8.2 Change of Use Performance and Compliance Alternatives

Key Takeaways

  • Part 10 requires the post-change performance level to be at least the previous level. Evaluate the independent reduction triggers in 10.3.2.2.

  • Compare the proposed hazard index with both the previous hazard index and existing construction index. A higher hazard index does not reduce performance under that test if it is at most the construction index, subject to the credit rule.

  • Review the independent load, evacuation, residential conversion, fire separation, sewage and retirement-home requirements.

  • Article 10.4.1.1. limits substitutions to listed alternatives and specifies when impracticability or the under-five-year restriction applies.

Last updated: November 2026

Apply the new-occupancy requirements

10.3.1.1. specifies provisions to check for the new major occupancy, subject to Section 10.4. They include high buildings, listed health and safety requirements, pools and spas, and listed Part 9 requirements for room dimensions, windows, guards, egress, plumbing facilities, ventilation and lighting. For conversion to Group B, Division 2, the article requires heating, ventilation and air conditioning to conform to 6.2.1.1.(1). For Group B, Division 3, that cross-reference applies to ventilation, air circulation and filtration. Verify the exact requirements for the actual occupancy.

Under 10.3.2.1., the building after the change must perform at least as well as it did before. For this evaluation, a farm building whose construction permit was applied for before January 1, 2025 may be evaluated against applicable requirements of the 2012 Code as it read on December 31, 2024. The reduction tests are in 10.3.2.2..

Evaluate each reduction test

TestHow to apply the applicable sentence
Structural loading, (1)–(2)Compare proposed dead and live loads with the existing floor and roof framing and supports. For the stated exception, restrict the affected floor to the loading it can support and post signs stating the restrictions.
Early warning and evacuation, (3)Use Table 10.3.2.2.-A for the new occupancy, including its referenced exit/access widths, signs, lighting, alarms, travel distance, exit counts, hotel provision and hardware. Upgrade deficiencies or apply the listed alternatives under the relevant conditions. Check the farm-building note.
Index comparison, (4)–(6)A change to a greater hazard index reduces performance under this test unless the new index is no greater than the existing construction index, subject to the credit provision.
Residential use of combustible construction, (7)–(8)Check whether new construction would require noncombustible construction or construction under 3.2.2.51. or 3.2.2.60. The stated exception requires a sprinklered building no more than six storeys in building height.
Multiple major occupancies, (9)–(10)Check separation between the new and adjoining occupancies using 3.1.3.1., 9.10.9. or Table 10.3.2.2.-B, and the occupancy restrictions in 3.1.3.2. and 9.10.9.14.
Sewage and retirement homes, (11)–(12)Compare calculated sanitary sewage flow to every relevant component’s capacity and check permitted type or amount of wastewater. For conversion to a retirement home, check sprinklers throughout, required voice communication and the stated self-closing door condition.

Suppose the before and after hazard indices are 3 and 4 and the existing CI is 4. The higher hazard index still fits the existing CI, so Sentence (5) can avoid a reduction on that criterion. Check all other reduction tests. Under Sentence (6), a one-point credit can apply to a small or medium existing building facing multiple streets, with qualifying firefighting access, if it contains no B1, C or F1 occupancy. Subtract it from the new hazard index when the conditions are met.

Table 10.3.2.2.-B applies to multiple major occupancies where a major occupancy changes. For example, where normal separation would be 2 hours, the table gives 1.5 hours for the existing building or 1 hour where sprinklered, subject to the applicable provisions. Confirm the normal rating before applying the table.

In a retirement-home change, review the doors to suites and sleeping rooms outside suites. Except for doors leading directly to the exterior, the absence of a self-closing device on a door described in 10.3.2.2.(12) gives a reduction under that sentence. The voice communication check ties to the specific high-building clauses cited in the sentence. These are separate checks from whether the conversion triggers a permit and whether the building’s construction index addresses the hazard index.

Check the conditions on the proposed substitution

Under 10.4.1.1.(1), a listed alternative to the stated Part 3, 4, 6 or 8 requirements can be used where the CBO is satisfied that normal compliance is impracticable because of structural or construction difficulties, or detrimental to preservation of a heritage building. For listed Part 9 or 12 alternatives under Sentence (2), that impracticability showing is unnecessary. Both routes are subject to Sentence (3). The cross-referenced tables are the authorized list. Verify the specific provision and row conditions.

For a building in existence for less than five years, Sentence (3) limits alternatives to requirements referenced in 10.3.2.2.(3), (5) and Table 10.3.2.2.-B. An owner’s difficulty changing a component does not supply an unlisted alternative. Where considering a different Code compliance route, identify its own authority and documentation requirements.

Primary references

Building Code Act, 1992 · 2024 Compendium, Division A · 2024 Compendium, Division C Part 1 · 2024 Compendium, Division B Part 10 · 2024 Compendium, Division B Part 11

Test Your Knowledge

The hazard index rises from 3 to 4 and the existing construction index is 4. No credit is needed. What is the conclusion under 10.3.2.2.(4) and (5)?

A

The project automatically satisfies all of Part 10.

B

The increase requires sprinklers under every provision.

C

There is no reduction under this index test, and the other performance criteria still need review.

D

The permit is waived because the proposed index equals the construction index.

Test Your Knowledge

A small existing building faces multiple streets and has qualifying firefighting access but contains Group C residential occupancy. Can it claim the 10.3.2.2.(6) hazard-index credit?

A

No. The Group C occupancy disqualifies the building for this credit.

B

Yes. Multiple streets alone qualify it.

C

Yes, if it contains no Group B, Division 1 occupancy.

D

Yes, because the rule excludes only large buildings.

Test Your Knowledge

A qualifying multiple-major-occupancy change is reviewed under Table 10.3.2.2.-B. If the usual separation is 2 hours, what alternative rating does the table give for the sprinklered case?

A

30 minutes.

B

45 minutes.

C

1.5 hours.

D

1 hour.

Test Your Knowledge

For an existing building more than five years old, a proposed alternative is listed under 10.4.1.1.(1) for a Part 3 requirement. What must be established before substitution?

A

The CBO is satisfied that normal compliance would delay the project or cost more than the substitute.

B

The CBO is satisfied that normal compliance is impracticable due to structural or construction difficulties, or is detrimental to the preservation of a heritage building.

C

The CBO is satisfied that a building of the same age in any municipality used the proposed substitute.

D

The CBO is satisfied that the approved existing use and original materials will remain unchanged.

Sections you finish are checked off in the contents.