2.1 The SSOW Planning Process, Roles & NR/L2/OHS/019 Framework
Key Takeaways
The competent planner develops the pack with the person in charge who will undertake the work.
The person in charge verifies the planned pack and later decides whether it can be accepted and implemented on site. The responsible manager authorises it after verification.
Allow time for advance verification and authorisation, and check whether the approved pack can be put into practice on site.
Choose a suitable control under the current planning hierarchy and check the Rule Book arrangements for both walking and working.
The work plan covers more than train movements
Network Rail standard NR/L2/OHS/019, Safety of People at Work on or Near the Line, links three kinds of risk. Operational risks include movements of trains, on-track plant and on-track machines. Site risks arise from the location, for example an open line beside the work or a hazard on the access route. Task risks result from the activity, for example lifting a cover or using a cutting tool. Some hazards affect more than one category. The practical check is whether the pack shows who controls the hazard and how the control will work.
The Safe Work Pack (SWP) records the selected controls. In its Bookham Tunnel report, paragraphs 31–36 and 151, RAIB explains the planning roles and records the change made by Network Rail in Issue 13. The planner must develop the pack with the person in charge (PIC) who will carry out the work. Network Rail’s RailHub planning tool helps compile the pack and share information. The planner and PIC still have to check that the information describes the actual work.
| Role | Responsibility in planning |
|---|---|
| Responsible manager (RM) | Appoints the planner and person in charge and reviews and authorises or rejects the verified pack. |
| Safe system of work planner | Brings together relevant work, route and hazard information, works with the person in charge who will undertake the work and obtains competent advice where needed. |
| Person in charge | Helps plan the work, verifies the pack, then decides whether it is acceptable on site and implements and maintains the safe system. |
The controller of site safety (COSS) applies the Rule Book duties for the safe system for the group. The person in charge under 019 is accountable for the safety of the workgroup, including task and site risks. They may also act as COSS if appointed and competent. If different people carry out the COSS and PIC duties for the job, check who is assigned each duty in the approved arrangements. The PIC’s accountability extends to how the protection, site and task controls fit together. A planner submitting a pack does not complete PIC verification or responsible manager authorisation.
Check the route, the activity and each phase
Use the current Sectional Appendix to check the relevant running lines, layout and permissible speeds. Use the applicable National Hazard Directory information and local knowledge to identify site and access hazards. Follow the applicable notices and check for changes. For example, a plan can correctly identify the work line at the stated mileage and still miss an adjacent open line on the walking route.
Use the highest suitable control in the applicable planning hierarchy. Check the choices for each phase separately. Handbook 7 Issue 10 separates the arrangements for a group walk from those for work at the site. It also requires a blocked line where the work affects the safety of the line, subject to the applicable instructions. For instance, reaching a worksite on a prearranged route does not protect an open line that the task would obstruct. The Network Rail technical notice identifies COSS (LKT) as a separate competence for planning and delivering lookout-warning arrangements.
Verify in advance and check at the site
Allow time for both verification by the PIC and review and authorisation by the responsible manager before planned work. Use the current company instructions for their deadlines and for any change of PIC or incident-response process. The PIC rechecks and accepts the authorised plan at the site only if it can be implemented there. In RAIB’s Bookham investigation, the pack contained a blockage for a different tunnel and line. At the site, compare the actual access point, line name and work limits with the detail used to agree protection. A correctly completed check for the wrong line is useless to the group.
Example: the wrong approach on the map
The planner and person in charge find that a proposed path to a planned inspection would pass close to the open relief line. An authorised route from another access point stays clear. They use the hazard information to check that route, record it in the work pack and identify a separate safe system for the inspection itself. The person in charge verifies the revised pack and the responsible manager then considers authorisation. At the site, the person in charge checks that the access point is usable and the approved arrangements match what is there before implementing the safe system.
The planner is developing a pack for planned work under Network Rail standard 019 Issue 13. Who should work with the planner?
The person in charge who will undertake the work
Any available COSS, even if they have no part in the work
The first driver expected to pass the site
Only the signaller who might later grant a blockage
Which source provides the running-line and permissible-speed information needed for planning?
Only the briefing attendance record
The plant operator’s task briefing alone
The current Sectional Appendix and applicable updates
The sponsor’s training register
Who verifies the planned pack before it is sent for authorisation?
The signaller when the blockage is granted
The person in charge, followed by the responsible manager’s authorisation review
The site warden before the group enters
The planner alone while preparing the first draft