3.1 Building Permits, Exemptions and Applicable Law
Key Takeaways
Under s. 8(1), the requirement applies to people carrying out or causing construction or demolition of a building, subject to specific exemptions.
Division C Article 1.3.1.1. distinguishes exemptions from the permit requirement alone and exemptions from both permits and Code compliance.
Section 8(2) supplies the grounds that can prevent ordinary permit issuance, including licensing, design, completeness and fee requirements.
For s. 8(2)(a), use the list in Division A Sentence 1.4.1.3.(1) and match the exact provision and regulated activity.
A plans review certificate with the required information limits refusal on Code-compliance grounds for the certified construction. Check the other s. 8(2) grounds separately.
First decide whether section 8 applies
Section 8(1) of the Building Code Act, 1992 (BCA) prohibits constructing or demolishing a building, or causing either, until the chief building official (CBO) issues the permit. The Act’s terms are broader than everyday usage. Construction includes extension, material alteration or repair and installation of a prefabricated or relocated unit. Demolition includes removal of a material part. The building definition also includes certain structures at or below 10 m², standalone plumbing, sewage systems and designated structures. A person who commissions work and a person who carries it out can each fall within s. 8(1). Read s. 1 before applying a size shortcut.
Match the exemption to the precise project
| Division C | Exempt work | Conditions or limit |
|---|---|---|
| 1.3.1.1.(1)(a) | Demolition of a farm building on a farm | Verify it meets the Code's farm building definition. A residential farmhouse is a different use. |
| 1.3.1.1.(1)(b) and (2) | Construction or demolition in territory without municipal organization | Sentence (2) removes the unorganized-territory exemption for construction of a sewage system. Check independent exemptions, including Clause (1)(c). |
| 1.3.1.1.(1)(c) | Construction of a Class 1 sewage system | Verify the class. The exemption is from the s. 8 permit. |
| 1.3.1.1.(5) | A tent or group of tents | Maximum 60 m² aggregate ground area, unattached to a building and more than 3 m from other structures. The permit and Code exemptions both apply when all conditions are met. |
| 1.3.1.1.(6) | A qualifying storage shed | Maximum 15 m² gross area, up to one storey in building height, unattached to any building or structure, exclusively ancillary storage for a principal building on the lot, and no plumbing. The permit and Code exemptions both apply. |
| 1.3.1.1.(7) | Demountable stage or support structure outside Division B Section 3.17 | Exempt from the permit requirement and Code compliance. Check whether Section 3.17 regulates it. |
For two 28 m² tents, total the ground areas: 28 + 28 = 56 m². Suppose the tents are unattached and each more than 3 m from every other structure outside the group. All three conditions apply. Moving the same group to exactly 3 m from a masonry wall fails the distance condition. Exemptions here govern the building permit and Code. Separate rules such as land-use restrictions may still apply to the activity. Compendium, Division C Part 1
Apply all of the ordinary refusal grounds
The CBO must issue the permit under s. 8(2) unless a listed ground applies. Read the list as separate checks:
- Proposed work: A contravention of the Act, the Code or another applicable law under clause (a).
- Builder or vendor: An applicant who is a builder or vendor under the New Home Construction Licensing Act, 2017 lacks the licence under that Act, under clause (b).
- Required professional design: Construction that requires design by an architect, professional engineer or both under the relevant professional statutes has not been designed accordingly, under clause (b.1).
- Qualifications and insurance: A person who prepared the submission or gave a Code-compliance opinion lacks applicable qualifications or required insurance, under clause (c).
- Certificate, application and fees: A required plans review certificate lacks prescribed information, the application is incomplete or fees due are unpaid, under clauses (d)–(f).
Under s. 8(2.1), a submitted plans review certificate with prescribed information prevents the CBO from refusing on the ground that the construction covered by the certificate does not comply with the Code. Match the scope of the certificate to the construction in the question. The other statutory grounds still apply. For example, if a properly certified warehouse design conflicts with an applicable zoning by-law, the certificate does not resolve that conflict. Building Code Act, 1992, s. 8
Verify the exact applicable-law entry
For s. 8(2)(a) use Division A Sentence 1.4.1.3.(1). Read the provision and its qualifying description, since naming an Act does not bring every provision of that Act into this list.
| Project fact | Example of a listed requirement |
|---|---|
| Proposed development conflicts with local zoning | By-laws made under ss. 34 or 38 of the Planning Act |
| A proposed building needs conservation authority permission in a regulated area | Development prohibitions under s. 28 or the specified permit provisions under ss. 28.1 to 28.1.2 of the Conservation Authorities Act |
| The project involves a designated property's demolition | Applicable municipal consent under s. 34 of the Ontario Heritage Act, or other listed heritage provision for the stated designation |
| The proposal includes a new building for a child care centre | Plan approval under s. 14 of Ontario Regulation 137/15 |
| A planned structure needs permission near a provincial highway | A listed ministerial permit under s. 34 or 38 of the Public Transportation and Highway Improvement Act |
A permit problem involving property taxes illustrates the scope limit. If all s. 8(2) requirements are satisfied and the owner merely has an unrelated property-tax balance, that balance is not a ground to refuse. Separate taxes from fees due for the application, which do affect the permit under clause (f). For a change-of-use permit under s. 10, check the separate definition in Sentence 1.4.1.3.(2). Compendium, Division A Part 1
A submitted plans review certificate covers the proposed construction and contains the prescribed information. The CBO identifies a contravention of a listed zoning by-law. What effect does the certificate have?
It requires issuance even while the zoning contravention remains.
It limits Code-based refusal for the work it covers. Zoning remains a separate ground.
It delegates the zoning decision to the agency that issued the certificate.
It limits zoning-based refusal for the work it covers. Code compliance stays open.
An organizer puts up two unattached 28 m² canopy tents beside each other as a group, 4 m from every other structure. What is the result under Division C Sentence 1.3.1.1.(5)?
A building permit is required because two tents count as a group of tents requiring structural review regardless of size
A building permit is required because tents over 10 m² always meet the BCA s. 1 definition of a building
A building permit is required because the tents must be at least 6 m from other structures to qualify for exemption
The group is exempt from the s. 8 permit and Code compliance because it meets the area, attachment and separation conditions.
A construction application meets every condition for issuance under s. 8(2). The only outstanding debt is the owner’s municipal property-tax balance. What should the CBO do?
Issue the building permit.
Refuse the permit as if a prescribed application fee were unpaid.
Require a conditional permit agreement to collect the tax balance.
Refuse until the tax amount is added to the construction drawings.
On an active farm inside a municipality, a farmer wants to remove a barn used to store crops harvested on that farm and an old farmhouse used only as a dwelling. Assume no other exemption applies. Which demolition needs a s. 8 permit?
Neither structure requires a demolition permit because both are located on an agricultural parcel
Both structures require a demolition permit because all demolitions require a permit under BCA s. 8(1)
The barn is exempt as a farm building on a farm, but the residential farmhouse requires a demolition permit
Only the barn requires a demolition permit because agricultural buildings are regulated under Division B Part 2