3.2 Fenced and Separated Systems of Work

Key Takeaways

  • For fenced working, check the type, approval and position of the barrier against the applicable rules before working on its safe side.

  • Handbook 7 permits approved tape or netting at 1.25 metres where the open line’s maximum speed is at most 40 mph. At least 2 metres is required without that speed condition.

  • A separated safe area has an identifiable limit at least 2 metres from the nearest running rail of an open line. For the COSS and just one other person, no site warden is required if both maintain that distance.

  • A site warden watches people and the safe area. Choose enough competent wardens for full coverage and test that everyone can hear the warning.

Last updated: November 2026

Fenced working: the type of barrier matters

RSSB Handbook 7 Issue 10, section 6.5 allows a safe system using a safety barrier approved by the infrastructure manager. Place it between the work group and any open line, and keep work on the safe side. For an approved rigid or tensioned barrier or a permanent fence, the Rule Book minimum is 1.25 metres from the nearest running rail of the open line. For barricade tape or plastic netting, the handbook allows placement at 1.25 metres if the maximum speed on the open line is no greater than 40 mph. At least 2 metres is required for tape or netting when relying on the rule without that speed restriction.

Confirm that the infrastructure manager approves the barrier and that the proposed position meets the applicable company instructions as well as the Rule Book. The Rule Book’s note on a 0.9-metre barrier used with an automatic track warning system for on-track plant does not permit the COSS to use a barrier at that distance in a group’s safe system.

Worked barrier check

A team proposes approved netting 1.5 metres from the nearest running rail of an open line with a maximum speed of 60 mph. Under Handbook 7 the 1.25-metre provision for tape or netting requires a maximum speed no greater than 40 mph. At 60 mph the handbook requires at least 2 metres, so the netting at 1.5 metres does not qualify. Check the current company instructions and approved layout before moving the barrier or selecting another method. Brief the group on the safe side and keep tools and materials off the barrier.

Separated working: keep the group within an identifiable safe area

Section 6.6 requires an identifiable safe area at least 2 metres from the nearest running rail of an open line. The COSS and each site warden must be able to identify the boundary. Normally appoint one or more site wardens who can see every person and the limits they are watching. If the group is just the COSS and one other person, the handbook allows no warden provided neither person goes closer than 2 metres. Section 6.3 gives the general 3-metre distance between each member of the group and an open line. If that distance cannot be kept, use one of the permitted arrangements in sections 6.4 to 6.8. The site and task still need suitable controls at any distance. This section is about working at the site. Under section 5.1 a warden is not the safe system for a group walking on or near a line.

Site warden set-up checkWhy it matters
Competence and identificationUnder Handbook 3 Issue 4, a warden uses a white armlet or badge with blue SITE WARDEN lettering. An armlet is on the left arm and a badge on the upper chest.
CoverageArrange enough wardens to see the limits and every person and to warn everyone. Hidden sections of a boundary, changed work positions or noise can invalidate the arrangement.
No conflicting dutiesWhile acting as a warden, keep the phone off and watch the group. Do not look out for trains or take part in the work. Check whether any additional company rule restricts combining the proposed roles.
WarningIdentify the wardens and limits to every worker, agree the warning and test it before work. Under Handbook 3, shout “get back” if someone attempts to leave the safe area. If they do not return immediately, use short sharp blasts on the whistle or horn until they return.

For example, after materials are moved, a cabinet obscures the warden’s view of the far end of a separated work site. Even though the boundary is still in the right place, the arrangement now fails the coverage check. Stop the work and set up an arrangement in which the wardens can see everyone and the limits and the group can hear the tested warning.

A site lookout watches for trains, while a site warden watches people and a boundary. The COSS stops the work and moves the group to safety if the safe system ceases to protect it.

Loading diagram...
Barrier and Separated-Area Decisions
Test Your Knowledge

The open line has a maximum speed of 60 mph. What minimum distance does Handbook 7 require for approved barricade netting from its nearest running rail?

A

At least 0.9 metres

B

At least 1.25 metres

C

At least 2 metres

D

The barrier’s approval removes any minimum distance

Test Your Knowledge

What does the site warden monitor in a separated safe system?

A

The group and the safe boundary

B

Approaching trains on behalf of the signaller

C

The signals protecting the line blockage

D

The electrical isolation indicator

Test Your Knowledge

The group consists of the COSS and one other person. They can both stay at least 2 metres from the nearest open running rail. What does Handbook 7 allow for this separated arrangement?

A

They must appoint two wardens

B

One can move inside 2 metres if the other person watches

C

They must replace the safe boundary with lookout warning

D

They can work without a separate warden if they both keep the required distance