5.2 Working Inside an Engineering Supervisor’s Work Site

Key Takeaways

  • The engineering supervisor manages the work site and authorises the COSS to set up the group’s safe system.

  • Agree the limits, nature of the work and safe system with the ES, receive the work-site briefing and sign RT3199 under Handbook 9 Issue 9.

  • An advance agreement requires an approved, planned and published arrangement and a grant and authority number before work.

  • When the group no longer needs the ES’s protection under the rules, tell the ES so the work site can be accounted for at handback.

Last updated: November 2026

Recognise the portion of line the ES controls

A work site is a defined portion of running line within a possession. It can contain several groups doing different tasks. The engineering supervisor (ES) authorises movements into and within the work site and authorises the COSS to set up the group’s safe system. The COSS must agree where their group will actually work. A task that extends over the work-site limit needs a different or revised arrangement through the appropriate roles.

Handbook 12 Issue 11 requires the ES while acting in the role to wear ENGINEERING SUPERVISOR in blue on yellow, as a left-arm armlet or an upper-chest badge. The ES agrees the work-site arrangements with the PICOP. For a work site requiring work-site marker boards (WSMBs), the ES and PICOP agree and record the actual locations. The red lights face traffic approaching the work site and the yellow lights face traffic leaving it. The standard placement and special cases near adjacent work sites or possession protection are covered in sections 3.4–3.5 and Handbook 11 Issue 11 section 6. A board identifies the arrangement for rail movements. It does not give a group permission to walk anywhere within or beyond it.

Agree the group’s actual protection

Check with the ESWhat the COSS needs to establish
The limits of the site of workThe correct line and the actual portion of the work site occupied by the group or affected by the task.
The nature of the workThe activity, equipment and limits of anything that could foul another line, and how these might change during the work.
The safe system to be usedWhat the ES has agreed about movements and what protection is needed from open lines or other hazards.
Work-site briefing and recordReceive the ES briefing and sign the Work-site Certificate, RT3199, under the ordinary Handbook 9 Issue 9 procedure.

Handbook 9 Issue 9, sections 3.1 and 3.2 distinguishes the ordinary agreement from one made before the work-site grant. The advance arrangement is only permitted when planned and published in advance and both the ES and COSS know what will happen. The COSS can reach the agreement, receive the briefing and sign the certificate early under that arrangement. Work still waits for the ES to confirm that the work site has been granted and give the authority number. The COSS records the number. Under either process the COSS establishes, tests and briefs the group’s safe system under Handbook 7 and records the group briefing on RT9909.

Use the issue in force for the work. RSSB’s Handbook 9 Issue 10 entry gives 5 December 2026 as its in-force date and describes the change to the signing requirement. Any currently authorised work-site deviation also has its own conditions. The published future issue does not itself change how a November 2026 work-site agreement is made.

Clear the job and tell the ES

Under Handbook 9 sections 3.8–3.9, tell the ES when you and your group are no longer on or near the line or you are sure the work can safely continue without the ES’s protection. The pre-planned, published telephone arrangement uses your name, location and authority number. Under Handbook 12 section 10, the ES records the release, checks the applicable arrangements for engineering trains and plant, and gets permission from the PICOP to remove work-site marker boards. The ES tells the PICOP the outcome and records it on RT3199. The COSS cannot give up the possession.

Worked boundary decision

A group repairing a joint inside a work site finds a defect beyond the agreed limit on the line ahead. The work-site marker board may be visible, but that is no reason to move the group towards the defect. Keep everyone within the agreed safe arrangements and report the defect to the ES, using the applicable emergency procedure if the defect could endanger a movement. If repairing it requires a different limit, the COSS needs an agreement for the changed work, with the right party for the actual limits, before allowing exposure. Check the protection of the route to the new location, the plant movements that might pass it and the controls for the repair itself. Rebrief the group before it starts the changed work.

Loading diagram...
Agreement, work and release of protection
Test Your Knowledge

Which lights on a standard physical work-site marker board face movements approaching and leaving the work site?

A

Green toward approaches and red toward departures

B

Yellow toward approaches and red toward departures

C

White in both directions

D

Red toward approaches and yellow toward departures

Test Your Knowledge

A planned and published advance agreement under Handbook 9 Issue 9 has been signed before the work site is granted. When can the group start the work?

A

Immediately after the signature

B

After the ES confirms the grant and gives the recorded authority number, and once the group’s safe system is in place

C

When the COSS sees a marker board

D

At the published time even without an authority number

Test Your Knowledge

Under the ordinary work-site agreement in Handbook 9 Issue 9, which certificate does the COSS sign after receiving the ES briefing?

A

RT3199 Work-site Certificate

B

RT3198 possession arrangements form

C

NR3180 line blockage form

D

RT9909 as a substitute for the Work-site Certificate