4.1 Inspection Notices and Fire Department Approval

Key Takeaways

  • Under s. 10.2 and Division C Article 1.3.5.1., the permit holder gives prescribed readiness notices to the chief building official or the registered code agency appointed for the relevant work.

  • Article 1.3.5.3. generally allows two countable days, five for the specified sewage notices and ten for the deferred-development-charge occupancy notice.

  • Count from the day after notice is given, excluding Saturdays, holidays and days the principal authority’s office is closed for public business.

  • Local notices under Article 1.3.5.2. depend on an instrument under s. 7(1)(e). Check that instrument for its inspection period.

  • If the municipality has assigned the fire chief as inspector for the relevant Code rules, Article 1.3.4.1. normally requires that inspector’s approval of the construction drawings.

Last updated: November 2026

Identify the duty holder and notice

Section 10.2 of the Building Code Act, 1992 requires notice at prescribed stages and an inspection within the prescribed period. The permit holder gives notice under Division C Article 1.3.5.1. The recipient is the chief building official (CBO) or the registered code agency (RCA) appointed in respect of the construction to which the notice relates. The inspector or agency carries out the prescribed inspection. A question can give you the correct stage and still require you to identify who gives, receives or acts on the notice.

Work in the questionProvincial stages in Article 1.3.5.1. to look for
Footings and foundationReadiness to construct footings, then substantial completion of footings and foundation before backfill
Framing and mechanical systemsSubstantial completion of framing and heating and air-conditioning ducts and pipes for Part 9. For other buildings, use the separate framing and mechanical rough-in clause.
Envelope and fire protectionSeparate stages for substantial completion of insulation and vapour barriers, air barrier systems, fire separations and protection systems, and fire access routes
PlumbingReadiness for inspection and testing of the systems listed in clause (i), and substantial completion of standalone plumbing before backfill
Specified pools and spasCheck the outlets and suction piping stage and the circulation system and pool completion stage before first filling.
SewageReadiness to construct under clause (l), then substantial completion of installation before backfill under clause (m)
OccupancyCheck clauses (o) and (p) for the listed occupancy components, and clause (q) for components required under the deferred-development-charge rule.

A principal authority may require additional notices from the permit holder for one or more stages listed in Article 1.3.5.2. under an instrument made under s. 7(1)(e). Examples include substantial completion of exterior cladding or site grading, or availability of as-constructed drawings. Verify the instrument and its inspection period. The provincial period in Article 1.3.5.3. addresses notices under Sentence 1.3.5.1.(2). 2024 Building Code Compendium, Division C Part 1

Select and count the inspection period

Provincial notice under 1.3.5.1.(2)Latest inspection period in 1.3.5.3.
Ordinary prescribed building stage, such as framingTwo days
Sewage system stage in clause (l) or (m)Five days
Deferred-development-charge occupancy stage in clause (q)Ten days

Article 1.3.5.3. uses days after receipt and directs counting to begin the day following the day notice is given. Exclude Saturdays, holidays and other days when the principal authority’s offices are closed to the public. If valid notices are given and received on Tuesday with no holidays and the offices closed on weekends, Wednesday and Thursday are the first two countable days. Friday is day three, the following Monday day four and the following Tuesday day five. Continue to Tuesday of the week after that for day ten. The inspector or RCA may consider compliance reports and may choose to inspect using means other than physical attendance. A permit holder cannot substitute their own inspection method.

Distinguish a missed inspection deadline from approval. A missed deadline does not establish that concealed work complies. Section 13(6) gives the CBO or RCA a separate uncovering power where there is reason to believe the work is noncompliant and one of the listed conditions applies. Those conditions include covering before the prescribed inspection period elapsed, and cases where the required notice was never received. A timing dispute under s. 10.2(2) can go to the Building Code Commission through s. 24(1)(c). Building Code Act, 1992, ss. 10.2, 13 and 24

For construction of sewage systems by a specified person, BCA s. 15.12(3) and Division C Article 1.3.5.4. also require prescribed information before construction starts. Look for the registered person and qualifying supervisor details cross-referenced to Sentence 3.3.4.1.(2) and the registered person’s contact representative. Giving that information does not replace a readiness notice.

Distinguish fire drawing approval from site inspections

Under Article 1.3.4.1., a municipality can assign specified Code fire-safety enforcement responsibilities to an inspector who is its fire chief. While the assignment applies to the project, the CBO needs the inspector’s approval of the submitted drawings for the assigned portion before issuing the construction permit. If an RCA is appointed for that building under s. 4.1(4)(a) or (c), the municipality cannot make that assignment and an existing assignment for the building is cancelled on appointment. Both clauses include pre-permit functions. A post-permit-only appointment under clause (b) is a different fact pattern. 2024 Building Code Compendium, Division C Part 1

Test Your Knowledge

A valid framing notice and a valid sewage pre-backfill notice are both given and received on Tuesday. There are no holidays and the principal authority’s offices are closed on Saturday and Sunday. When are the respective inspections due?

A

Wednesday and Friday

B

Friday and Monday

C

Thursday and the following Tuesday

D

Thursday and Thursday

Test Your Knowledge

Which prescribed inspection period applies to the notice under Division C Clause 1.3.5.1.(2)(q)?

A

Ten countable days

B

Five countable days

C

Two countable days

D

One calendar month

Test Your Knowledge

A municipality assigned its fire chief, who is an inspector, specified Code fire-safety review for a proposed building. An RCA is then appointed for the same building under s. 4.1(4)(a). What happens to the assignment for that building?

A

It continues until the construction permit issues.

B

It stays in force because an agency has only post-permit powers under clause (a).

C

It continues and the two reviewers must sign every drawing.

D

It is cancelled on the date of the appointment.

Test Your Knowledge

A site grading notice is required solely by a local instrument under s. 7(1)(e). Which source should you check to determine whether the authority prescribed a period for that additional inspection?

A

The provincial ten-day occupancy inspection provision

B

The applicable local by-law, resolution or regulation

C

The permit review periods in Table 1.3.1.3.

D

The annual maintenance inspection report