements. Record the location, the affected work and the relevant documentation. Maintain safe conditions while resolving the issue and comply with regulatory duties. Do not apply a provision from a different A201 edition or project.

Keep site supervision and documents current

Under A201 §§ 3.9.1–3.9.3, the contractor employs a competent superintendent and necessary assistants who attend the site during performance. The superintendent represents the contractor for communications. The contractor submits the proposed superintendent’s name and qualifications, and the architect has 14 days from receipt to communicate reasonable objection or need for more review. Once the superintendent is in place, changing that person requires owner consent, which may not be unreasonably withheld or delayed.

Under § 3.11, make accessible on site a current version of the Contract Documents marked to record field changes and selections, and approved shop drawings, product data, samples and similar required submittals. Electronic or paper documents can be used. The owner and architect have access, and upon completion the contractor delivers the records to the architect for submittal to the owner. Record changed conditions while the work is visible.

Use contemporaneous records

A project-wide progress meeting can review the updated schedule, upcoming work, submittals, RFIs, pending changes, payment, tests and access concerns. Use the project’s requirements for who chairs it, how often it meets, and who distributes minutes. A trade coordination meeting may focus on the contractor’s near-term crew sequencing, shared access and deliveries. Record each action with a responsible party and due date. Capture a request for change pricing separately from authorization to do it.

A contractor’s daily report, when required, can record weather, crews, equipment, completed work by location, deliveries, tests and disruptions. AIA G711–2018 illustrates an architect’s field report. It records observed conditions and deviations, identifies follow-up and captures who was present. If a material delay occurs, preserve dated information about the activity, impact, and steps taken. Use the applicable notice provisions instead of assuming a daily entry or meeting minute initiates a Claim.

Use the field record during follow-up

Suppose the most recent schedule shows equipment delivery before a planned connection shutdown. The daily report records that the delivery truck missed the permitted access window. The progress meeting can assign the contractor to reconfirm transport and the owner to confirm the next available shutdown. The architect’s field report can identify observable work left incomplete at the tie-in. Keep the source, date, and action clear in each record, then verify whether the updated plan changes any contract milestone.

When the issue is…Record or action that fits
Who attended and what follow-up is dueRecord it in the meeting minutes
Which changes apply on siteUpdate the set available under the contract
A prescribed method poses a potential safety problemUse the notice and alternative procedure in A201 § 3.3.1
A decision will change the agreed workObtain the authorization required by the contract

References AIA A201–2017 §§ 3.3, 3.9, 3.11, 4.2 and Articles 6 and 10, AIA G711–2018 field report, EJCDC C-700 base §§ 7.01 and 7.13, Muskegon packet, and UFGS quality control documentation example.

Test Your Knowledge

An unmodified AIA A201–2017 project prescribes a method the contractor determines may be unsafe. What does § 3.3.1 require?

A

Give timely notice to the owner and architect and propose an alternative for the architect’s limited design-intent review.

B

Use a different method while keeping the decision from the owner and architect.

C

Follow the prescribed method because the owner automatically assumes all safety responsibility.

D

Transfer field supervision to the architect until the project is complete.

Test Your Knowledge

What must the contractor make available on site under AIA A201–2017 § 3.11?

A

Only the document index, with all records kept in the architect’s office.

B

A set assembled for the first time when the work is substantially complete.

C

Current marked contract documents and approved submittals in electronic or paper form.

D

Only the change orders, with field changes omitted.

Test Your Knowledge

A progress meeting notes that a changed equipment route may affect contract time and price. How should that item be handled?

A

Treat the minutes as automatic approval of added cost and time.

B

Let the building official negotiate the change price.

C

Leave the decision to an internal trade crew meeting.

D

Record the issue and next action in the minutes and use the applicable contract procedure to authorize any change.