9.2 Off-Site Tiny Houses and the Two Municipal Permits

Key Takeaways

  • Section 1.11 applies to qualifying previously unoccupied houses with at most one dwelling unit and no more than 37 m² of building area.

  • For partial construction, check the limited applicable-law and installation exemptions and the conditions that apply when the installation site is known or unknown.

  • The installation municipality must issue a s. 8 permit before installation. Its time periods under the specified clauses start on the later of two statutory dates.

  • Each municipality receives notices for the work covered by its permit. The originating official’s compliance letter and other records support the later installation review.

Last updated: November 2026

Confirm that the house meets Section 1.11

Under Division C 1.11.1.1., the house has at most one dwelling unit and a building area of 37 m² or less. It is to be partially constructed in one municipality and moved for installation in another, or partially built in one location and moved for installation at a location not yet known. In either case it must not have been previously occupied. The rest of Division C Part 1 applies except where Section 1.11 provides otherwise.

For example, a 36 m² one-unit house built in a workshop and towed to a known site in another municipality can meet this scope. The delivery route alone does not settle the issue. A previously occupied 36 m² house or a house with two dwelling units fails an explicit condition. A label such as tiny house does not replace the test.

Separate partial construction from site installation

Under 1.11.1.2.(1), with the applicable conditions met, an applicant applying to the chief building official (CBO) in the municipality of partial construction can defer certain demonstrations to the installation stage. For an ordinary s. 8(1) permit, this applies to the applicable-law part of Act s. 8(2)(a). For a conditional permit, it applies to s. 8(3)(a). It also applies to Code requirements relating to installation at the site. The remaining criteria and conditions must be checked. A limited exemption from showing compliance with some requirements at the first stage does not turn the first permit into authorization to install.

Site at first applicationConditions under 1.11.1.2.(2)
KnownGive the address or location and information about anticipated installation needed to design the house. The proposed construction must meet the location-dependent Code requirements at that site.
UnknownSubmit a declaration of the location assumptions used in the design and information about anticipated installation needed to design the house. The proposed construction must meet the location-dependent requirements at a location with the declared characteristics.

These requirements include matters such as climatic and seismic loads, temperature, limiting distance and exposing building face, soil gas control and firefighting access. For example, if the location is unknown and the designer assumes a specified snow load, that assumption must be documented. A later installation site with a more demanding load needs evidence that the proposal meets the actual site’s requirements.

Transfer records and apply the installation clock

The first applicant must give the purchaser the permit documents it submitted or received, including as-constructed plans and a declaration of assumptions if applicable, as well as compliance letters and inspection materials. Under 1.11.1.2.(5) and (6) the installation site requires the receiving municipality’s Act s. 8 permit. The applicant demonstrates compliance with the applicable matters deferred from the first stage and the other s. 8 requirements, and submits the first-stage documents they received. This can require local zoning and evidence about the actual site installation.

Sentence 1.11.1.2.(7) sets the start for the periods in Sentences 1.3.1.3.(1) and (3) and Clause (6)(b) using the later of the date the partial-construction permit is issued and the date specified by 1.3.1.3.(7). For example, suppose the qualifying installation submission is received Wednesday, May 27, 2026, producing May 28 under the regular start rule. If the partial-construction permit is issued Monday, June 1, the special start date is June 1. Keep this start-date rule distinct from the period length and excluded days under the applicable provisions.

Suppose the initial application names a site in one municipality but the purchaser selects another. The receiving application must address the actual installation and local applicable law. The original application’s drawings and compliance records still document what was constructed. For a design that depended on the first location’s soil gas or limiting-distance assumptions, check whether the documentation also demonstrates compliance at the replacement site.

Direct each inspection notice to the correct municipality

Under 1.11.1.3., give the prescribed notice to the CBO or registered code agency (RCA) for the municipality whose permit covers the construction being inspected. The originating municipality’s CBO gives its permit holder a letter confirming which prescribed notices were received, that the related inspections were carried out, and that no contraventions were found or those found were remedied. The installation permit holder gives the receiving CBO additional inspection letters, documents or information not already supplied at application, or confirms they have received none. A compliance letter records the inspection result for partial construction. The permit file for installation also needs the actual site evidence and applicable approvals.

Primary references

Building Code Act, 1992 · 2024 Building Code Compendium, Division C Part 1 · Ontario tiny-home permits and inspections

Test Your Knowledge

Which proposal meets the dwelling-unit, building-area and move conditions of Division C 1.11.1.1., assuming the described partial construction?

A

A previously unoccupied one-unit house of 37 m² to be moved for installation in a different municipality.

B

A previously occupied one-unit house of 34 m² to be moved to a different municipality.

C

A previously unoccupied house with two dwelling units and 37 m² of building area.

D

A previously unoccupied one-unit house of 39 m² to be moved to a different municipality.

Test Your Knowledge

At the partial-construction stage the site is unknown. What does 1.11.1.2.(2) require as a condition of the limited exemption?

A

Omit all location-related design information until the house is moved.

B

Declare the location assumptions, include necessary installation information, and design to Code requirements for those assumed conditions.

C

Use the originating municipality’s zoning as conclusive evidence for every future site.

D

Acquire an installation permit for the workshop even though the home will be installed elsewhere.

Test Your Knowledge

For a qualifying installation permit, the date under 1.3.1.3.(7) is May 28 and the partial-construction permit issues June 1. On what date do the periods specified in 1.11.1.2.(7) begin?

A

May 27.

B

May 28.

C

June 2.

D

June 1.

Test Your Knowledge

Which official issues the letter confirming the prescribed notices and inspection outcomes for partial construction under 1.11.1.3.(3)?

A

The purchaser’s architect.

B

The provincial Minister.

C

The CBO of the municipality where the house was partially constructed but not installed.

D

The CBO of the receiving municipality before reviewing installation.