8.4 Renovation Performance, Compensating Construction and Substitutions
Key Takeaways
Part 11 classifies construction and occupancy when the work changes major occupancy, including rules for mixed occupancies and the limited one-point credit.
Section 11.4 tests post-work performance against the previous level. Structural adequacy, occupancy, plumbing, sewage and combustible extensions have separate triggers.
Identify the actual compensating construction required by 11.4.3. for the trigger and the adversely affected part or systems.
Section 11.5 conditions differ for listed Part 3, 4, 6 and 8 substitutions versus listed Part 9 and 12 substitutions.
Classify the building and evaluate its performance
If construction will change major occupancy, 11.2.1.1. uses Table 11.2.1.1.-A for the construction index and Tables -B to -N for the hazard index. Apply the multiple-occupancy rules cross-referenced in 11.2.1.2. and check the prohibited combinations referenced in 11.2.1.3. A permitted Group G calculation can use Group F, Division 2 as its basis. A small or medium building facing multiple streets can use the one-point proposed hazard-index credit for Table 11.4.3.4.-A when it has the specified firefighting access and contains no Group B1, Group C or Group F1. The size and construction exclusions in 11.2.1.1.(3) concern the listed Part 2 and Part 3 size articles.
Under 11.4.1.1., the building’s post-work performance cannot be lower. Where the work would reduce it under 11.4.2., carry out compensating construction under 11.4.3. The evaluation of a farm building whose construction permit was applied for before January 1, 2025 may use the applicable 2012 Code requirements as of December 31, 2024.
| Proposed effect | Reduction and required response |
|---|---|
| Inadequate structural support | Under 11.4.2.1., check for a different major occupancy, an occupant load increase over 15%, or a live-load increase from changed use within the same major occupancy, and insufficient framing or support for the proposed dead and live loads. Under 11.4.3.2. support the loads or restrict the affected floor and post the restrictions. |
| Higher occupant load | 11.4.2.2. uses over 15% subject to its sewage cross-references. At 15% or less check whether the new load is more than 15% above the fire-alarm threshold or existing exit capacity. Apply 11.4.3.3. and Table 11.4.3.3. including its Group C provisions and additional construction in the stated case. |
| Change in major occupancy | Under 11.4.2.3., review higher HI or the specified deemed changes, including the Group C suite split, gaming, the specified farm changes, post-disaster or retirement-home use, and unknown previous major occupancy. Check warning/evacuation, separation ratings, combustible construction and the taller Group C trigger with its exception. Under 11.4.3.4. match the trigger to its own work or table, such as increased CI, upgraded separations or sprinklers. |
| Affected plumbing, sewage or extension of combustible construction | 11.4.2.4.–11.4.2.6. test adversely affected plumbing, applicable sewage effects including calculated capacity or prohibited discharge, and an added storey or storeys taking combustible construction above four storeys. Match the response in 11.4.3.5.–11.4.3.7. to Part 7, Part 8 or sprinklers as applicable. |
For example, a change from 100 to 115 occupants is exactly 15%. If existing exit capacity is 96 occupants, the new load is about 19.8% above that capacity. Test that exceedance under 11.4.2.2.(3) and evaluate required work under 11.4.3.3. If there is a sewage system, apply its own capacity test. For the dwelling-unit rule in 11.4.2.5.(3), check added bedrooms, work exceeding 15% of finished area, or added fixtures, together with the calculated flow exceeding any component’s capacity.
Under 11.4.3.1., identify the area being altered, required separations from immediately adjoining areas and above/below floor areas, affected exit systems, and existing systems adversely affected by the work. An index upgrade or a sprinkler can address an identified trigger where prescribed. Follow the actual response for each reduction.
For a change under 11.4.2.3.(1), check the exact clause before applying the construction-index upgrade. Article 11.4.3.4.(1) links Table 11.4.3.4.-A and the minimum construction index to Clauses (a), (b), (c), (d), (e) and (g). A covered retirement-home reduction under Clause (f) has its own sprinkler, voice communication and self-closing door requirements in Sentence (7). Where plumbing is adversely affected, 11.4.3.5. points to upgrading that plumbing under Part 7. More than one reduction can apply on a single project, so check each resulting duty.
Apply the prescribed substitution conditions
Under 11.5.1.1., find the applicable row in Tables -A, -B, -C, -D/E or -F. For a listed substitute for a Part 3, 4, 6 or 8 requirement, the chief building official must be satisfied normal compliance is impracticable due to structural or construction difficulties or is detrimental to the preservation of a heritage building. The same finding is unnecessary for listed Part 9 or 12 substitutes under Sentence (2). Apply the row’s own conditions. If the proposed design does not fit the listed substitute, review the separate evidenced alternative-solution route under Division C Section 2.1 where appropriate.
Primary references
2024 Compendium, Division A · 2024 Compendium, Division B Part 11 · 2024 Compendium, Division B Part 10 · 2024 Compendium, Division C Part 2
After a renovation, the occupant load will rise from 100 to 115. The existing exit capacity under the applicable Article 3.4.3.2. check is 96. What does 11.4.2.2.(3) imply?
Performance is unchanged because the old load increased by exactly 15%.
Performance is reduced because the new load is more than 15% above exit capacity.
Performance is reduced because the new load necessarily changes the hazard index.
Performance is unchanged because the question states no change in major occupancy.
The proposed extension adds a storey to an existing combustible building, taking it from four to five storeys in building height. Which compensating construction follows the reduction under 11.4.2.6.?
Install an extra municipal address sign.
Upgrade only the plumbing in the new storey.
Sprinkler the building under 11.4.3.7.
Post a structural load restriction at the entrance as a substitute for 11.4.3.7.
A designer in a Part 11 project proposes an applicable listed substitute for a Part 9 requirement. What does 11.5.1.1.(2) say about impracticability?
The listed substitute can be used without showing the CBO that normal compliance is impracticable.
The designer must obtain a Minister’s Ruling first.
A CBO finding of impracticability is mandatory for every listed substitute.
The substitute is valid only if it comes from Division C Section 2.1.
An eligible Part 11 renovation uses the one-point credit under 11.2.1.1.(2). The proposed occupancy has a hazard index of 4 before the credit. Which adjustment is correct for the Table 11.4.3.4.-A comparison?
The existing occupancy’s hazard index is decreased by one.
The existing building’s construction index is increased by one.
The proposed occupancy’s hazard index is increased to five.
The proposed occupancy’s hazard index is decreased to three.
Sections you finish are checked off in the contents.