8.3 DC Conductor Rail Safety and Permits

Key Takeaways

  • Under Handbook 17, the ordinary distance from live equipment is at least 1.5 metres. Approved closer work has separate conditions.

  • When company rules allow work within 300 mm of live conductor rail, use a conductor rail shield if possible. A shield does not establish an isolation.

  • The authorised person issues a conductor rail permit for a planned isolation. Check and brief the exact limits and conditions.

  • Never touch or step on the conductor rail or guard boarding, or step between the conductor rail and the adjacent running rail.

Last updated: November 2026

Apply the rules for the route

Handbook 17 Issue 6 gives the conductor rail rules for this part of the Rule Book. Issue 6 came into force on 6 June 2026. Check any applicable local instructions for the infrastructure where you will work. Before going on or near the line in a conductor rail area, ensure the Personal Track Safety competence is valid for the DC system. Identify the conductor rail equipment (CRE), shoe gear and exposed electrical equipment on vehicles. Treat them as live unless the applicable authorised arrangements establish otherwise. A conductor rail close to the walking surface can be reached by a foot, tool or object moved by the group.

Manage the approach and the movement of items

Under section 4.1, keep yourself and anything you hold at least 1.5 metres from live CRE, shoe gear or associated live train-mounted equipment. A closer approach requires a method statement and electrical risk assessment approved by someone authorised to do so, the specified precautions in place, and people following those precautions. Where company rules permit work nearer than 300 mm to a live conductor rail, apply a conductor rail shield if possible. That is a further precaution for an allowed activity, not a general clearance for routine work.

SituationApply this check
Crossing a line under the applicable safe systemDo not touch or step on CRE or guard boarding, and do not step between the conductor rail and its adjacent running rail. Follow the briefed crossing method.
Moving materials or equipmentApply the method or company precautions. Avoid carrying over the conductor rail where possible. Do not drag objects across or drop them on live CRE.
Flood water or a broken assetDo not enter flood water that may touch the equipment, touch broken rails or bridge a gap. If safe train operation is affected, report first to the signaller and ensure the ECO is informed.

Receiving and returning a conductor rail permit

Under sections 1 and 8.1, an authorised person (AP) issues the conductor rail permit (CRP) for a planned isolation. The COSS cannot start work that requires that isolation until they receive the permit. Check its equipment, limits, hazards and restrictions, and explain them to everyone before work. Consider how tools and materials may approach equipment outside the isolated area. An electrical permit does not establish the protection needed from trains. Temporary and local isolations are separate procedures allowed only under the corresponding instructions.

Keep the permit until the group has finished, then return it immediately to the issuer. If another COSS takes over, explain the limits and hand over the permit only when they understand the applicable limits, hazards and conditions. Tell the AP immediately if the permit is lost so a duplicate can be arranged. If the loss is discovered when work is complete, the handbook calls for a visual inspection with the AP to make sure personnel and materials are clear.

Worked decision: the adjoining conductor rail is still live

A team under a CRP on one road needs to move a metal item near a conductor rail on another road. At one point the person carrying it could bring it within 1.2 metres of that live equipment. That is below the ordinary 1.5-metre threshold. Keep the team clear and raise the issue with the person in charge. A revised route that avoids the live rail may be suitable. If it cannot be avoided, check the approved electrical arrangements for that activity and the protection from trains. The original CRP has not changed because the route changed.

Emergency switch-off and damaged equipment

If there is an incident likely to need the electricity switched off, contact the ECO immediately or arrange for someone to do so. Under Handbook 17 sections 5 and 6, state that it is an emergency call. Give the location and contact details, why switch-off is needed, whether anyone is in danger, whether any short-circuiting bars have been applied and whether emergency services are waiting to help. Stay in contact until the ECO confirms switch-off or other arrangements. Confirmation of switch-off alone does not give permission to approach or touch. Follow the specific instructions in section 3.1 for confirmation that it is safe to approach without touching. The signaller separately manages danger to trains. Section 6.3 describes limited emergency use of short-circuiting bars by a competent person if the ECO cannot be contacted and a person is in danger through contact. It does not make a short-circuiting bar a universal CRP requirement. Follow the applicable emergency arrangements and keep everyone clear of equipment that has not been confirmed safe.

Loading diagram...
Selecting protection for work near conductor rail
Test Your Knowledge

What is the ordinary Handbook 17 distance from live conductor rail equipment for a worker and anything they hold, without approved closer-working arrangements?

A

At least 1.5 metres

B

At least 300 mm

C

At least 2 metres

D

At least 2.75 metres

Test Your Knowledge

Which statement describes a conductor rail permit under Handbook 17?

A

A worksite marker board acts as the electrical permit

B

The permit confirms that all train movements are stopped

C

A shield fitted to a live rail provides the same status as the permit

D

The authorised person issues it for the specified equipment and the COSS briefs its actual limits and conditions

Test Your Knowledge

A group is crossing a conductor rail line under the applicable safe system. Which foot position is prohibited?

A

A point on the authorised route clear of the electrical equipment

B

A place outside the track on the briefed route

C

Between the conductor rail and its adjacent running rail

D

A designated position of safety clear of the equipment

Sections you finish are checked off in the contents.