4.2 Occupancy After Completion and in Stages

Key Takeaways

  • For the section 11 completion route, give notice of completion. The required final certificate or inspection and compliance steps depend on whether an agency has the specified appointment.

  • Article 1.3.3.1. supplies general unfinished-building occupancy conditions. Article 1.3.3.2. provides a distinct route for qualifying low-rise residential buildings.

  • Article 1.3.3.4. requires a permit for specified residential buildings. It includes requirements for fire safety, the envelope, tested services and required garage door self-closing devices.

  • Special permit provisions apply to specified Part 3 buildings, affected lands in the Lower Don and Downtown Brampton, eligible super tall buildings and projects with deferred development charges.

  • For Article 1.3.3.8., check both charges payable before occupancy and the applicable building readiness criteria.

Last updated: November 2026

Decide which occupancy route governs

Under s. 11 of the Building Code Act, 1992, before occupancy of a newly erected or installed building or part, give notice of the completion date to the chief building official (CBO) or registered code agency (RCA), subject to the Code’s authorizations. Under s. 11(3) a required final certificate applies for agency appointments under s. 4.1(4)(b) or (c), or under s. 4.2. In the other s. 11(4) cases the building or part must have been inspected or ten days must have elapsed after completion notice is served on the CBO, and any s. 12 order must be complied with. The ten-day rule in s. 11 does not confer an occupancy permit when a particular Code rule requires one. Building Code Act, 1992, s. 11

General unfinished and low-rise residential routes

Division C Article 1.3.3.1. permits early occupancy under an occupancy permit issued by the CBO or their designate when applicable conditions are met. Check the structure and enclosing walls to the roof, requirements for the area to be occupied and exits, isolation from ongoing construction, and operational systems. For example, completed ground-floor offices remain unavailable if the required exit route from the highest occupied floor is incomplete. When an RCA with the specified post-permit appointment is involved, check the agency’s certificate and the CBO’s permit role separately.

Article 1.3.3.2. applies to qualifying unfinished residential buildings no taller than three storeys and no larger than 600 m² in building area. It allows at most one dwelling unit above another and at most two sharing common egress, with no tourist accommodation or retirement home use. Check the article’s exclusions and the complete, operational, inspected and, where specified, tested components. Under Article 1.3.3.3., a person taking or permitting early occupancy under Article 1.3.3.1. or 1.3.3.2. must notify the CBO promptly upon completion.

Article 1.3.3.4. imposes a separate occupancy permit on a specified class of residential buildings. Its size limits are three storeys and 600 m² of building area, with no unit above another, no shared means of egress, no tourist accommodation and no retirement home. Check the exceptions for existing altered buildings or applicable Article 1.3.3.8. For a new one-unit house in this class, verify the structure and envelope, firefighting access, alarms and egress, required garage exhaust fume barrier and self-closing devices, and the required operating and tested services. A missing required self-closer on the garage-to-dwelling door fails the occupancy conditions even if finishes are nearly done.

Special occupancy permits

Division CWhen to open the article
1.3.3.5.Scope of Division B Article 3.2.2.51. or 3.2.2.60. Check the specified conditions, including structure to roof, envelope, separations, access and operational systems, and the exception for certain existing work.
1.3.3.6. and 1.3.3.6.A.A mapped Lower Don or Downtown Brampton property. Check the location-specific exemption, demonstration of flood protection and other conditions. The Brampton rule includes an exception for qualifying non-residential temporary buildings.
1.3.3.7.Proposed occupation before structure and enclosing walls reach the roof of a building at least 65 storeys or over 250 m high. Notice of intent must be given at the first s. 8 application. Check the extra safeguards and reports.
1.3.3.8.Development charges payable under s. 26.1(3.1) of the Development Charges Act, 1997. Before issuance check charges payable at that stage and the applicable construction criteria.

For the super tall building route, look up the requirements for the structure to extend ten storeys above the uppermost storey to be occupied, subject to the stated limited floor assembly exception, and the enclosing walls to extend five above it. Other conditions address separate access, fire protection and occupant safety during construction. Once structure and exterior walls reach the roof, Article 1.3.3.7. directs the reader to Article 1.3.3.1. for occupation of the remainder. For an occupancy question, use only the branch matching the project’s height, timing and notice facts.

Development charge deferral is a separate occupancy gate. When Article 1.3.3.8. applies, technical readiness alone does not authorize occupants to move in before payment of the charges required before issuance. Where the Code links an occupancy step to applicable compliance under s. 168.3.1 of the Environmental Protection Act, check that requirement as well. Compendium, Division C Part 1 · Ontario Building Code amendments

Test Your Knowledge

The building is complete. No special Code occupancy rule applies, and an agency has the applicable s. 4.1(4)(b) appointment. What does s. 11 require besides notice of completion?

A

The prescribed final certificate

B

Ten days of silence in place of the agency certificate

C

A plans review certificate as the only completion document

D

A written conditional permit agreement

Test Your Knowledge

A new house falls within Article 1.3.3.4. A required self-closing device on the door between the built-in garage and dwelling is missing. Can the CBO issue an occupancy permit on the stated facts?

A

Yes, if the owner accepts responsibility.

B

Yes, if ten days have elapsed after a completion notice.

C

Yes, if the exterior envelope is complete.

D

No. The missing required self-closing device fails a condition for issuance.

Test Your Knowledge

A qualifying 70-storey building seeks partial occupancy before the enclosing walls reach the roof. When must notice of intent to use Article 1.3.3.7. have been provided?

A

At the time of the first lease

B

At the time of the first s. 8 permit application for the building

C

After the first occupied storey is inhabited

D

Upon application for the last permit for the building

Test Your Knowledge

A building has met the applicable construction criteria under Article 1.3.3.8., but charges payable before issuance remain unpaid. What happens to the requested occupancy permit?

A

It must be issued if a final inspection occurred.

B

It must be issued after two days.

C

It cannot be issued before the required charges have been paid.

D

An RCA may issue it in place of the CBO.