6.3 Alternative Solutions and Performance Evidence
Key Takeaways
Division C Part 2 applies to all buildings covered by the Code. Division A 1.2.1.1. sets the performance test for an alternative solution.
Identify the applicable acceptable solutions and their attributed objectives and functional statements. Supply evidence that the proposed solution reaches the required performance in those areas.
Explain the assumptions and limits of the evidence, along with relevant testing, commissioning, operation and maintenance conditions.
When no published suitability test exists, a test can simulate or exceed anticipated service conditions or compare with a similar known acceptable material or system.
Start from the applicable acceptable solution
Division C Article 2.0.1.1. applies Part 2 to every building covered by the Code. Division A Article 1.2.1.1. sets out two routes to Code compliance. The first follows the applicable acceptable solutions in Division B. The second uses an alternative solution that achieves at least the minimum performance of those solutions for their attributed objectives and functional statements. Supplementary Standard SA-1 identifies the objectives and functional statements attributed to the acceptable solutions. Read each functional statement in relation to its associated objective. A comparison that addresses only structural strength can leave unanswered questions about a fire-safety function attributed to the same prescriptive provision.
Begin with the actual building and question. Establish the occupancy and other facts that determine which provisions apply, identify the design feature in question, and describe the applicable Division B reference. Then ask which performance outcomes the proposal must reach. Comparing two products without a baseline does little to establish the Code comparison. A change might also affect more than one acceptable solution, so identify all applicable provisions before designing a test program or choosing other evidence.
Assemble the submission for the reviewer
Under Division C 2.1.1.1., the proponent gives the documentation to the chief building official (CBO) or appointed registered code agency (RCA) as applicable. The documentation identifies the applicable objectives, functional statements and acceptable solutions and establishes the required performance using past performance, a test that meets Article 2.1.1.2., or another evaluation. Sentence (2) also requires information on relevant assumptions, limiting or restricting factors, testing procedures, studies or building performance parameters, including relevant commissioning, operation and maintenance requirements.
| Part of the submission | Question to answer |
|---|---|
| Applicable provisions and attributions | Which Division B acceptable solutions establish the baseline, and which SA-1 objectives and functional statements are attributed to them? |
| Evidence | How does the proposed design reach the applicable performance? Does the evidence cover the assembly, intended application and relevant conditions? |
| Boundaries and operation | Which assumptions, installation constraints, commissioning steps or ongoing maintenance requirements are necessary for the evidence to apply? |
The last row matters when a design depends on a prescribed arrangement of components or on continuing inspection and maintenance. For example, if an engineering evaluation applies only to a particular wall assembly and specified joint details, record those restrictions for construction and future review. The alternative-solution documentation rule and the professional qualification rules are separate. Show performance under Article 2.1.1.1. and check any independently applicable design qualification or professional design requirement.
Select tests for the actual performance question
Under 2.1.1.2., where a published test method for suitability does not exist, design the test either to simulate or exceed anticipated service conditions or to compare the material or system with a similar one known to be acceptable. Results from a different test standard can be used if the alternative standard gives comparable results. Explain what makes the conditions or comparison relevant to the actual project.
Suppose a design proposes a new joint arrangement in a fire separation. The engineer identifies the applicable separation and continuity requirements and the SA-1 attributions. A test on an assembly using the proposed joint geometry can inform the comparison if its exposure and sample support the building’s intended use. Evidence from a different assembly can be useful if the designer documents which features are comparable and which differences the evaluation accounts for. If a result depends on specific dimensions or installation details, carry those limits into the submission.
If an installed system depends on an initial commissioning check and recurring inspections, record both the initial check and the continuing conditions in the documentation. If construction later changes a material detail of the accepted design, assess whether the evidence still supports the revised detail and whether Act s. 8(12) requires notification, filing the details and obtaining the CBO’s authorization. For example, a different joint sealant may affect the test’s applicability even where the finished wall looks identical.
A project’s accepted documentation establishes compliance on the facts of that project. On a second building, a design team can reuse relevant evidence by showing that it applies to the new assembly and use. The earlier permit does not compel a new CBO to accept the design. If an applicant and the reviewer dispute technical sufficiency, check the parties and scope for a Building Code Commission application under Act s. 24(1)(a).
Primary references
2024 Building Code Compendium, Division A Part 1 · 2024 Building Code Compendium, Division C Part 2 · Building Code Act, 1992
A design team wants to rely on an alternative solution accepted for a different building. What should it do for the new permit application?
Show that the evidence applies to the new project and document performance against its applicable acceptable solutions and attributions.
Submit only the previous permit, which binds all Ontario chief building officials.
Match the previous occupancy label and omit all assembly evidence.
Request a new municipal construction by-law adopting the assembly.
A new assembly is tested for the required performance, and the results depend on one joint geometry and a specified maintenance program. Which information belongs in the submission under 2.1.1.1.?
The supplier’s registration and sales records for installations using the joint.
The assembly’s estimated cost and the contractor’s written acceptance of the warranty.
The test assumptions, geometry limits and applicable commissioning, operation and maintenance requirements.
A zoning letter and the scheduled dates of planned inspections in place of test conditions.
There is no published test method for a proposed alternative solution. Which testing approach is allowed under Division C 2.1.1.2.(1)?
Test under any convenient conditions, regardless of its use.
Compare performance with a similar known acceptable material or system, or simulate or exceed anticipated service conditions.
Use the test only if there is a prior ruling on the identical product.
Reject all further performance evidence until a national test standard is published.
A proposed assembly meets one attributed objective, but the submitted evidence does not address another applicable functional statement associated with a different objective. Is the first result sufficient under Division A 1.2.1.1.?
Yes. Performance is averaged across all the applicable objectives.
Yes. A lower cost offsets an unmet applicable functional statement.
Yes. A new material must satisfy only one attributed objective.
No. The submission must address the applicable objectives and functions.