2.2 The Safe Work Pack (SWP) & Form RT9909 Verification
Key Takeaways
RT9909 is the safe-work briefing and arrangements record within the Safe Work Pack.
The Safe Work Pack covers route information, risks, permits, safety arrangements and welfare as applicable.
Record and resolve changes through the current planning procedure. A revised control must meet the applicable operating rules and approvals.
For a line blockage, apply Handbook 8 and record the signaller’s authority number on NR3180. A pack or briefing record alone does not grant it.
What belongs in the pack
The Safe Work Pack (SWP) brings together the planning and safety information for the work. The RAIB Bookham report, paragraphs 31–36 illustrates how the pack passes from preparation and checking to site acceptance. Use the current company requirements to decide which records apply. This checklist shows what you need to be able to confirm from the pack for the group.
| Pack material | How it is used |
|---|---|
| Validation and acceptance record | Shows the planning, verification, authorisation and acceptance steps. |
| RT9909, the record of arrangements and briefing | Use it to record the arrangements and the group’s confirmation that they understand the briefing, as set out in Handbook 7. |
| Route, access and protection details | Show how the group enters, walks to, works at and leaves the site. Include relevant Sectional Appendix and Hazard Directory information. |
| Site, task and operational risk controls | Use task-specific risk information and any relevant permits and diagrams, for example a lift plan or electrical permit when required. |
| Welfare and emergency arrangements | Review the applicable access, welfare and emergency arrangements at the site. |
A line blockage has its own arrangement and form, NR3180, under Handbook 8 Issue 10. If the pack plans for a blockage, the COSS must follow the agreement, protection and grant procedure and record the authority number. A draft entry in a pack is a plan. It does not confirm that the signaller has changed the status of a line.
A verified pack still needs a site decision
Verification addresses whether the planned work, information, risks and proposed controls are suitable. The responsible manager then checks and authorises the verified plan. The person in charge still needs to accept it against the circumstances on site. For example, confirm the actual place of access, which lines are open, where the group may work and which resources and competent people are available. A useful check compares the stated arrangement with the real feature it depends on, such as whether a fence can stand at its approved distance all the way along the work site.
The COSS establishes, tests and briefs the applicable safe system before permitting work. Handbook 7 Issue 10, sections 5–7 distinguishes the safe system for walking from the one used at the work site. A group that can reach its work place safely may still be unable to use the planned arrangement once it gets there. Likewise, a working system that has been agreed does not excuse a missing route to enter or leave safely.
Identify any special close-out arrangements in advance. For example, RAIB’s Queens Park safety digest explains why a rail-handling trolley placed within an axle-counter section may not be detected and why line clear verification is used to manage the use and removal of trolleys where required. Identify who will do the applicable checks and pass on the result before confirming that the work is clear. Signing the group briefing record does not establish that the line is clear for handback.
Handle discrepancies before work starts
If planned access is blocked or the expected safety equipment is unavailable, keep the group clear. Compare the actual conditions against the pack and raise the discrepancy with the person in charge. Record any change through the applicable company procedure and obtain the required agreement or authorisation before using a revised system. The COSS still has to establish and test that system and brief everyone. Treat a proposal to move to a less protective option as a planning decision requiring justification and approval. Do not appoint an informal lookout in place of a planned blockage.
Example: a fence cannot be installed as shown
A team arrives for a planned fenced task. A newly installed cabinet makes it impossible to put the approved barrier where the pack shows it. Keep the group clear and refer the discrepancy to the person in charge and planner. A different arrangement may be feasible, for example a correctly arranged line blockage, but it has to fit the task and location and meet the applicable authorisation and Rule Book requirements. If none can be put in place, stand down the work. At the end of the shift the person in charge returns the SWP to the planner, with any discrepancies and relevant feedback. That return does not itself give up a line blockage.
At the work site a cabinet prevents the approved fence from being positioned at its required distance. What should the group do?
Continue with the fence at a reduced distance without telling anyone
Ask a worker to act as an informal lookout while the fence is moved
Treat the pack’s verification as proof the site is safe
Remain clear while the discrepancy and suitable arrangements are resolved
A pack has been verified and authorised. What remains to be decided on site?
Whether the approved arrangements can be accepted and put in place at the actual site
Whether the planner needs to change the original training records
Whether authorisation can replace the check of the actual access route
Whether the group can treat all lines near the work as blocked
What is the relationship between RT9909 and the Safe Work Pack?
RT9909 grants the signaller’s line blockage authority
RT9909 is the same as the whole Safe Work Pack
RT9909 records arrangements and briefing within the wider pack
The form is only used to record engineering test results