5.2 Design Firms, Other Designers and Exemptions

Key Takeaways

  • The Act s. 15.11(5) trigger is a specified submission or required general-review report; it is not every act of drawing a building.

  • Division C distinguishes businesses providing design activities to the public from other designers. Test the two exemptions separately.

  • The public register lists different fields for design businesses and other designers. A BCIN identifies the person or firm; the registration class defines the scope.

  • The provincial Schedule 1 expressly exempts the specified Ontario architecture and engineering credential holders from completing the schedule. Other exemption claimants may still have to complete it.

Last updated: November 2026

When the designer rules apply

Section 15.11(5) of the Building Code Act, 1992 (the Act) covers designs and compliance information or opinions for the chief building official (CBO) in connection with a permit, a request under s. 8(12) or (13), or a required general-review report. Preparing the required written report based on general review is itself covered. The Act’s inclusive definition of design covers such things as sketches, plans, specifications and graphic representations for construction. Division A defines design activities by referring to these statutory activities. A casual sketch is not necessarily a regulated submission. At permit review, s. 8(2)(c) separately asks whether the person has any required qualifications and insurance.

RuleApply it to these facts
Division C 3.2.1. and 3.2.2.Section 3.2 supplies qualifications for s. 8(2)(c) and s. 15.11(5). If registration under 3.2.4.1.(1) is not required, test the other-designer rule in 3.2.5.1.(1) and its exceptions.
Division C 3.2.3.1.Registered refers to registration under 3.2.4.2.(1) in the business subsection and 3.2.5.2.(1) in the other-designer subsection.
Division C 3.2.4.1.A business offering regulated design activities to the public ordinarily registers with the director. It must arrange for a qualified person in the relevant class to review and take responsibility for the work and carry prescribed insurance under the applicable registration conditions.
Division C 3.2.5.1.An other designer must ordinarily register under 3.2.5.2.(1). An exemption can apply when a qualified person will review the design and take responsibility, or for the specifically listed types of design work.

A sole proprietor selling permit drawings for a new client-owned house cannot claim their client’s ownership as their own. If no exception applies, the sole proprietor needs the business registration, appropriate qualified design responsibility and prescribed insurance. If a salaried employee designs work for their employer without offering design activities to the public, first assess the other-designer rule and exceptions; do not infer automatic individual registration or exemption from the employment relationship alone.

Two exception lists, plus the Act

Section 15.11(8) excludes holders of a licence or certificate under the Architects Act or Professional Engineers Act from ss. 15.11(5) and (6.1). It does not expand their professional scope. Section 8(2)(b.1) remains a separate refusal ground if those professional Acts require an architect, a professional engineer or both and the application lacks the required professional design.

  • Business exceptions: Article 3.2.4.1. includes specified design work for a person’s own building, a house extension, material alteration or repair, and certain house plumbing, HVAC and ancillary building work. It also includes a qualifying registered builder or vendor’s design activity for a home it will construct or sell under the terms of the referenced warranty statute, and work on a sewage system the registered installer will construct. These are business exceptions. They do not by themselves dispose of the other-designer rule.
  • Other-designer exceptions: Article 3.2.5.1. includes construction of a house the designer owns, an ancillary building serving that house or a unit in it, and separately an ancillary building serving a house or a unit in a house with a building area of not more than 55 m² under Clause (3)(j). It also includes specified sewage systems the designer will construct if the designer owns the system or is a registered installer. Read the ownership and work conditions in the actual clause; do not substitute the scope of the House registration class or a permit exemption.
  • Apply the farm limits to the right rule: Both provisions include low-human-occupancy farm buildings with at most two storeys and less than 600 m² of building area. The firm clause additionally excludes Group G, Division 4 agricultural occupancies with no human occupants from this particular exemption.
  • Other listed activities: The two lists address specified tents, signs, site services, pre-engineered elements designed by a person competent in the appropriate discipline, incidental components and a pre-2006 transitional case. Check the exact list: for example, the firm exemption specifically lists certain certified or conforming manufactured buildings and cites a different tent sentence from the other-designer exemption.

Register, insurance and the permit paperwork

Under 3.2.6.1.(2), a firm’s public entry includes its name, identifying number if assigned, business address and classes, plus the names and assigned identifying numbers of the people responsible for its design activities by class. Under Sentence (3), the other-designer entry lists name, assigned number if any and classes. Under 3.2.7., use Table 3.5.2.1. to match a class to the proposed design; the notes address incidental activities in another class.

Act s. 15.13(1) lists registered code agencies and the specified categories under ss. 15.11(5) and (6.1), and allows the Code to specify other persons who construct buildings. Apply the insurance specified by the Code. Subsection 3.6.2. specifies coverage for registered design firms and registered code agencies, not every person who drafts a plan. Section 15.13(2) excepts a builder or vendor as defined in the New Home Construction Licensing Act, 2017 in respect of construction of a building. Section 15.13(5) separately prohibits starting or continuing construction without providing the prescribed information to the CBO if part of it will be undertaken by a specified person required to have insurance under (1). Do not use the unproclaimed change to the s. 15.13(1) cross-reference.

On the provincial application effective February 16, 2026, a firm’s responsible designer provides their individual and firm BCINs on Schedule 1; an other designer provides the required information for their own declaration. An exempt owner-designer states the actual Code basis for exemption instead of claiming another person did the work or borrowing their number. Holders of the specified Ontario architecture or engineering credentials do not have to complete Schedule 1 under its express instructions. This form exception is not permission to ignore any separate professional design or document requirements.

Primary references: Building Code Act, 1992 · 2024 Building Code Compendium, Division C Part 3 · Ontario permit application and schedules (effective February 16, 2026) · Ontario practitioner registration and exam requirements

Test Your Knowledge

A paid contractor produces a complete permit design package for a client’s new coffee shop. Assume no one else will review and take responsibility, no exemption applies, and the professional Acts do not require an architect or engineer. Is the contractor exempt because the fit-up is non-load-bearing?

A

Yes. A business submitting a coffee shop design below 600 m² is exempt.

B

No. The applicable business and designer requirements still apply.

C

Yes. A tenant can claim the owner-designer exemption for the contractor.

D

Yes. A business is exempt if all affected walls are non-load-bearing.

Test Your Knowledge

An owner personally designs a house they own. An independent contractor offers to design a new client-owned house for pay. Both propose the same layout. Who can claim the ownership exception under 3.2.5.1.(3)(b) for those design activities?

A

Both, since the layouts are identical.

B

The contractor, because the client owns the house.

C

Neither, because every permit designer needs a BCIN.

D

The owner for their own design, not the contractor for the client’s design.

Test Your Knowledge

For the provincial application effective February 16, 2026, compare an exempt owner-designer with a licensed Ontario professional engineer responsible for a different project. Which distinction is correct?

A

The owner declares the exemption. The engineer can omit Schedule 1.

B

The owner can omit Schedule 1. The engineer declares the exemption.

C

Both complete Schedule 1 and provide their individual exam results.

D

Both can omit Schedule 1 if they have no registered design firm.

Test Your Knowledge

A registered design business is reviewing its public register entry. Which information does 3.2.6.1.(2) require for the business that is not required for an individual other designer under Sentence (3)?

A

Only the responsible people’s last exam dates and assigned categories.

B

Only the business name, with no details about responsible designers.

C

The business address and responsible designers’ names and assigned numbers by class.

D

The business address and every employee’s private address and licence details.

Sections you finish are checked off in the contents.