4.2 Additional Protection: T-CODs, Disconnections & Other Methods

Key Takeaways

  • Arrange additional protection whenever possible. It is mandatory if the work will affect the safety of the line.

  • The signaller gives permission before a track circuit operating device is placed or activated. Tell the signaller when it is applied.

  • A signalling technician’s disconnection and an authorised remote signalling disconnection follow different Handbook 8 instructions.

  • A planned T-COD arrangement under Handbook 8 is separate from an emergency track-circuit operating clip under Handbook 2.

Last updated: November 2026

Put the agreed protection in place before the grant

RSSB Handbook 8 Issue 10, section 2 distinguishes the signaller's protecting signal or closed route at a block marker from additional protection. Arrange at least one applicable additional method when possible. You must arrange it if the work affects the safety of the line. Agree the method with the signaller, who does not give the authority number until the required additional protection is in place. Do not choose a device just because it is available. It must be authorised as applicable and protect the right portion of line.

MethodChecks and responsibilities
Signalling disconnection by a technicianAsk the signaller to arrange for the signalling technician to disconnect the equipment protecting the line.
Lock-out deviceCheck that you are competent to use the device and it protects the portion to be blocked.
Track circuit operating device (T-COD), placed or remotely activatedCheck that the Sectional Appendix authorises it, the signalling is working normally and the work will not affect the track circuit. Obtain signaller permission before applying and tell the signaller when it has been applied.
Single line staff or tokenObtain it from the signal box or the token instrument and follow the applicable local instructions.
Engineering possession reminder (EPR)Where authorised in the Sectional Appendix, ask the signaller to apply it.
Block indicator or acceptance switchesThe block indicator may be placed to train on line where Signal Box Special Instructions permit. The acceptance switches may be placed or kept at normal for a tokenless block line. The signaller arranges these controls.
Remote disconnection of signalling equipmentIts use must be authorised at the location, the work planned in advance and the user authorised. The signalling must be working normally, the equipment must protect the right portion and the work must not impair the relevant track circuit. Obtain signaller permission before activation.

Detonators used for a planned line blockage

Handbook 8 also allows detonator protection for a line blockage. Section 2.8 calls for three detonators spaced 20 metres apart on the same rail and a possession limit board (PLB) at the first. Arrange their placement at the protecting signal or block marker, or clear of points or through crossings beyond. Apply the method in both directions for a single or bidirectional line or when single line working is in use. Do not confuse this planned method with the full emergency protection in Handbook 2, which has a different trigger and placement rules. The board at the detonators is also different from the red flag or light at the work site under section 4.1.

How to reason through a track circuit example

A track circuit detects a train using the electrical relationship between the two running rails. The presence of a train's wheelsets changes that circuit. A device that depends on a working track circuit cannot be assumed to operate a separate form of detection. The practical test is the approved protection for the location, not the generic name of the equipment. If the task would prevent the track circuit from operating correctly, a T-COD is unsuitable even where it is otherwise authorised.

For example, a COSS requests a planned blockage for work that would affect the circuit needed by the locally authorised T-COD. Even though the signalling is working normally before the work, the task fails the condition about keeping the track circuit working correctly. The COSS tells the signaller the nature of the work and agrees a suitable alternative. If suitable additional protection cannot be provided, this work cannot proceed under the proposed blockage.

Keep application and work authority separate

Suppose a different task can use an authorised remotely activated T-COD. Agree the limits and arrangements. After the signaller gives permission to activate the device, apply it as instructed and report it has been activated. Even though the equipment is now applied, the workgroup continues to wait for the signaller's blockage authority and the COSS's briefing. This is the sequence that distinguishes an action taken as part of setting up protection from the authority to start the work itself.

After work, handback depends on the type of protection. A remotely activated T-COD is not deactivated until after telling the signaller the blockage is no longer required or is suspended. A signalling disconnection has its own reconnection procedure. Identify what was used and follow section 5.1 rather than carrying a single rule across all devices.

Loading diagram...
Choosing and Applying Additional Protection
Test Your Knowledge

Where is additional protection under Handbook 8 always required?

A

Only at a site with a remote device

B

When the work will affect the safety of the line

C

Only when working with a second COSS

D

Only in a route with block markers

Test Your Knowledge

A T-COD is authorised at the location, but the job would impair the track circuit it uses. What should the COSS do?

A

Apply the T-COD after getting the blockage number and continue

B

Use the T-COD because the signalling worked before the task

C

Fit an emergency clip in its place without telling the signaller

D

Agree another suitable protection method before any work that needs it

Test Your Knowledge

What communication applies to an authorised remotely activated T-COD under Handbook 8?

A

Get the signaller’s permission before activation and tell the signaller when it has been activated

B

Activate first and notify only if the blockage overruns

C

Treat activation as the signaller’s authority number

D

Wait until normal services resume to tell the signaller