6.4 Ministerial Rulings, Interpretations and Innovative Materials
Key Takeaways
Section 28 lets the Building Materials Evaluation Commission authorize innovative materials, systems or designs on application and subject to conditions. Check the Canadian Construction Materials Centre restriction in s. 28(6).
Section 28.1 governs written binding interpretations of an existing Code provision. The ministry posts them online and provides a written copy on request.
Section 29(1)(b) concerns amendments to referenced documents. Section 29(1)(c) concerns approval of alternative materials, systems or designs and has additional Code criteria.
A s. 29(1)(c) ruling applies across Ontario unless it states otherwise. It prevails over a conflicting s. 28 authorization.
Determine what the proponent seeks
A designer documenting performance for one project uses Division C Section 2.1. Ontario also has statutory mechanisms for authorizing the use of an innovation, interpreting a Code provision, and making a ruling about referenced documents or alternative materials. Identify the instrument by the action taken and the person or commission empowered to take it.
| Instrument | Authority and effect |
|---|---|
| Authorization under Act s. 28 | The Building Materials Evaluation Commission (BMEC) can authorize an innovative material, system or building design on application and subject to conditions. Under s. 28(5), use in the approved manner is deemed not to contravene the Code. |
| Written interpretation under s. 28.1 | The Minister interprets an existing Code provision in writing. The interpretation binds anyone exercising powers or performing duties under the Act and anyone subject to it. |
| Ruling under s. 29(1)(b) | The Minister can adopt an amendment to a code, formula, standard, guideline, protocol or procedure already adopted by reference in the Building Code. |
| Ruling under s. 29(1)(c) | The Minister can approve an alternative material, system or building design considered to achieve Code performance, subject to applicable criteria and ruling conditions. |
Check the BMEC and CCMC boundary
The Lieutenant Governor in Council appoints the BMEC’s members and may designate its chair and vice-chair. Under s. 28(4), the BMEC can research or examine construction materials, systems and designs, authorize innovative ones on application, and recommend Act or Code changes to the Minister. Read any authorization for its conditions, including use restrictions. Section 28(5) protects use in the approved manner. Section 28 is in the syllabus and Division C Section 2.3 is excluded.
Effective July 1, 2025, s. 28(6) bars the BMEC from exercising its s. 28(4) powers for a material, system or building design that the Canadian Construction Materials Centre (CCMC) has examined or expressed its intention to examine. For example, if the CCMC has announced plans to examine a new panel system, confirm whether the announcement meets that condition before attempting the BMEC route. The CCMC’s involvement does not itself approve the system under Ontario law. The same legislative changes repealed s. 29(1)(a), the former ruling route that adopted evaluation reports. Use the in-force alternatives in s. 29(1)(b) and (c) when the question asks what the Minister can do today.
Check the conditions of a Minister’s ruling
Under Division C 2.4.2.1., an approval under s. 29(1)(c) may be granted only if it is consistent with at least one of the following:
- A Building Code Commission decision on technical sufficiency under s. 24(1)(a).
- Approval of the material, system or design throughout another province or territory under its law.
- A revision of the specified 2020 National Building Code of Canada or National Plumbing Code of Canada approved by the Canadian Commission on Building and Fire Codes.
This consistency test applies to the approval route in clause (c). The ruling entitles a person to use the approved material, system or design across Ontario unless the ruling provides otherwise, and use in the approved manner is deemed not to contravene the Code under s. 29(6). Read the conditions and any geographic restriction. If that ruling conflicts with a BMEC authorization, s. 29(7) gives the ruling priority. Section 29(4) requires notice of a ruling in The Ontario Gazette at least once and availability on request. Division C Subsection 2.4.1. is reserved.
Distinguish interpreting the Code from investigating enforcement
Under s. 28.1(1) and (2) and Division C 2.4.3.1., a written interpretation binds the Act’s officials and regulated persons. The ministry must post it on the Building Code website and provide a written copy on request. A telephone explanation from a municipal official does not create a binding interpretation under this section. The syllabus excludes s. 28.1(3) and (4) and s. 29(2), (3) and (8).
Section 30 gives the Minister a separate inquiry power where there appears to be a possible failure of construction or demolition standards or of enforcement of the Act or Code. The Minister may designate a person to inquire, and s. 33 of the Public Inquiries Act, 2009 applies. An inquiry into enforcement failures and a written interpretation of a particular Code provision are different statutory actions.
Primary references
Building Code Act, 1992 · 2024 Building Code Compendium, Division C Part 2 · General Legal/Process syllabus · Ontario Building Materials Evaluation Commission · Protect Ontario by Building Faster and Smarter Act, 2025, Schedule 1
The Canadian Construction Materials Centre has expressly announced its intention to examine a new wall panel system. A manufacturer applies to BMEC for authorization of the same system in November 2026. What does Act s. 28(6) require?
BMEC can grant authorization until CCMC publishes its evaluation.
BMEC may authorize the system if it labels the result a ruling.
CCMC’s announcement automatically authorizes the system in Ontario.
BMEC must refrain from exercising s. 28(4) powers for that system.
The Minister seeks to resolve inconsistent municipal readings of the same existing Code sentence with a binding written interpretation. What instrument applies?
An interpretation under Act s. 28.1, with public access under Division C 2.4.3.1.
A site-specific permit issued under s. 8(2).
A construction-stop order issued by the Minister under s. 14.
A referral under the Corporations Act.
A proponent seeks a ruling under Act s. 29(1)(c) for an alternative system. Which fact can meet one of the consistency criteria in Division C 2.4.2.1.?
The manufacturer supplies a favourable assessment without a jurisdiction-wide approval.
A single municipality in another province permits the system on one project.
Approval is consistent with lawful approval of the system throughout another province or territory.
An Ontario municipality collected the ruling fee but had no comparable technical approval.
An in-force s. 29(1)(c) ruling conflicts with a BMEC authorization for the same use. Which instrument prevails?
The BMEC authorization if it is newer.
The Minister’s ruling under Act s. 29(7).
Whichever instrument was submitted first.
The instrument that allows the proposed design without conditions.
Sections you finish are checked off in the contents.