5.3 Engineering Trains and On-Track Plant Movements
Key Takeaways
PICOP, ES and machine controller have distinct duties. Confirm who controls each part of the actual movement.
For an agreed movement through the group’s site of work at no more than 5 mph under Handbook 9, put everyone in a safe position before it passes.
Apply the machine-specific tests and check the proposed movement and exclusion zone with the relevant competent people.
If plant could foul an adjacent line or the agreed separation fails, stop the work and ensure the hazard is reported and protected before work restarts.
Identify the line and who can authorise the movement
Engineering trains carry materials or equipment. On-track plant (OTP) includes road-rail vehicles, rail-mounted maintenance machines and their associated trailers and attachments with guidance wheels. Under Handbook 9 Issue 9 and Handbooks 11 and 12, the person in charge of the possession (PICOP) authorises movements within the possession outside the work site. The engineering supervisor (ES) authorises movements into and within a work site. The machine controller (MC) controls the applicable movement of plant and briefs its operator. The COSS protects the workgroup under the agreed safe system and needs to know how a movement could affect it.
| Situation | What the COSS checks |
|---|---|
| Engineering train or plant approaching a group inside a work site | Agree the passage with the ES within the agreed safe system. Confirm the line, limits and where people will be before the movement arrives. |
| Work between established work sites | Under Handbook 9 Issue 9, the special arrangement outside a work site needs planning and the PICOP’s permission, plus a safe system for the actual site. The possession alone does not safeguard the group. |
| Plant operation beside a line still open | Verify whether the machine, attachments or loads could foul that line. If so, arrange the protection required by the applicable operating instructions. |
Match the speed to the agreement
Handbook 9 sections 3.3–3.5 require the COSS using those safeguarded, fenced or separated arrangements in a work site to agree with the ES either that there will be no train or OTP movements at the site of work, or that the movements there will be made at no greater than 5 mph. If the latter applies, section 3.7 requires everyone to be in a safe position before any movement passes through the site of work. The ES gives the speed instruction. The speed rule ties to the COSS–ES agreement at that site. Elsewhere movements at caution depend on the applicable instructions, what the driver or operator can see and the distance needed to stop.
Under Handbook 9 Issue 9 section 4.2, the pre-planned outside-work-site arrangement uses the PICOP’s authority and warning arrangements based on up to 25 mph in either direction on the possessed lines only. The COSS records the agreement and completion on RT9909 and must meet the applicable Rule Book and company conditions before using the arrangement. Darkness, poor visibility and in or near a tunnel prohibit this arrangement. An adjacent open line still needs its own applicable arrangements. RSSB lists different provisions from 5 December 2026 in Handbook 9 Issue 10.
Plant testing and worker separation
Handbook 15 Issue 7, sections 2–6 allocates duties to the MC and plant operator. The operator does the tests specified for the plant and the MC makes sure they are done. Tests go before on-tracking unless they can only be done afterwards. If a required test after on-tracking fails, the plant must be taken off the line immediately. The MC also briefs route restrictions, stopping locations, poor rail conditions and hazards.
Set and brief the exclusion zone for the actual machine and activity. Under Network Rail’s Lifesaving Rules, enter the agreed exclusion zone only when directed by the person in charge. RAIB’s Braybrooke digest explains that workers need permission from the machine controller for the road-rail vehicle concerned. Use the agreed site method. Approach only once the responsible person confirms it is safe and gives permission.
Worked decision: swing towards an open line
A road-rail excavator inside a work site slews towards an adjacent running line. Its counterweight appears to have moved beyond the agreed limit, even though a limiter was part of the plan. Stop work and keep the group clear. Alert the MC and ES, and if the open line may have been fouled, promptly report the danger so movements on the affected line can be stopped. Find out what happened and whether the work can continue without fouling the line. If it cannot, the relevant people must establish the necessary protection and agree an amended method. Recheck the machine controls and brief the revised safe system before letting the group restart.
The COSS and ES agree under Handbook 9 that plant may pass through the site of work at no more than 5 mph. Where must the COSS have the group?
At the original working positions if the machine sounds its horn
In the four-foot until the plant stops
In a safe position before the movement passes through the site of work
Next to the machine so the operator can check attendance
A machine-specific test that must follow on-tracking fails. What is required under Handbook 15?
Start production and check again at handback
Operate only at a walking pace with the fault
Ask the COSS to waive the plant test
Take the plant off the line immediately
A worker needs to enter the exclusion zone of a road-rail vehicle. What must happen first?
The person directing safe access must confirm it is safe and give permission under the agreed arrangements
The worker may enter if the machine is temporarily stationary
The worker may enter if wearing the correct high-visibility clothing
The worker may enter from the rear to avoid distracting the operator