4.1 Planning and Requesting a Line Blockage

Key Takeaways

  • Handbook 8 governs blocking a line by an IWA, COSS or protection controller outside the possession arrangements in Handbook 9.

  • Agree the affected line, work, site limits, timing, protecting signals or block markers and the additional arrangements with the signaller.

  • The current Line Blockage Form is NR3180. Use the correct manual or RailHub version.

  • Record the authority number the signaller gives after agreeing the recorded details and completing protection. Then apply the site arrangements and brief the group.

Last updated: November 2026

When Handbook 8 applies

A line blockage protects a defined portion of line from movements under an agreed arrangement with the signaller. RSSB Handbook 8 Issue 10 sets out how an individual working alone (IWA), controller of site safety (COSS) or protection controller (PC) arranges it when the line needs to be blocked and no trains or on-track plant are involved in the work on that line. The handbook gives particular exceptions about a train remaining in the section. In a possession, the COSS follows Handbook 9 or Handbook 9 ERTMS for the work. A blockage protects the identified line and limits. It does not provide automatic protection for access over a different line or isolate electrical equipment.

Check the requirements of Handbook 7 section 4 when the work affects safety of the line or the group would be at risk from trains. A warning method cannot substitute for a blockage where a blocked line is required. Some tasks may use another permitted safe system, and the actual lines and limits must be agreed for the selected method.

Agree the details and read back the record

The Line Blockage Form NR3180 is the record. The RSSB catalogue identifies issue 07-25 for a Network Rail RailHub-generated form and issue 02-26 for manual completion. A completed draft or pre-planned schedule does not give authority to start work.

Agree with the signallerWhy it matters
The line, type of work and locations between which it will take placeThe work limits and routes of potential train movements must be understood the same way.
How long the work needs and when permission can first be givenA planning time is distinct from the grant of authority.
The signals to be kept at danger or block markers at which the route is to be closedAccount for both directions on a single or bidirectional line.
Any additional protection and arrangements for points, single line working and level crossingsThe behaviour of train and road movements near the site can change which protection is needed.

Complete the form and read the entry to the signaller to confirm that it is correct. For work beyond points that still need to be used, the signaller has to protect the work by applying the handbook rule about their position before a train approaches them. Normally the work site must be at least 200 metres from the protecting signal or block marker. If work affecting the safety of the line has to take place within that distance, tell the signaller. Section 1.4 requires protection at the previous signal or block marker and sets conditions for any train that goes beyond it.

When the blockage can be treated as granted

The signaller tells you when the protecting signal has been placed to danger or the route has been closed at the protecting block marker, and confirms it will stay that way. Arrange the agreed additional protection under section 2. If additional protection is required, it has to be in place before the authority number is given. Normally the affected portion must be clear of all trains. There are two exceptions in section 3. Where authorised, you and the signaller can be sure that all trains have passed beyond the site of work. The other is where a disabled or standing train will make no further movements until the blockage is given up.

Once both parties are sure the form is correct and the arrangements are in place, the signaller gives the authority number. Record it on NR3180. For a group working, or when the work will affect the safety of an approaching train, section 4.1 then requires a visible red flag or red light in the four-foot on the approach to the work site, in both directions on a single or bidirectional line or when single line working is in use. Complete the site's safe system and briefing before releasing the group to work.

Worked request

An inspection team plans work on the Down Main between two named signals. A train is still within the affected portion and no exception applies. While the group stays in its safe area, the COSS agrees the work, limits and time and reads back NR3180. The signaller confirms when the line is clear and the agreed signal arrangements are in place. Once the agreed additional protection is in place, the signaller gives the authority number. The COSS records it, arranges the red flag or light for the work site, and briefs the group. Knowing that a train has passed your position does not by itself establish the line blockage or authorise work.

Loading diagram...
Agreeing and Granting a Line Blockage
Test Your Knowledge

What confirms that the COSS may treat a planned line blockage as granted under Handbook 8?

A

The planned start time has arrived

B

The COSS sees the last booked train go past

C

The agreed arrangements are complete and the signaller’s authority number is recorded on NR3180

D

The Safe Work Pack has been verified but the signaller has not been contacted

Test Your Knowledge

When discussing a line blockage on a bidirectional line, which approaches must be accounted for in the agreement?

A

Both directions, using the relevant protecting signals or block markers

B

Only the direction normally used by passenger trains

C

Only the direction from which the last train approached

D

All adjoining lines are automatically included

Test Your Knowledge

Which document is the current line blockage record used here by the COSS and signaller?

A

RT9909, the safe-work briefing record

B

RT3199, the work-site certificate

C

A copy of a possession notice alone

D

NR3180, using the applicable manual or RailHub form