9.3 Factory Certification and Site Installation

Key Takeaways

  • Division A applies the Code to site-built and factory-constructed buildings. Division C 1.12.1.1. provides a deemed-compliance rule for the specified Part 3 manufactured work.

  • Check for certification under CSA A277 and identify the manufactured building or part it covers.

  • Components designed and constructed outside the place of manufacture and installation at the site remain subject to the Code.

  • Review site-specific permit, installation and inspection requirements for the actual project, including the work and interfaces outside the manufactured portion.

Last updated: November 2026

Identify what is manufactured and what the certificate covers

Division A 1.1.1.1. applies the Building Code to site-built and factory-constructed buildings. Division C 1.12.1.1.(1) addresses a manufactured building or manufactured part within the scope of Part 3. Subject to Sentence (2), such work is deemed to comply with the Code if it is certified in accordance with CSA A277, the procedure for certification of prefabricated buildings, modules and panels. Read the article as a compliance rule for the specified manufactured work. Identify the building or part to which the certification applies and confirm the standard.

For example, assume a building is within the scope of Part 3 and contains three manufactured modules. A document covering one module supports application of the rule to that manufactured part if the certification meets the article. Ask for evidence covering the remaining modules before relying on the same rule for them. A supplier’s description of a module as prefabricated establishes how it was made. The additional fact for applying Sentence (1) is certification in accordance with the named standard.

Allocate components and installation to the correct review

Part of the projectApplicable compliance question
Certified manufactured building or part in the article’s scopeDoes the CSA A277 certification cover the manufactured work for which the applicant relies on 1.12.1.1.(1)?
Components designed and constructed outside the place of manufactureSentence 1.12.1.1.(2)(a) maintains the Code requirements for those components. Check the applicable site drawings, details and supporting evidence.
Site installationSentence 1.12.1.1.(2)(b) maintains Code requirements for installation. Check the design of the work that locates, supports, connects or secures the building on the actual site, as applicable.

Consider a certified manufactured Part 3 building delivered to a site where a separate contractor designs and builds the foundations. The certificate can support the covered factory work. The Code still applies to the foundations and the installation, including the interfaces between the modules and their supports. The designer should identify site conditions and the installation details that matter to the work. For an inspection question, ask what will become concealed and which prescribed notice applies to that site work. Certification of the module does not supply the readiness notice for the installation.

Trace the administrative steps for the actual construction

Apply the usual permit analysis under Act s. 8 when the project involves construction requiring a permit. A certificate that supplies evidence of Code compliance for the manufactured portion leaves the chief building official (CBO) to assess the other issuance requirements, including applicable law and the information the permit process calls for. Where an installation requires the construction of foundations or anchorage on site, the drawings submitted for the permit should let the reviewer evaluate that work and its relationship to the manufactured building. Check Division C 1.3.2.2. for the permit holder’s site documentation duties.

At each prescribed construction stage, the permit holder gives readiness notice to the CBO or registered code agency, as applicable, under Act s. 10.2 and Division C 1.3.5. The applicable inspection timeline follows receipt of the prescribed notice. For example, if work includes a required inspection of footing formwork before concrete, the administrator should be able to identify the site work and its permit from the notice. The manufactured building’s approved dimensions or support details may help the inspector evaluate the foundation. They do not eliminate the trigger for a prescribed inspection.

Suppose the site is within a zone where the proposed use is allowed, but the installer wants to anchor a module at different points from those shown in the approved permit documents. Review the attachment as part of the installation. If a change to the permit documents is material, Act s. 8(12) requires notice, filing details and obtaining CBO authorization before making it. The planning decision and the module’s certification do not establish that the revised connection satisfies the Code.

Section 1.11 addresses a different question: when a qualifying previously unoccupied tiny house can use separate partial-construction and installation permits. Section 1.12 addresses whether qualifying certified manufactured work is deemed to meet the Code and what remains subject to site review. In a factory-construction scenario, first identify which regulatory provision the question asks you to apply. The classification, certification document and location of the work each answer a different part of the permit decision.

Primary references

Building Code Act, 1992 · 2024 Building Code Compendium, Division A Part 1 · 2024 Building Code Compendium, Division C Part 1 · O. Reg. 163/24 · General Legal/Process syllabus

Test Your Knowledge

A building within the scope of Part 3 has a manufactured portion certified under CSA A277. What effect does Division C 1.12.1.1.(1) give to that certification?

A

It establishes zoning compliance for installation wherever the module is used.

B

It exempts the whole building including all work undertaken at the site.

C

It deems the certified manufactured portion compliant, subject to Sentence (2).

D

It serves as a permit for installation in the receiving municipality.

Test Your Knowledge

A contractor builds foundations designed and constructed outside the manufacturer’s plant. The Part 3 modules going on top are certified under CSA A277. How are the foundations treated?

A

The Code requirements continue to apply to the foundations.

B

They are deemed compliant by the module certificate alone.

C

They are outside the Code unless the owner requests a review.

D

They must follow the zoning by-law instead of the Building Code.

Test Your Knowledge

The permit for installation of a certified manufactured building includes site work at a stage for which the Code prescribes a readiness notice. What should the permit holder do?

A

Send the notice to the factory certification organization in place of the local official.

B

Give the prescribed notice to the CBO or registered code agency, as applicable.

C

Skip the notice because the manufactured building was certified.

D

Wait until after finishing the work before checking the prescribed notice stage.

Test Your Knowledge

A permit applicant presents CSA A277 certification for the factory work but the proposed site fails an applicable zoning requirement. What follows for an ordinary construction permit?

A

The certification creates a zoning variance.

B

The CBO must grant the permit under Division C 1.12.1.1.

C

The municipality where the modules were built issues the installation permit on that basis.

D

The certificate supplies no substitute for meeting applicable law under Act s. 8(2)(a).