2.3 Delivering the COSS Safety Briefing & Worker Verification
Key Takeaways
Check the authority and competence needed for the person’s actual duties before allowing access through the applicable Sentinel procedure.
Brief the task, location, open and blocked lines and relevant controls. Check that the group understands and record confirmation on RT9909.
Agree a safe route and arrange briefing for a late arrival. If the COSS must leave the group, stop the work and make sure the group is in safety.
Under Handbook 7, check and retain an approved visitor permit, brief the visitor and stay with them until they leave the operational railway.
Check the people, then check their understanding
RSSB Handbook 7 Issue 10, sections 5 and 7 requires the controller of site safety (COSS) to make sure the workgroup understands the safe system before going on or near the line. A COSS doing those duties uses the blue identifier with white COSS lettering, worn as an armlet on the left arm or a badge on the upper chest.
Use the applicable Sentinel swipe-in process to confirm authority to work and check competence for the proposed duties before admitting a sponsored worker. The status of a worker’s Personal Track Safety competence does not by itself prove that they can operate plant, use a warning system or accept a particular permit. Check the record and applicable restrictions for the person and assignment. Follow the site procedure if the check cannot be completed or the system refuses access. Familiarity with the worker is not a substitute for a valid check.
What to brief
Tell the group what the work is and where it will take place. Give location references the workers can recognise. Cover the arrangements that apply to the job:
- Lines and access: Identify the blocked and open lines and include the route and arrangements for any walking phase.
- Barriers and wardens: Tell workers to stay on the safe side of a barrier and avoid leaning on it or placing tools on it. Identify any site wardens and the working limits.
- Warning and response: Explain the equipment warning or the lookout warning and the position of safety. Identify the site lookouts if that system is in use.
A general direction such as “over there” is easily misunderstood on a site with parallel lines.
Ask workers to show that they understand, for example by pointing to their safe boundary, naming the adjacent open line and saying what they will do when warned. These are ways of checking understanding. If someone points at the wrong line, stop and clarify the arrangements before they go on or near the line. Each worker confirms understanding by signing the safe-work briefing form, RT9909. Collecting signatures does not resolve a misunderstanding.
Joining the group and visitor permits
A late arrival who is at an access gate needs a safe way to join. Under section 5.4 the person speaks to the COSS before walking to the work site. Agree the access point and intended destination, then give the route and set up the applicable safe system as needed. Some locations can be reached away from the line. Others require the COSS to come to the person, brief them and accompany them. If the COSS must leave the workgroup, stop the group’s work and ensure everyone is in a position of safety.
A person with a visitor permit under company instructions has a separate process in section 8. Check the document that confirms approval, sign and retain the permit, brief the visitor on the safe system, and stay with them until they leave the operational railway. Follow the permit’s limits on activities. A visit is not a way to assign a safety-critical duty to a person who lacks the required competence.
For example, an approved visitor may come to observe a task without the competence needed to do it. Brief them on the part of the site they can visit, including any open line or boundary, and keep them with you. The worker swipe process and a visitor’s permission serve different purposes.
Example: a late delivery changes the route
A competent machine operator arrives after the group has started work. Construction at the gate means the route in the earlier briefing is no longer available. The operator contacts the COSS and waits in safety. The COSS checks the person and agrees an applicable route and arrangements before they move, and covers the worksite briefing and acknowledgement before the person joins the work. If the COSS needs to leave the group to meet the operator, the group stops and moves to a position of safety first. Do not send the operator to follow an improvised route along a running line.
If someone raises a safety concern, Network Rail’s Worksafe procedure tells them to stop, move to safety and explain the concern promptly to the person in charge. The person in charge discusses and assesses it with them. Work remains stopped if there is no agreement that it can proceed safely, and the matter is escalated to the manager.
Which action best verifies understanding during a COSS safe-work briefing?
Obtain signatures without discussing which line is open
Ask a worker to point out the open line and explain what action they take when warned
Ask only the foreman and assume the answer applies to everyone
Hand the pack around without discussing it
A late worker calls from the access gate. The COSS must leave the group to accompany them. What must happen before the COSS leaves?
The group can keep working as long as it stays within sight of the gate
Only the new worker must stop while the COSS leaves
The late worker must follow the group’s footprints to the work site
Stop the group’s work and make sure everyone is in a position of safety
A worker thinks the current arrangement has become unsafe. What is the immediate Worksafe response?
Stop, move to safety and promptly tell the person in charge what is wrong
Keep working until a planned break
Leave without telling the person in charge
Continue if another worker agrees to watch the open line